Suspended (cradle) scaffold pricing by applying quota line items for exterior insulation/painting on non-railway works: dedicated sub-item first; substitution and actual-cost-based paths where none exists

For exterior insulation/painting baskets on non-railway building works: (1) where a dedicated item exists (Hunan 2025 "suspended basket", Shaanxi "exterior-decoration basket"), apply it directly — measured by covered projected area, no deduction for door/window openings; (2) where no dedicated item exists (e.g., Beijing 2021/2024), apply the corresponding eaves-height item of the decoration external scaffold, or — where the scheme adopts baskets — charge the electric-basket cost (rental + assembly/disassembly) as incurred into the measures cost; (3) no duplicate charging against the comprehensive/decoration external scaffold; assembly and disassembly are included and not charged again. Beijing workmanship code DB11/T 1832.10-2022 endorses basket construction for real-stone paint, but pricing still follows path (2).

Applicable Codes

  • T SZCA 5-2022
  • GB 50500-2013
  • DB11/T 1832.10-2022 建筑工程施工工艺规程 第10部分:装饰装修工程

Topic Positioning

Quota-application decisions for suspended-basket construction of exterior insulation and painting on local building/decoration works: dedicated item first; substitution or charging as incurred where none exists; and duplicate-charging traps.

Core Conclusions

The basket falls under measures items - scaffolds, with three application paths: (1) where a dedicated item exists (Hunan 2025 "suspended basket", Shaanxi "exterior-decoration basket"), apply it directly — measured by covered projected area, no deduction for door/window openings, generally without work-type breakdown (the railway FY series, by contrast, is graded by work type). (2) Where no dedicated item exists (e.g., Beijing 2021/2024): apply the corresponding eaves-height item of the decoration external scaffold; where the scheme adopts baskets, charge the electric-basket cost (rental + assembly/disassembly) as incurred, per the T SZCA 5-2022 general provisions and by reference to GB 50500-2013, into the measures cost. (3) The basket must not be charged duplicatively with the comprehensive/decoration external scaffold; assembly/disassembly and material handling are included in the item and not charged again.

Applicable Boundaries

Applies to non-railway building decoration works; railway building works apply the FY series of TB/T 10831-2024 Volume 10. Beijing has a workmanship basis (DB11/T 1832.10-2022: exterior real-stone paint should use basket construction) but still no dedicated pricing item — handle per path (2). Item numbers, eaves-height grades, and fee scopes differ by region; the current quota of the project's locality prevails. Scaffold-conversion fees and baskets are different paths — do not confuse them.

Further Reading

Hunan 2025 consumption-standard scaffold calculation rules; Shaanxi new consumption quota (consultation draft) "exterior-decoration basket"; T SZCA 5-2022 general provisions; GB 50500-2013 special decoration scaffolds; DB11/T 1832.10-2022 Part 10.