Long-auger drilled pumped piles (plain concrete / CFG): pump-first-then-lift coordination — pump before lifting, lift rate set by pumping, continuous placement
Core of pump-lift coordination in long-auger pumped piles: concrete must be pumped to hole bottom and pressurized before lifting the auger; lifting before pumping is strictly forbidden (JGJ/T 419-2018 cl. 5.6.2); auger lifting speed must match pump output — Beijing DB11/T 1832.1-2021 cl. 9.4.5 quantifies the red line as "the concrete valve at the auger stem shall be not less than 4m below the concrete level inside the stem"; placement shall be continuous in one operation, no stopping the pump to await material in saturated sand/silt; the concrete level in the pump hopper shall be not less than 400mm above the hopper bottom (JGJ/T 419-2018 cl. 5.6.3).
Applicable Codes
- JGJ/T 419-2018 长螺旋钻孔压灌桩技术标准(第5.6.2、5.6.3条)
- JGJ 94-2008 建筑桩基技术规范(第6.4.4条)
- DB11/T 1832.1-2021 建筑工程施工工艺规程 第1部分:地基基础工程(第9.4.5条)
- SJG 126-2023 桩基施工技术标准(第8.4.3条)
- DBJ 13-07-2006 建筑地基基础技术规范(第9.3.4条)
- DBJ/T 15-152-2019 建筑地基基础施工规范(第16.3.3条)
Topic Positioning
This card covers the coordination of "pumping concrete and lifting the auger" in forming long-auger drilled pumped piles (plain concrete and CFG piles) — operation sequence, quantified red lines and stratum-specific measures, per industry standard JGJ/T 419-2018 and JGJ 94-2008, consolidating several local standards for direct use in disclosure and quality checks.
Core Conclusions
Four iron rules of coordination:
- Never lift before pumping. JGJ/T 419-2018 cl. 5.6.2, original: "The auger may be lifted only after concrete is pumped to the hole bottom and pressurized; lifting the auger before pumping concrete is strictly forbidden." Rationale: lifting first leaves the pile toe loose or voided, impairing or even destroying end bearing — the key quality control of this method.
- Lift speed must match pump output (lift set by pump). JGJ/T 419-2018 cl. 5.6.3: "The auger lifting speed shall match the concrete pump output." DB11/T 1832.1-2021 cl. 9.4.5 quantifies: "the concrete valve on the auger stem shall be not less than 4m below the concrete level inside the stem" — if the head difference drops below 4m (lifting too fast or under-pumping), slow down.
- Continuous placement; no stopping to await material. JGJ/T 419-2018 cl. 5.6.2: "Concrete placement shall proceed continuously until pile concrete is pumped to the design level; avoid shutdowns for lack of material." Stoppings cause broken piles, necking, loose pile concrete and cages not reaching depth; in saturated sand/silt no pump stoppages (DB11/T 1832.1-2021 cl. 9.4.5 and JGJ 94-2008 cl. 6.4.4 double constraint).
- Keep enough concrete in the pump hopper. JGJ/T 419-2018 cl. 5.6.3: "The concrete level in the pump hopper shall be not less than 400mm above the hopper bottom" — prevents air entry, voids and pipe blockage.
Standard per-pile sequence:
- Before first pumping or after long idle, lubricate pipes with mortar (DBJ/T 15-152-2019 cl. 16.3.3; SJG 126-2023 cl. 8.4.3);
- At start, pause 10-20s under pressure; once the core pipe fills and the bottom valve opens, lift slowly (DBJ/T 15-152-2019 cl. 16.3.3; DBJ 13-07-2006 cl. 9.3.4.8: lift the auger 300-500mm first, pause 10-20s; SJG 126-2023: lift the bit 200-300mm first, pause 10-20s to confirm the bottom valve opens before lifting);
- Pump and lift continuously in one operation, no mid-stop;
- Clear soil from the flights while lifting; after completion clear residual concrete from stem and pipes (DB11/T 1832.1-2021 cl. 9.4.5); concrete standing time in pump and lines must not exceed initial set — otherwise clear stem, pipes and pump.
Quantified indicators (site wall chart):
- Valve below in-stem concrete level: not less than 4m (DB11/T 1832.1-2021 cl. 9.4.5);
- Hopper level above hopper bottom: not less than 400mm (JGJ/T 419-2018 cl. 5.6.3; DBJ/T 15-152-2019 cl. 16.3.3 and DBJ 13-07-2006 cl. 9.3.4.5 same);
- Initial pumping pause: 10-20s;
- Bit lifting speed: preferably not over 2.5m/min (SJG 126-2023 cl. 8.4.3);
- Pump pressure: preferably 6-10MPa (SJG 126-2023 cl. 8.4.3);
- Slump: preferably 180-220mm (JGJ 94-2008 cl. 6.4.4; for long-auger piles add fly ash 70-90kg/m3 and control slump 160-200mm — too high bleeds and blocks, too low flows poorly);
- Coarse aggregate max size: preferably not over 30mm (JGJ 94-2008 cl. 6.4.4); fine aggregate medium-coarse sand, sand ratio 40%-45% (DBJ 13-07-2006 cl. 9.3.4.3);
- Pump-to-rig distance: preferably <=60m; keep lines level and supported for long runs (DBJ 13-07-2006 cl. 9.3.4.4, 9.3.4.6);
- Concrete over-consumption coefficient: shall exceed 1.2 (DBJ 13-07-2006 cl. 9.3.4.10); over-placement above pile top preferably 0.3-0.6m (DBJ 13-07-2006; SJG 126-2023 requires filling the empty bore above pile top to ease cage vibration-insertion);
- Above 30 degrees C, insulate lines (wet straw bags) and spray periodically to prevent water loss and blockage (SJG 126-2023 cl. 8.4.3; DBJ 13-07-2006 cl. 9.3.4.7);
- Keep the rig's vent holes clear during placement (JGJ/T 419-2018 cl. 5.6.3) to prevent air locks and blockage.
Companion quality items: pre-check after rig positioning — bit vs pile point offset <=20mm; slow initial penetration; no reversing or lifting during drilling; stop and investigate upon sticking, shaking, deviation or abnormal noise (DBJ 13-07-2006 cl. 9.3.4.1-9.3.4.2); specimens: one set per rig per day or per 50m3, standard-cured (DB11/T 1832.1-2021 cl. 9.4.5); piles over 1m diameter one set each, >=1 set per placing shift, 3 cubes per set (DBJ 13-07-2006 cl. 9.3.4.12); trial piles recommended to verify geology, plant and parameters (cl. 9.3.4.13).
Applicable Boundaries
- Process: long-auger center-pumped pile forming (plain concrete, CFG, and cage-inserted reinforced piles all apply); per JGJ 94-2008 cl. 6.4.4 the method suits cohesive soil, silt, plain fill above the water table and medium-dense-plus sand — non-displacement, strong penetration, low noise, vibration- and slurry-free.
- Regional notes: the 4m red line is Beijing DB11/T 1832.1-2021 (execute directly in Beijing); 2.5m/min and 6-10MPa are Shenzhen SJG 126-2023; concrete over-consumption coefficient >1.2 is Hebei DBJ 13-07-2006. Cross-region, follow JGJ/T 419-2018, with local details per the project's current standards and design.
- Physics of lift speed: lift speed = pump output / pile cross-section (at fixed output, larger diameter = slower); on site judge directly by the "valve >=4m below concrete level" rule — no computation needed.
- Cage insertion (currently to 20-30m) requires integrated measures for verticality and cover (JGJ 94-2008 cl. 6.4.4).
Further Reading
- JGJ/T 419-2018 cl. 5.6.2, 5.6.3 (pump before lift, matched lifting, vent holes, hopper level);
- JGJ 94-2008 cl. 6.4.4 (slump, aggregate, fly ash, strata, cage insertion);
- DB11/T 1832.1-2021 cl. 9.4.5 (Beijing: 4m red line, specimens);
- SJG 126-2023 cl. 8.4.3 (Shenzhen: pipe lubrication, valve confirmation, 6-10MPa, <=2.5m/min, heat protection);
- DBJ 13-07-2006 cl. 9.3.4 (Hebei: positioning, sand ratio, 60m pump distance, over-placement, specimens, trial piles);
- DBJ/T 15-152-2019 cl. 16.3.3 (Guangdong: mortar lubrication, 10-20s pressurizing, continuous placement, hopper level).
Keywords
- 长螺旋钻孔压灌桩
- 长螺旋压灌素混凝土桩
- CFG桩
- 泵送提钻配合
- 先泵后提
- 连续压灌
- 提钻速度
- JGJ/T 419-2018