Code requirements for factory welding of civil air defence door frame anchorage hooks and erection lifting hooks, the installation sequence, the structural reinforcement of door frame walls, and the door leaf commissioning accessories (sealing strips, removable thresholds)
Anchorage hooks of civil air defence doors must be welded in the factory and delivered together with the door frame; welding on site is not permitted (DB23/T 2934-2021 clause 3.0.4; site welding stresses and distorts the frame and offers no conditions for second-time re-alignment). Installation must strictly follow the sequence 'set the door frame -> tie the reinforcement -> cast the concrete monolithically'; tying the reinforcement first causes interference between the anchorage hooks and the bars at the frame so the door cannot be installed (clause 3.0.5). Door frame wall construction follows DBJ/T 36-054-2019 clause 4.6.3: main bars no less than 12mm diameter, spacing no more than 250mm, reinforcement ratio no less than 0.25%, two d16 diagonal bars on the inner and outer faces at each of the four corners of the door opening with length no less than 1000mm, door frame thickness no less than 300mm, the steel door frame integral with the door frame wall, and the door frame and its erection lifting hooks designed and constructed simultaneously; hook material and anchorage length are checked against the civil air defence door design drawings (standard detail atlases) and must not be copied from rules of thumb for general embedded steel.
Applicable Codes
- DB23/T 2934-2021 人民防空工程防护设备安装技术规程 第3.0.4、3.0.5、5.4.4、5.4.6条
- DBJ/T 36-054-2019 江西省城市地下综合管廊兼顾人防工程设计导则 第4.6.3条
- https://www.guanshanhu.gov.cn/zwgk/zdlyxx/rmfk/202304/t20230410_78979099.html
Topic positioning
Anchorage hooks, erection lifting hooks and removable thresholds on civil air defence doors (protective airtight doors and airtight doors) are not loose items 'left to the civil contractor on site': their welding location, installation sequence, door frame wall reinforcement and door leaf commissioning are all constrained by regulations, and this is also the technical premise for judging whether the cost of the accessories belongs to the door item or to the builder's rebar and embedded steel. This card gives the factory-welding requirements for anchorage hooks, the correct sequence, the structural reinforcement of the door frame wall, and the essentials of door leaf commissioning.
Core conclusion
1. Anchorage hooks must be welded in the factory and delivered with the door frame DB23/T 2934-2021 clause 3.0.4, original text: 'Anchorage hooks of civil air defence doors shall be welded in the factory and delivered together with the door frame; welding on the construction site is not permitted. The spacing of the anchorage hooks and the welding requirements shall comply with the civil air defence door design drawings.' The commentary's reasoning: welding the hooks to the door frame induces stress distortion in the frame, and after hook welding the frame must be re-aligned a second time to guarantee frame flatness, for which site welding offers no conditions. -> No anchorage-hook fabrication or welding work quantity arises on site; its cost belongs to the finished protective equipment package, and no separate site embedded-steel fabrication item may be listed.
2. Installation sequence: door frame first, then rebar tying, then monolithic casting DB23/T 2934-2021 clause 3.0.5: 'Installation of civil air defence doors shall strictly follow the sequence of setting the door frame, tying the reinforcement, and casting the concrete monolithically.' It also notes: if the contractor ties the door frame wall reinforcement first, the anchorage hooks of the civil air defence door frame interfere with the bars at the frame and installation becomes impossible. -> In sequencing, door frame installation must come before reinforcement tying for the frame wall; a mis-sequenced civil-and-erection interface is a common rework point.
3. Structural reinforcement of the door frame wall and simultaneous design of the lifting hooks DBJ/T 36-054-2019 clause 4.6.3 for the door frame walls of reinforced concrete flat-slab protective airtight doors: 1 The main bars of protective airtight door frame walls shall be no less than 12mm in diameter, with spacing preferably no more than 250mm and a reinforcement ratio no less than 0.25%; 2 Two diagonal bars of 16mm diameter shall be provided on the inner and outer faces at each of the four corners of the protective airtight door opening, each no less than 1000mm long; 3 The door frame thickness of protective airtight doors shall be no less than 300mm; 4 The steel door frame of a protective airtight door and the door frame wall shall be made integral; 5 The door frame of a protective airtight door and its erection lifting hooks shall be designed simultaneously and constructed simultaneously. -> Item 5 is the constructional basis for 'lifting hooks detailed together with the door frame': the hooks are positioned at design stage together with the frame and the frame wall bars, so there is no lawful basis of 'hooks not drawn, welded freely on site'; where the hooks are detailed on the structural rebar drawings, their quantity follows the member rebar basis and is not listed again as embedded steel.
4. Source of the material and anchorage lengths of lifting hooks and anchorage hooks At regulation level the only rule is 'compliance with the civil air defence door design drawings' (DB23/T 2934-2021 clause 3.0.4). The specific material and build-in lengths must be taken from the civil air defence door design drawings or the clauses of the standard detail atlas adopted, checked one by one; they must not be copied from general embedded-steel constructions (such as generic rules of thumb for anchor-bar lengths).
5. Door leaf installation, commissioning and accessories (sealing strips, removable threshold, hardware)
- Sealing strips: DB23/T 2934-2021 clause 5.4.4 requires sealing strips to be installed and fixed securely during commissioning, so that after closing the door leaf fits evenly against the door frame and at the mid-leaf joint; strip joints shall use 45-degree bevel splices avoiding curved bends, a single-leaf door shall have no more than 2 strip joints and a double-leaf door no more than 6, and T-joints at the mid-seam shall be made in one piece with a mould; the strips of the removable thresholds of protective airtight doors and airtight doors shall be fitted per the drawings; sealing plates shall be fixed securely, and after closing the pressure strips on all sealing faces shall be centred in the groove.
- Commissioning quality: clause 5.4.6 requires that parts be undamaged and that sealing strips, sealing plates, valve rubber pads and buffer pads show no dry cracking or peeling; after commissioning the leaves open and close flexibly, run smoothly, look tidy and carry complete markings; for doors with a removable-threshold function, the removable threshold shall be trial-installed after hanging the door leaf and removed and kept properly only after passing acceptance; the screw holes on both sides of the door frame shall be plugged with grease and cotton yarn, and the holes of the bottom frame with grease and flat-head screws; after the hinge and locking mechanisms are commissioned, shims under the lock seats shall be added or removed so the door leaf fits the frame tightly and the lock heads load evenly; the installation tolerances for steel removable-threshold civil air defence doors, steel no-threshold civil air defence doors and metro running tunnel doors shall follow Table 5.4.6 of that regulation where the design is silent. -> Removable thresholds, sealing strips and locking parts are door leaf commissioning accessories, and their value follows the finished door or door item - a different pricing axis from 'embedded steel charged separately'; the two must not be mixed in one list.
Applicable boundaries
- This card gives constructional and sequencing requirements, not differences of quota line-item content between regions; cost allocation still follows the work content and material columns of the quota line items applied.
- Hook spacing, welding process and tolerance values must follow the design drawings and the chosen atlas; this card gives only the clause basis that 'the design drawings govern' and the reinforcement minimums of the door frame wall.
- Clause 4.6.3 comes from the guide for urban utility tunnels doubling as civil air defence works and applies to utility-tunnel door frame walls; door frame walls of ordinary underground civil air defence works must be checked against the corresponding design codes and atlases - the values point the same way but must not be copied across types.
- The Table 5.4.6 tolerances must be read from the original table of the regulation; values are not listed here.
Further reading
- DB23/T 2934-2021 'Technical regulation for installation of protective equipment in civil air defence works': chapter 3 basic provisions, clauses 3.0.4 and 3.0.5; section 5.4 installation and commissioning of civil air defence doors, clause 5.4.4 (Fig. 5.4.4 strip installation on removable-threshold doors), clause 5.4.6 and Table 5.4.6 installation tolerances for steel door leaves.
- DBJ/T 36-054-2019 'Jiangxi guide for design of urban utility tunnels doubling as civil air defence works', clause 4.6.3, Fig. 4.6.3-1 door frame wall reinforcement, Fig. 4.6.3-2 corner reinforcement at door openings.
- Constructional details of door frames, anchorage hooks and lifting hooks in the standard detail atlases and design drawings for civil air defence doors (material and build-in length per the atlas and drawings).
- Public information page of the civil air defence authority (source link): https://www.guanshanhu.gov.cn/zwgk/zdlyxx/rmfk/202304/t20230410_78979099.html
Keywords
- 人防门
- 锚固钩
- 门框墙配筋
- 安装工序
- 活置门槛
- 密封胶条
- 防护设备安装
- 安装允许偏差