Installation and acceptance of HEPA filters and clean laminar-flow hoods: pre-installation conditions, frame flatness 1mm, mechanical-seal gaskets 6~8mm with compression ratio, liquid-trough sealing at 2/3 trough depth with a melting point over 50C, and independent hangers with 1.0h continuous trial running

Before HEPA installation the fit-out and pipework must be complete and accepted, the clean air-conditioning system run continuously for over 12h and everything wiped clean; mounting frames flat and clean with flatness deviation within 1mm per filter; mechanical sealing with air-tight gaskets 6mm~8mm thick, uniformly compressed at 25%~50% (GB 50243-2016: 25%~30%, seams never straight-jointed); liquid-trough sealing with level, leak-free troughs, sealant at about 2/3 trough depth and melting point above 50C; check by full inspection and leak testing. Laminar-flow hoods use independent posts or hangers with anti-sway measures, never supported off equipment or wall panels; vertical unidirectional-flow levelity within 0.1%, horizontal verticality +/-1mm and height tolerance +/-1mm; after installation run continuously no less than 1.0h and check the electrical interlocks.

Applicable Codes

  • GB 51110-2015 洁净厂房施工及质量验收规范 第5.4.4~5.4.7条、附录C
  • GB 50243-2016 通风与空调工程施工质量验收规范 第7.3.17条
  • GB 50591-2010 洁净室施工及验收规范 App. A~H
  • CRAA 430 空气过滤器 分级与标识
  • GB/T 1429 组合式空调机组

Positioning

Acceptance provisions for HEPA filters (including filter sections of HEPA supply outlets), fan-filter units (FFU) and clean laminar-flow hoods in clean-room air systems: pre-installation conditions, frame flatness, the quantified mechanical- and liquid-sealing requirements, hood levelity and trial running, and the compression-ratio difference between the two national standards.

Core conclusions

1. Pre-installation conditions (GB 51110-2015 clause 5.4.4, key item) '1 The architectural fit-out and pipework of the cleanroom (area) shall be complete and accepted. 2 The cleanroom (area) shall be fully cleaned and wiped, and the clean air system wiped and run continuously for over 12h. 3 The HEPA installation place and related parts shall be cleaned and wiped. 4 HEPA filters shall have passed visual inspection, the product meeting the drawings and CRAA 430 (Air Filters - Classification and Marking); frames, media and sealant free of deformation, fracture, damage or loss.' Check: all; by observation.

2. HEPA installation (GB 51110-2015 clause 5.4.5, key item) '1 Install immediately after passing visual inspection. 2 The mounting frame shall be flat and clean; flatness deviation within 1mm per filter. 3 Direction correct; after installation the filter perimeter and interfaces tight and leak-free. 4 Mechanical sealing: air-tight gaskets 6mm~8mm thick, tight against the filter frame; compression uniform after installation at 25%~50%. 5 Liquid-trough sealing: trough frames level, no leakage, no dirt or water in the trough; sealant height about 2/3 trough depth, melting point above 50C.' Check: full testing and leak testing; methods: measurement and observation, leak tests per Appendix C.

3. GB 50243-2016 clause 7.3.17 (HEPA and hood installation) '1 Frames flat and clean, flatness tolerance 1mm. 2 Mechanical sealing: gaskets about 6mm~8mm thick, flat; compression uniform, ratio about 25%~30%. 3 Liquid-trough sealing: trough frames level, no leakage, trough free of dirt and water; sealant not exceeding 2/3 trough depth, melting point above 50C. 4 Laminar-hood levelity deviation 1 per mille, height tolerance 1mm.' Check: sampling plan II; by ruler and observation. Commentary: gasket thickness and seam treatment matter greatly - seams must not be straight joints; 2/3 depth balances sealing of inserted ends against overflow. Compression-ratio difference: GB 51110-2015 (cleanroom-specific) 25%~50%; GB 50243-2016 (general HVAC) 25%~30% - cleanroom works follow GB 51110-2015, general HVAC GB 50243-2016.

4. FFU installation (GB 51110-2015 clause 5.4.6) '1 Preconditions per 5.4.4. 2 Visual inspection in a clean environment - no deformation, corrosion, film loss or panel damage. 3 Frames flat and smooth. 4 Direction correct; installed FFUs accessible for maintenance. 5 Sealing at the frame connections.' Check: full testing and leak testing.

5. Laminar-flow hood installation (GB 51110-2015 clause 5.4.7) '1 Visual inspection first - no deformation, loss or fracture. 2 Independent posts or hangers with anti-sway fixing, never supported off related equipment or wall panels. 3 Hoods mounted directly on ceilings: sealing and vibration isolation between the casing and ceiling panels. 4 Vertical unidirectional-flow hoods: levelity within 0.1%; horizontal: verticality +/-1mm, height tolerance +/-1mm. 5 After installation, continuous trial running no less than 1.0h, checking running equipment, parts and electrical interlocks.' Check: full testing and leak testing.

6. Related provisions (same section)

  • Air handling units assembled on site: air leakage testing - classes 1~5 units not over 0.6%, classes 6~9 not over 1.0%, method per GB/T 1429; sampling by class, full or 50%.
  • Electric heaters: smooth dust-free surfaces, preferably stainless; insulation 800mm before and behind of non-combustible material; flange gaskets to ducts heat-resistant and non-combustible; metal casings earthed; exposed terminals guarded.

Applicable boundaries

  • For HEPA, FFU and hood installation and acceptance (key items) in clean systems, and unit assembly and heater checks.
  • Sampling differs: GB 51110-2015 clauses 5.4.5~5.4.7 'full testing and leak testing'; GB 50243-2016 clause 7.3.13 plan II - follow the standard invoked, never swap.
  • Post-installation leak tests per GB 51110-2015 Appendix C; comprehensive performance point layouts per GB 50591-2010 Appendices A-H.
  • Medium / coarse filters of ordinary (non-clean) HVAC are outside the clean sealing and leak-test requirements.

Further reading

  • GB 51110-2015 clauses 5.4.4~5.4.9 and Appendix C; GB 50243-2016 clause 7.3.17 and commentary; GB 50591-2010 Appendices A-H; CRAA 430; GB/T 1429.