GB/T 50856-2024 cable installation BOQ code (030409) and the billing attribution of adjacent items: 030408 is trolley wire installation, the billing routes for protective conduit, cable trays and wireways, and branch boxes, the definition of laying methods, and how the BOQ 'single-run extended metres' maps to the quota-side rate build-up banded by cross-section and core count
Under the current GB/T 50856-2024, cable installation is Table D.9.1, code 030409; 030408 is 'trolley wire installation' (Table D.8.1). The 2013 edition codes 030408 = cable installation and 030411 = conduit and wiring were repealed when Appendix D was renumbered in the 2024 edition, so carrying over the old codes constitutes a BOQ error. In Table D.9.1 power cables and control cables are measured in m, calculated as the total single-run length shown on the design drawings plus the reserved length (reservations and additions per Table D.17.3-5). The notes to Table D.9.1 make clear: cable protective conduit at building entries is billed as 'connecting short pipe' under Appendix D.12; cable trays and wireways are billed under Appendix D.12; cable branch boxes are billed as 'terminal boxes' under Appendix D.5. For rate build-up, quota line items are selected by laying method, cross-section and core count and multiplied by core/material coefficients; the coefficients adjust consumption only and never change the BOQ metre figure.
Applicable Codes
- GB/T 50856-2024 · Standard for measurement of general mechanical, electrical, plumbing and fire services App. D Table D.9.1(电缆安装,code 030409)
- GB/T 50856-2024 App. D Table D.8.1(滑触线装置安装,code 030408)
- GB/T 50856-2024 App. D.17.12(Table D.9.1 有关问题说明)
- GB/T 50856-2024 Table D.17.3-5(电缆敷设预留长度及附加长度)
- DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) 第6.4.54~6.4.67条
Topic positioning
The BOQ code attribution and adjacent-item billing boundaries of cable installation under GB/T 50856-2024 'Standard for Quantity Take-off of General Installation Works', Appendix D: preventing misuse of BOQ codes and misattributed items, and aligning with the quota-side rate build-up banded by conductor cross-section and core count.
Core conclusion
1. The cable installation code is 030409 Table D.9.1: 'The item setup, the content of item descriptions, the units of measurement and the quantity take-off rules for cable installation BOQ items shall follow Table D.9.1.' - Table D.9.1 Cable installation (code: 030409): power cables and control cables are measured in m, calculated as the total of single-run lengths shown on the design drawings plus the reserved length.
2. 030408 is not cable installation; it is trolley wire installation Table D.8.1: 'The item setup, the content of item descriptions, the units of measurement and the quantity take-off rules for trolley wire installation BOQ items shall follow Table D.8.1.' (code 030408). Version note: in GB 50856-2013, 030408 was cable installation and 030411 was conduit and wiring; the 2024 edition renumbered Appendix D as a whole (cable installation became 030409 and conduit and wiring became 030412), so carrying over the old codes constitutes a BOQ error; when cross-checking editions, verify the codes clause by clause instead of copying them.
3. The five original notes to Table D.9.1 (Appendix D.17.12) 1 The laying method of cable protective conduit means above ground or underground; cable protective conduit used as sleeve where cables enter a building shall be coded and billed as 'connecting short pipe' under conduit and wiring in Appendix D.12 of this standard; 2 The reserved and additional lengths for cable laying are given in Table D.17.3-5; 3 Cable trays and cable wireways shall be coded and billed under the corresponding items of conduit and wiring in Appendix D.12 of this standard; 4 Cable branch boxes shall be coded and billed as 'terminal boxes' under low-voltage electrical equipment installation in Appendix D.5 of this standard; 5 The laying method of cables means direct burial, in cable trenches (tunnels), in duct banks, indoors, in vertical shafts and the like.
That is: code 030409 covers only the cable itself - its laying and its terminations and joints; trays and wireways, conduit (including the connecting short pipes at building entries) and branch boxes (billed as terminal boxes) fall outside it and go to Appendix D.12 and Appendix D.5 respectively.
4. Mapping the BOQ metre figure to quota-side rate build-up banded by cross-section and core count
- BOQ side: a cable installation BOQ item is measured in m, the quantity being the single-run length plus the reserved (additional) length, with the specification carried by the item description (voltage class, laying method, cross-section, core count, material and so on).
- Quota side: line items are selected by 'laying method + cable cross-section + core count' (power cables and control cables in separate items, mineral-insulated and prefabricated branch cables with dedicated items), then multiplied by core-count/material adjustment coefficients (for example five cores x1.15, single core x0.67, aluminium or aluminium alloy x0.67, labour in vertical risers x1.30; values follow the original text of the quota chapter notes being applied).
- The two tracks each govern their own side: switching cross-section bands or applying core-count coefficients changes only the quota consumption and the all-in unit rate, never the BOQ quantity figure; the BOQ length must not be inflated by adopting a higher cross-section band item or by applying coefficients.
Applicability boundaries
- Applies to building and general installation BOQs prepared under GB/T 50856-2024 Appendix D; municipal works follow the corresponding appendices of GB/T 50857-2024 and urban utility tunnels follow SJG 111.3-2022 - different coding systems that must not be mixed.
- Projects under way or at settlement using the 2013 edition BOQ format follow the contractually agreed edition; 2024 codes must not override the old edition basis.
- This card settles only code attribution and billing routes; it does not cover the item-by-item reservation values, cable termination measurement details, or the specific coefficient values of each quota system.
- Quota coefficients vary with the quota system; before pricing, always go back to the original text of the cable chapter notes of the quota being applied; coefficients must not be carried across systems.
Further reading
- GB/T 50856-2024 'Standard for Quantity Take-off of General Installation Works', Appendix D: Table D.9.1 (cable installation, code 030409), Table D.8.1 (trolley wire installation, code 030408), Appendix D.17.12 (notes to Table D.9.1), Appendix D.12 (conduit and wiring), Appendix D.5 (low-voltage electrical equipment installation, 'terminal boxes'), Table D.17.3-5 (reserved and additional lengths for cable laying).
- Quota-side banding and coefficients: DB11/T 2382-2024 'Consumption Standard for Construction Works', clauses 6.4.54-6.4.67 (IX Cables); Jing Jian Fa [2021] No. 201, General Installation Volume 4, Electrical Equipment Installation, Chapter 8 Cables - notes and quantity take-off rules.