Effect of thickness deviations of road base and surface courses on acceptance conformity and settlement (tolerances, representative-value evaluation, deduction scenarios)
Measurement is by the thickness after compaction (GB/T 50857-2024 Appendix B.6.6); deviations within tolerance (hot-mix asphalt surface course +10 to -5 mm, asphalt macadam base ±10 mm) do not affect settlement; beyond tolerance, the thickness is evaluated by the representative-value method, passing where the representative value is conforming and the single-point pass rate is at least 90%/95%; only where a negative deviation beyond tolerance renders the sub-item non-conforming does re-working or a contract-based deduction follow, positive deviations generally not increasing the price.
Applicable Codes
- CJJ 1-2008 城镇道路工程施工与质量验收规范
- GB/T 50857-2024 市政工程工程量计算标准
- DB/T 29-74-2018 天津市城市道路工程施工及验收标准
- DB22/T 5143-2023 城镇道路薄层罩面技术标准
- DB61/T 5001-2021 城镇道路路面检测与评价技术规程
- JTG 3450 公路路基路面现场测试规程
Topic Positioning
How thickness deviations of road base courses and asphalt surface courses affect acceptance conformity and settlement - answering "does thinner or thicker mean a deduction?"
Core Conclusions
Measurement is uniformly by the thickness after compaction (GB/T 50857-2024 Appendix B.6.6). Tolerance red lines: hot-mix asphalt mixture surface course +10 to -5 mm, asphalt macadam base ±10 mm (CJJ 1-2008 clauses 8.5.1/7.8.5, master-control items). Beyond tolerance, the thickness is evaluated by the representative value: representative value = mean - t(alpha) x standard deviation / sqrt(n) (90% confidence for surface courses, 95% for base courses); the item passes where the representative value is not less than the design thickness minus the tolerance and the single-point pass rate is at least 90% (base courses, and surface courses of secondary trunk and access roads) or at least 95% (surface courses of expressways and arterial roads) (DB/T 29-74-2018 Appendix H). Settlement by scenario: deviations within tolerance do not affect settlement (priced by design area x design thickness against the quota line items, with no adjustment for either positive or negative deviation); only where a negative deviation beyond tolerance renders the sub-item non-conforming does re-laying follow (at the contractor's cost) or concessionary acceptance with a deduction in proportion to the measured thickness, the deduction rules following the contract; positive deviations generally do not increase the price; where the contract agrees measurement by the measured thickness (buy-back / price-audit type projects), the core-drilling test report directly determines the amount.
Applicable Boundaries
The tolerance values apply to conventional hot-mix asphalt mixture surface courses and asphalt macadam base courses; thin overlays follow DB22/T 5143-2023, the thickness tolerance being -20% of the design value (the dedicated standard is more lenient and takes precedence); core-drilling thickness measurement follows JTG 3450 (T 0912), the core holes being backfilled and compacted with the same material. Deduction percentages and concessionary-acceptance procedures belong to the contract; this card gives no specific values. Compaction is separately controlled at not less than 96% for expressways and arterial roads and not less than 95% for secondary trunk roads and below (surface courses).
Further Reading
CJJ 1-2008 clause 8.5.1 (surface-course inspection: compaction, thickness and deflection as master-control items), clause 7.8.5 (base course compaction not less than 95%); GB/T 50857-2024 Appendix B.6.6 (thickness after compaction); DB/T 29-74-2018 Appendix H (representative-value evaluation and pass-rate thresholds); DB61/T 5001-2021 clause 4.1.5 (core-drilling thickness measurement); DB22/T 5143-2023 clause 7.2.3 (thin-overlay inspection). For process control, combine with the loose-laying (compaction) coefficient card for asphalt mixtures (determined on trial sections, checked at all times) to keep deviations within tolerance.
Keywords
- 厚度偏差
- tolerance (permissible deviation)
- 路面厚度
- 厚度代表值
- 结算
- 压实后厚度
- 热拌沥青混合料
- 薄层罩面