Determining the width and pavement structure of on-site temporary roads (construction haul roads)
Width by functional class: double-lane trunk road pavement 6.0~7.0 m (subgrade >= 7.5 m), single-lane lead-in pavement 3.5~4.5 m (subgrade >= 4.5 m) + passing bays (width 5.5~6.5 m, effective length >= 20 m, spacing 100~300 m), fire lane width >= 4 m preferably looped. Structure by usage intensity: heavy-duty zones' entry sections within 200 m hardened with >= 20 cm concrete, general trunk lines with clay-bound gravel/graded crushed stone; with a base course, base thickness >= 15 cm and 25 cm wider each side than the surface.
Applicable Codes
- ZJQ08-SGJB 015-2018 基础设施工地建设施工技术标准
- DB62/T 3160-2019 甘肃省铁路工程绿色施工验收及评价标准
- DB32/T 2618-2023 高速公路工程施工安全技术规范
- DB11/T 1874-2021 道路工程施工安全技术规程
- DB37/T 5143-2019 城市道路工程现场文明施工管理标准
- GB 51282-2018 煤炭工业露天矿矿山运输工程设计标准
- TB 10066-2000 铁路站场道路和排水设计规范
Topic Positioning
Methods for determining the width, alignment, and pavement structure layers of on-site temporary roads (construction haul roads), consolidating current standard calibers across railway, highway, and building industries — directly usable for temporary road scheme preparation.
Core Conclusions
Width classed as "trunk double lane, lead-in single lane + passing bays": double-lane trunk pavement 6.0~7.0 m (subgrade >= 7.5 m); single-lane lead-in pavement 3.5~4.5 m (subgrade >= 4.5 m); passing-bay pavement width 5.5~6.5 m, effective length >= 20 m, spacing 100~300 m. Temporary fire lanes >= 4 m wide, preferably looped; where looping is impossible, provide a 12 x 12 m turning area at the dead end. Alignment: minimum curve radius 15~20 m, maximum longitudinal grade generally <= 8% (12% in difficult sections), continuous descents not over 1000 m; single-lane roads have a 2% single-side drainage slope, double-lane a 2% crown. Structure classed by vehicle type and usage intensity: entry haul roads of extra-large bridges/tunnel portals/mixing stations/precast yards hardened with >= 20 cm concrete within 200 m; general trunk lines use clay-bound gravel or graded crushed stone (minimum standard); clay-bound gravel surface 0.1~0.4 m thick, with base 1.0~1.5 m for large/medium mining trucks and 0.4~1.0 m for small vehicles; on hard rock subgrade no base is needed; maximum particle size <= 2/3 of layer thickness; with a base, base thickness >= 15 cm and 25 cm wider each side than the surface; on soft ground a cushion layer (>= 15 cm) may be set. Ancillary: subgrade compaction, side drainage ditches, culverts at low collection points, without destroying the original water system and flood discharge capacity.
Applicable Boundaries
Applies to scheming on-site temporary roads/haul roads during construction; widths should still be checked against the largest transport vehicle on site, and over-wide/heavy transport (e.g., girder carriers) requires special design. The cited local standards belong to different regions (Gansu/Jiangsu/Beijing/Shandong, etc.) — specific projects prioritize the current rules of the project location; formal roads follow formal road design codes; this card targets temporary roads only.
Further Reading
See ZJQ08-SGJB 015-2018 "Technical standard for infrastructure site construction" Clause 12.2.1 (haul road width, alignment, structure, hardening); DB62/T 3160-2019 "Gansu provincial standard for green construction acceptance and evaluation of railway works" Clause 9.2.7 (railway on-site double/single lane and passing-bay indicators); DB32/T 2618-2023 Clause 6.2.1, DB11/T 1874-2021 Clause 3.0.10 (haul road width and passing bays); DB37/T 5143-2019 Clause 4.4.4 (fire lanes); GB 51282-2018 "Standard for design of mine haul engineering of open-pit mines in the coal industry" Clauses 5.5.1~5.5.5 (clay-bound gravel pavement structure and thickness); TB 10066-2000 "Code for design of railway station yard roads and drainage" Clauses 5.0.5~5.0.9 (base/cushion thickness and construction).