Cost treatment principles for material demobilization, inter-project transfers, and remaining inventory on construction projects

Demobilization: issued amounts already costed are reversed via red-letter return slips; turnover materials transfer back only at unamortized net book value; transfers: transferor reverses, transferee records—at book actual cost / planned cost + variance / internal settlement price; external sales go through other operating income/expense; remaining inventory: carried as inventory at actual cost, not into current costs; inventory gains/losses on count are routed through "pending property gains and losses" into current profit/loss after cause determination; at completion achieve "work done, materials cleared, site clean."

Applicable Codes

  • 国发〔1984〕34号 国营企业成本管理条例
  • 财会字〔1993〕2号 施工企业会计制度
  • GB/T 50326-2017 建设工程项目管理规范
  • GB/T 50500-2024 建设工程工程量清单计价标准
  • T/ZBD 100.4-2023
  • GB 50755-2012 钢结构工程施工规范
  • TB/T 10821-2024 铁路工程基本定额

Topic Positioning

Cost treatment rules for three types of events in construction project materials—demobilization (returns to store/supplier), inter-project transfers, and remaining inventory (period-end counting/completion closeout): clarifying what goes into cost, what reverses cost, and what is merely inventory, to prevent inflated project costs and final account disputes from inconsistent bases.

Core Conclusions

General principles: actual cost + accrual basis, cost accumulation synchronized with physical progress (GB/T 50326-2017 11.4.3).

  1. Material demobilization: amounts issued and already costed must be reversed (red-letter) against current material cost. Surplus returns are reversed via return slips; returns of non-conforming or wrongly purchased materials reverse procurement cost, with return freight and handling charges charged to project on-costs (indirect costs); turnover materials transfer back only at the unamortized portion (net book value = original value - accumulated amortization; amortization rules per TB/T 10821-2024 Chapter 9); the amortized portion stays in cost.
  2. Material transfers: transferor reverses, transferee adds, both parties at the same valuation basis. Three valuation modes: book actual cost (under the already-selected FIFO/weighted average/moving average/specific identification—fixed once chosen); planned cost with simultaneous carryover of material cost variances; internal settlement price (with a management fee markup and internal profit when independently accounted). Transfer freight and handling charges are borne by the transferee. External sale of surplus materials is not an internal transfer—recognise as "other operating income" and carry over the cost of sales.
  3. Remaining inventory: normal period-end stock is carried as inventory at actual cost, not into current costs—costed upon issue; inventory gains/losses on count are first recorded under "pending property gains and losses," then after cause determination: gains offset administrative expenses; management-caused losses go to administrative expenses, natural disasters to non-operating expenses, responsible-party or insurance compensation to other receivables; at completion, survey and count remaining materials—transfer what can be transferred, sell off what cannot be used (reversing cost) ("work done, materials cleared, site clean").

Applicable Boundaries

Applies to construction enterprises' project-level material cost accounting and final account; free-issue materials (by the employer) must follow the contract basis—actual consumption = issued quantity - stock quantity; surplus must be returned or clawed back per agreement; over-issue/over-consumption liability per GB/T 50500-2024 3.6.3; planned-cost/internal-settlement accounting follows company policy. Not covered: price inquiry, procurement comparison, specific values for the number of reuses (amortization cycles) (see dedicated cards).

Further Reading

  • Guo Fa [1984] No. 34 Regulation on Cost Management of State-owned Enterprises; Cai Kuai Zi [1993] No. 2 Accounting System for Construction Enterprises (inventory valuation, other operating income/expense accounts)
  • GB/T 50326-2017, 11.4.3 cost accounting, 14.4.4 material assessment
  • GB/T 50500-2024 (China national pricing standard for BOQ), 3.6.3 over-issue/over-consumption liability for employer-supplied (free-issue) materials
  • T/ZBD 100.4-2023 construction cost expert assessment (judicial appraisal): return and clawback of surplus free-issue materials (by the employer); GB 50755-2012 5.7.5 turnover material demobilization reconciliation
  • Material consumption statistics and wastage rates: T/CBDA 61-2022 8.2.2 (receipt/issue/stock/scrap data); TB/T 10821-2024 appendix (material handling and operation wastage rates)