Core-count selection between single-core and three-core cables, bracket arrangement patterns (trefoil / flat) and the permitted tier rules: GB 50217-2018 clauses 3.5.3 and 5.1.4, GB 50168-2018 clause 6.4.3, and single-core cable layout requirements for rail transit
For three-phase circuits from 3kV to 35kV, 3-core cable shall be selected except where the working current is large or the route is laid underwater, in which cases single-core may be used. The single-core cables of one AC circuit may be laid in trefoil (cloverleaf) formation; except for the single-core case, power cables should keep a gap of one outer diameter between each other, and multiple power cables of one important circuit should not be stacked. Three-core AC cable should not exceed one tier on ordinary brackets and hangers, or two tiers in trays, while single-core AC cable shall be arranged on brackets on the same side and fixed with restraints; in close trefoil formation, apart from the fixing positions, the cables shall be bound tight with clamps or straps at intervals, and in cable tunnels single-core cable must be fixed (short-circuit electrodynamic forces can shift and damage long lengths). For medium-voltage ring networks (three-phase AC), single-core cable should be trefoil; DC should be flat (in-line); control cables may be close-packed or stacked in tiers.
Applicable Codes
- GB 50217-2018 · Standard for Design of Cables of Electric Power Engineering 第3.5.3条、第5.1.4条
- GB 50168-2018 · Standard for Construction and Acceptance of Cable Lines in Electric Equipment Installation Engineering 第6.4.3条
- CJJ/T 256-2016《中低速磁浮交通供电技术规范》第6.2.1条
- DB23/T 3336-2022《悬挂式单轨交通技术标准》第15.4.3条
Topic positioning
Whether a three-phase circuit takes a 3-core cable or three single-core cables, and, once single-core is chosen, the arrangement on one tier of bracket (trefoil, flat) and the permitted number of tiers. These are design and construction code rules; they drive bracket tiers, clamping and binding, tier spacing and space reservation, and run on a separate track from the core-count conversion factors in quota pricing (the quota sees core count only, not layout).
Core conclusions
1. Core-count selection (3kV to 35kV three-phase circuits)
GB 50217-2018 clause 3.5.3:
'1 For circuits with large working currents, or where cable is laid underwater, single-core cable may be selected; 2 except in the case of item 1 of this clause, 3-core cable shall be selected; the 3-core cable may be of the ordinary belted type, or of the type built up from three single-core cables twisted together.'
The commentary gives the pros and cons of single-core (including twisted 3-core) against ordinary belted 3-core: three single-core cables cost more than one ordinary 3-core cable, but (1) at terminations in switchgear and panels they reduce or avoid crossing and give wider electrical safety clearances, easing installation; (2) on long routes they reduce or eliminate cable joints and improve operational reliability; (3) ampacity is about 10% higher, which can drop the cross-section selection by one step; (4) once an earth fault occurs it is difficult for it to develop into a phase-to-phase short circuit; (5) the permissible bending radius is smaller, easing the laying of large-section cables. The twisted 3-core type (three single-core cables helically wound at a pitch or bound at intervals into one body) combines the single-core advantages with the simpler laying and similar cost of belted 3-core.
2. Arrangement on one tier of bracket
GB 50217-2018 clause 5.1.4:
'1 Control and signal cables may be close-packed or stacked in tiers; 2 apart from the same circuit of single-core power cable in AC systems, which may be laid in trefoil (cloverleaf) formation, multiple power cables of one important circuit should not be stacked; 3 except for single-core cable in AC systems, power cables should keep a gap of one cable outer diameter between each other.'
Key points: the trefoil exemption is granted only to the same circuit of single-core AC cable; multicore power cables such as 3-core in one important circuit should not be stacked, and except for the single-core case a gap of one outer diameter applies between cables.
3. Tier limits and single-core fixing (construction acceptance side)
GB 50168-2018 clause 6.4.3:
'1 Control cables on ordinary brackets should not exceed two tiers; on trays not more than three tiers. 2 Three-core AC power cable on ordinary brackets and hangers should not exceed one tier; on trays not more than two tiers. 3 Single-core AC power cable shall be arranged on brackets on the same side and shall be restrained and fixed. When laid in close trefoil (cloverleaf) formation, apart from the fixing positions, the rest shall be bound tight with cable clamps or straps at certain intervals to prevent loosening. In cable tunnels single-core cable must be fixed. Under a short-circuit fault, the electrodynamic action between single-core cables produces mutual repulsion that can shift a very long length of cable off the brackets and damage the cable.'
That is: three-core cable has clear tier caps (no more than 1 tier on ordinary brackets and hangers, 2 in trays), while single-core cable is governed not mainly by tier count but by 'brackets on the same side + restrained fixing + trefoil binding + mandatory fixing in tunnels'. This drives bracket tiers, widths and clamp counts and should be reflected in the method statement and the preliminaries.
4. Layout pattern tied to system type and setting
- CJJ/T 256-2016 clause 6.2.1: where single-core cable is used, medium-voltage ring network power cable should preferably be laid trefoil, traction DC power cable flat, and control cables close-packed or stacked in tiers. Commentary: medium-voltage ring networks are three-phase AC cable, and trefoil layout balances the three-phase magnetic field best; traction DC cable has no field-balance issue and carries large current, so flat layout helps heat dissipation and cable protection; control cables carry very small currents, need no heat relief and are many and small in section, so packing and stacking save space. The same clause adds a selection preference: in rail transit stations, where laying space is limited, power cables of 185mm2 and above are bulky and hard to lay as multicore cable and should use single-core.
- DB23/T 3336-2022 clause 15.4.3: where the medium-voltage ring network power cable is single-core, trefoil layout should be used; low-voltage DC power cable should be laid flat (in-line).
Pattern in short: three-phase AC (medium-voltage ring) single-core -> trefoil (cloverleaf); DC (traction / low-voltage DC) -> flat / in-line; control cable -> close-packed or stacked in tiers.
Applicability boundaries
- This card states design and construction acceptance code rules and does not address quota conversion: cable laying quota line items apply factors by laying method, cross-section and core count only; no extra factor accrues for trefoil or flat layout, and fixing materials such as cable cleats and hangers are already inside the laying line items.
- The tiers in clause 6.4.3 are expressed as 'should not' - recommended control values that can be exceeded under special conditions (confined space, design confirmation), but with technical and acceptance records kept.
- The laying line items are compiled for plain-terrain and in-plant cable construction conditions and do not fit waterlogged ground, underwater or pit-bottom work; core-count selection for underwater laying follows GB 50217-2018 clause 3.5.3 item 1.
- Single-core cable in AC systems raises induced voltage in metallic sheaths, earthing and eddy-current issues that need separate checking (outside the evidence scope of this card; consult the relevant provisions of the design codes).
- The rail transit (maglev, monorail) provisions are industry or local standards and are cited only within their scope of application.
Further reading
- GB 50217-2018 'Standard for Design of Cables of Electric Power Engineering' clause 3.5.3 (core-count selection for 3kV to 35kV three-phase circuits and commentary), clause 5.1.4 (cable arrangement on one tier of bracket).
- GB 50168-2018 'Standard for Construction and Acceptance of Cable Lines in Electric Installation Engineering' clause 6.4.3 (laying on brackets, tiers, single-core fixing).
- CJJ/T 256-2016 'Technical Specification for Power Supply of Medium and Low Speed Maglev Transit' clause 6.2.1 (single-core cable layout and commentary).
- DB23/T 3336-2022 'Technical Standard for Suspended Monorail Transit' clause 15.4.3 (medium-voltage ring trefoil, low-voltage DC flat).
Keywords
- 单芯电缆
- 三芯电缆
- 品字形排列
- 一字形布置
- 电缆支架层数
- 芯数选择
- GB 50217
- GB 50168