视为放弃
- 01
Re-work confirmation requirements and claim procedure deadlines for material scrap from changes/employer-risk events: notice of intent within 28 days, claim report, employer reply in 14/28 days, and deemed waiver/acceptance on default (GB/T 50500-2024, 7.6.1/8.11.3/8.11.5)
Material-scrap claims require a written re-work confirmation demand with…
GB/T 50500-2024 第7.6.1条GB/T 50500-2024 第8.11.3条GB/T 50500-2024 第8.11.5条2026-09-12 - 02
Supplementing omitted claims after final-account double signing: the dual bars of procedural forfeiture and finality of settlement, and the exception windows (GB/T 50500-2024 Clauses 8.11.3 and 10.3.12)
After the final-account documents are signed and sealed by both parties…
GB/T 50500-2024 建设工程工程量清单计价标准 第8.11.3/8.11.5/8.11.6/10.3.12条法释〔2020〕25号 建工解释一 第二十九条民法典 第147/151/152条2026-08-31