Setting conditions for prime, tack and seal coats on asphalt pavements (tack required, prime advisable / mandatory, lower seal scope) and material selection (slow-breaking spray-type emulsion for prime; fast or medium-breaking emulsion / modified emulsion for tack; modified or rubber asphalt plus pre-coated chips for the lower seal) and spread-rate bases

Interlayer treatment runs: tack coats between asphalt layers, prime coats advisable on all bases, lower seal coats required on semi-rigid bases of expressways (arterials) (CJJ 169-2012 Article 5.3.6); on graded gravel and crushed stone bases and cement, lime and fly-ash stabilised semi-rigid bases, a prime coat must be applied (GB 50092-96 Article 9.1.1). Materials by breaking speed: prime - slow-breaking spray-type emulsified asphalt, or medium / slow-curing liquid asphalt or coal tar, consistency by trial spreading (dense semi-rigid bases - thinner, more penetrating oil; granular bases - thicker); tack - fast or medium-breaking emulsion, or modified emulsion - slow-breaking tack binders run off badly on semi-rigid bases. Spread-rate tables state total liquid asphalt / emulsion including thinner and water, emulsion residue taken at 50%.

Applicable Codes

  • GB 50092-96 沥青路面施工及验收规范 第9.1.1条、第9.1.2条及条文说明
  • CJJ 169-2012 城镇道路路面设计规范 第5.3.6条
  • DB/T 29-74-2018 天津市城市道路工程施工及验收标准 第10.1.2条、第10.2.2条
  • JTG F40-2004 公路沥青路面施工技术规范

Scope of the question

Where the three interlayer treatments of asphalt pavements - prime, tack and seal coats - sit, when they are required or advisable, and which asphalt materials (emulsion breaking speed and grade) each takes.

Core conclusions

1. Setting conditions (CJJ 169-2012 Code for Design of Urban Road Pavements, Article 5.3.6) Asphalt pavement layers shall stay tightly bonded: 1 tack coats between asphalt layers; 2 prime coats advisable on all bases; 3 lower seal coats on semi-rigid bases of expressways and arterials. Commentary: new asphalt layers may take an emulsion spray; over old asphalt or cement concrete pavements and bridge decks, hot or modified asphalt, or modified emulsion, is preferred. The lower seal sits on the semi-rigid base surface, protecting it from construction traffic, aiding curing, keeping rain out and bonding base to surface - commonly modified or rubber asphalt followed by single-size pre-coated chips covering 60-70% of the sprayed area, no more, no overlap; usable also on bridge decks and between surface and middle courses.

2. Mandatory prime (GB 50092-96 Code for Construction and Acceptance of Asphalt Pavements, Article 9.1.1) On graded sand-gravel and crushed stone bases and cement, lime, fly-ash and other inorganically stabilised soil or aggregate semi-rigid bases of asphalt pavements, a prime coat must be applied.

3. Prime materials (GB 50092-96 Article 9.1.2) Prime binder preferably slow-breaking spray-type emulsified asphalt, or medium / slow-curing liquid petroleum asphalt or coal tar, quality per Appendix C Tables C.0.3, C.0.4, C.0.5. Consistency by trial spraying: dense semi-rigid bases take thinner, penetrating oils; graded gravel and crushed stone bases take thicker. Emulsion grade by base type and local climate. DB/T 29-74-2018 Tianjin standard, Article 10.1.2: prime preferably slow-breaking spray-type emulsion and slow-curing liquid asphalt, quality per JTG F40; prime oil grade and rate per Table 10.1.1 (rates are total liquid asphalt / emulsion including thinner and water, emulsion residue at 50%).

4. Tack materials (DB/T 29-74-2018 Article 10.2.2) 1 Tack binders preferably fast or medium-breaking emulsified asphalt or modified emulsion, quality per JTG F40. 2 Tack material grades and rates per Table 10.2.2 (same rate basis - total liquid including thinner and water, residue at 50%). Commentary: practice on semi-rigid bases shows slow-breaking tack binders running off badly - fast or medium-breaking preferred.

5. Anti-pick-up after prime, and its difference from the lower seal (GB 50092-96 9.1.1 commentary) Semi-rigid base surfaces are dense and take little oil - wrong materials run off; abolishing the prime for that reason is wrong and has caused crescent-shaped pushing cracks. Grades and rates are fixed by test per base type. After prime, a thin cover of chips or coarse sand (fine, single thin layer) keeps the emulsion from being picked up by plant and pavers - lightly rolled just to hold. Lower-seal chips follow surface treatment practice with real thickness, choke stone and compaction into a layer of their own.

Applicability limits

  • Strength differs: GB 50092-96 says must apply a prime on graded and semi-rigid bases; CJJ 169-2012 says tack required / prime advisable / lower seal required on expressway and arterial semi-rigid bases. Highway projects also check JTG F40's prime, tack and seal chapters (DB/T 29-74-2018 names JTG F40 as the quality basis).
  • Breaking speed by use: prime slow-breaking (or medium / slow-curing liquid asphalt, coal tar); tack fast or medium-breaking (plain or modified emulsion) - never interchanged.
  • Table rates verify by trial spreading or trial sections; they include thinner and water, residue at 50% - other residue contents convert.
  • Emulsion codes: P spray, B mixing; C, A, N cationic, anionic, non-ionic - cite the source of any rate table.
  • Lower seal and post-prime chip dusting are different things: the former a true layer with thickness, choke stone and compaction; the latter a thin anti-pick-up dusting, not a structural layer.

Further reading

GB 50092-96 Articles 9.1.1, 9.1.2 and the 9.1.1 commentary; Appendix C Tables C.0.3 (emulsified asphalt), C.0.4 (liquid petroleum asphalt), C.0.5 (coal tar); CJJ 169-2012 Article 5.3.6 and commentary; DB/T 29-74-2018 Articles 10.1.2 (Table 10.1.1) and 10.2.2 (Table 10.2.2); JTG F40-2004 prime, tack and seal chapters; CJJ 1-2008 Article 8.1.7 paragraph 1 Tables 8.1.7-2 (emulsified asphalt) and 8.1.7-5 (modified emulsion).