Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

GB/T 50860-2024 structures measurement standard: pool and chimney work-item setup, calculation rules, member boundary attribution, and the twelve-digit item code rules

In GB/T 50860-2024 (effective 2025-09-01, replacing GB 50860-2013), pools follow Appendix A Table A.1.1 (code 070101), concrete chimneys Table A.6.1 (070106), masonry chimneys Appendix B Table B.1.1 (070201); each member is listed separately for concrete/reinforcement/formwork; member boundaries follow table notes (wall-base-beam bottom boundary, capitals/pedestals into roof/floor slabs, chimney height datum); item codes per 4.2.2 use twelve Arabic digits (digits 1-2 discipline code 07 = structures works; digits 10-12 set by name and characteristics, no duplicates within one bid works' single project), 4.2.1 requires the five elements; Appendix C preliminary items (070301) exclude scaffolding within 3.6 m, whose cost enters work-item unit prices.

Topic Positioning

Item setup, characteristics description, measurement units, calculation rules, member boundary/attribution notes, and item-coding rules for pools and chimneys (concrete/masonry) work-item BOQs under GB/T 50860-2024 "Standard for measurement of structures works" (MOHURD Announcement No. 191 of 2024, effective 2025-09-01, replacing GB 50860-2013). For structures BOQ compilation and quantity take-off.

Core Conclusions

Standard structure: Appendix A concrete structures, Appendix B masonry structures, Appendix C preliminary items (code 070301). Pool and chimney itemization and measurement rules (clause numbers are table-note originals):

  1. Pools per Table A.1.1 (code 070101). Characteristics must describe pool shape (circular/square), concrete type, strength grade, etc. Note boundaries (originals):
  • Note 2: with a wall-base beam, the beam bottom is the boundary — above is pool wall, below is floor slab; without one, a conical bottom counts to the slope top surface, and the splayed footing at the wall's lower part goes into the floor slab area.
  • Note 3: for a flat-slab roof, the enlarged top of the wall goes into the roof slab volume; for a ribbed slab, primary and secondary beams go into the roof slab; for a spherical cap, bounded by the wall top surface, the side beams go into the roof slab.
  • Note 4: internal column height runs from floor-slab top (or pedestal top) to roof-slab bottom (or capital bottom); capitals and pedestals merge into roof slab and floor slab volumes respectively.
  1. Concrete chimneys per Table A.6.1 (070106):
  • Note 1: chimney height means the height from outdoor ground to the flue-gas outlet.
  • Note 2: concrete platforms at each level inside the chimney, hopper platforms and their supports, smoke partitions, drip plates, etc. follow the current GB/T 50854.
  1. Masonry chimneys per Table B.1.1 (070201):
  • Note 1: chimney height means outdoor ground to the top of the top ring beam (excluding the triangular cap).
  • Note 2: cast-in-place concrete chimney foundations, insulation, and linings follow this standard's Appendix A.6.
  • Note 3: these are masonry foundations; if concrete, itemize per Appendix A.6.
  1. Formwork forms (A.15.3): formwork forms may be described as straight, inclined (only for slopes > 20%), curved (radius <= 12 m), arched, etc.

  2. Five BOQ elements (4.2.1): the BOQ shall be compiled per the codes, names, characteristics, units, and rules of Appendices A and B; the five elements are indispensable in a work-item BOQ.

  3. Item code rules (4.2.2, original): item codes use twelve Arabic digits; digits 1-9 per the appendices; digits 10-12 per the item name and characteristics of the proposed works; codes must not duplicate within the same single project of the same bid works. Digit meanings: 1-2 discipline code (01 building & decoration; 02 antique building; 03 general installation; 04 municipal; 05 landscape; 06 mining; 07 structures; 08 urban rail transit; 09 blasting; later codes by analogy); 3-4 appendix sequence; 5-6 division sequence; 7-9 item name sequence; 10-12 list-item name sequence. When one single project contains multiple unit works compiled per unit work, digits 10-12 must not duplicate — e.g., pool floor slabs with identical characteristics in 3 unit works are coded 070101001001/002/003 with quantities listed per unit work.

  4. Characteristics and work content (4.1.2): characteristics are an indispensable basis for determining unit prices and must be described accurately and completely; work contents list principal content only — auxiliary content such as machinery moves and material transport, though unlisted, is included; do not split into separate items unless specially noted.

  5. Preliminary items (4.3.3): Appendix C preliminary items exclude scaffolding with erection height within 3.6 m; that cost is considered in the corresponding work-item unit prices.

  6. Edition differences (2024 vs 2013): reinforcement and formwork become independent items within each member's work-item table (e.g., pool floor slab / slab reinforcement / slab formwork, in m3, t, m2 respectively); Appendix C no longer has formwork items; the 2013 practices of "borrowing GB 50854 for reinforcement" and "formwork under preliminary items" no longer apply. Final codes, characteristics, and rules subject to the published text.

Applicable Boundaries

Applies to structures works (pools, chimneys, water towers, silos, etc.) BOQs compiled to GB/T 50860-2024; not for buildings (GB/T 50854) or municipal works. The 2024 item structure differs from 2013 — do not carry over 2013 practices (borrowed reinforcement, formwork under preliminaries). Digits 10-12 are set by the compiler per name and characteristics, no duplicates within one bid works' single project; identical-characteristic items across unit works must be distinguished by digits 10-12. Item rows (codes, characteristics, rules) are partly OCR-incomplete — verify against the officially published GB/T 50860-2024 text; internal chimney platforms, hopper platforms, smoke partitions, and drip plates now go to GB/T 50854 items, not structures items.

Further Reading

See GB/T 50860-2024: 4.2.1 (five elements), 4.2.2 (twelve-digit codes and discipline code table), 4.1.2 (characteristics and work content), 4.3.3 (scaffolding within 3.6 m); Appendix A Table A.1.1 (pools, 070101) notes 1-4, Table A.6.1 (chimneys, 070106) notes 1-2, A.15.3 (formwork forms); Appendix B Table B.1.1 (masonry chimneys, 070201) notes 1-3; Appendix C Table C.1.1 (preliminary items, 070301). Chimney internal platform items: GB/T 50854-2024.