BOQ itemisation boundary for earthworks, bedding, masonry, chambers and thrust blocks attached to installation works: the routing rules by which GB/T 50856-2024 Clause 3.0.4 refers to GB/T 50854 / GB/T 50857 / GB/T 50858
Per GB/T 50856-2024 Clause 3.0.4, earthwork excavation and backfill, bedding, masonry, plastering, trench cover slabs and cast-in-place foundations involved in installation works are itemised under the corresponding items of GB/T 50854; wells, precast pipelines, pipe thrust blocks, new-to-existing pipe connections, temporary blow-off pipelines, warning tapes / marker posts / warning signs, and waste incinerator and auxiliary equipment installation are itemised under the corresponding items of GB/T 50857; fountains, misting systems and irrigation systems are itemised under GB/T 50858; the pipe proper remains measured under Appendix K (031001) by centreline length, with no deduction for the lengths occupied by wells.
Applicable Codes
- GB/T 50856-2024 通用安装工程工程量计算标准 第3.0.4条
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. A
- GB/T 50857-2024 市政工程工程量计算标准 App. A
- GB/T 50858-2024 园林绿化工程工程量计算标准
Scope of the topic
Civil-type work arising incidentally in water supply, drainage, heating and gas installation works -- earthworks, bedding, masonry, chambers, thrust blocks and the like -- is not coded within the installation standard's own appendices; GB/T 50856-2024 Clause 3.0.4 routes it along three lines ('building / municipal / landscape') to the corresponding measurement standards. This card gives the gist of that boundary clause and where each item lands, answering 'who itemises and who measures' when the earthworks sit in a building BOQ and the pipes in an installation BOQ.
Core conclusions
1 The boundary clause (GB/T 50856-2024 Clause 3.0.4, gist of the text) 'Unless otherwise provided in this standard, items of earthwork excavation and backfill, bedding, masonry, plastering, trench cover slabs and cast-in-place foundation works involved in general installation works shall follow the corresponding items of the current national standard GB/T 50854, Standard for Measurement of Building and Decoration Works; items of wells, precast pipelines, pipe thrust blocks, connections between new and existing pipes, temporary blow-off pipelines, warning tapes, marker posts, warning signs, and waste incinerator and auxiliary equipment installation works shall follow the corresponding items of the current national standard GB/T 50857, Standard for Measurement of Municipal Works; and items of fountain, misting and irrigation system works shall follow the corresponding items of the current national standard GB/T 50858, Standard for Measurement of Landscape and Greening Works.' Commentary: the clause prescribes how earthwork excavation and backfill, bedding, masonry, plastering, trench cover slabs, cast-in-place foundations, wells, precast pipelines, pipe thrust blocks, new-to-existing pipe connections, temporary blow-off pipelines, warning tapes, marker posts, warning signs, waste incinerators and auxiliary equipment installations are coded and itemised, and how fountains, misting and irrigation systems are coded and itemised.
2 Where each item lands
| Work content | Governing standard | Which item class in that standard |
|---|---|---|
| Pipe-trench excavation and backfill | GB/T 50854 | Appendix A earthworks (010101 / 010102 / 010103) |
| Bedding and cast-in-place foundations | GB/T 50854 | Appendix items for concrete and reinforced concrete |
| Masonry, plastering, trench cover slabs | GB/T 50854 | The corresponding masonry / plastering / cover slab items |
| Wells (inspection chambers, valve pits and the like), precast pipelines | GB/T 50857 | Appendix items for wells and precast pipelines |
| Pipe thrust blocks, new-to-existing connections, temporary blow-off lines | GB/T 50857 | The corresponding appendix items |
| Warning tapes, marker posts, warning signs | GB/T 50857 | The corresponding appendix items |
| Fountains, misting, irrigation systems | GB/T 50858 | The corresponding items |
| Pipe proper (water supply, drainage, heating, gas) | GB/T 50856 | Appendix K Table K.1.1 (code 031001), by design centreline length in m |
3 Measurement calibre for the pipe proper (the interface point) GB/T 50856-2024 Table K.1.1, explanatory note 8: pipe quantities deduct no lengths occupied by valves, pressure reducers, steam traps, water meters, expansion joints and other fittings, nor by wells of any kind; square expansion compensators enter the pipe installation quantity with the length they occupy, their fabrication and installation being included in the all-in unit rate. The pipe is thus priced by centreline length with chamber lengths not deducted, while the chamber proper is separately itemised under GB/T 50857 -- the two coexist without double counting.
4 Variation synchronisation The civil BOQ (earthworks, bedding, chambers) and the installation BOQ (pipe proper) sit in different appendices with different units. When a variation avoids an obstacle, both sides must adjust in step under the same variation instruction, the same as-built drawing baseline and the same measurement period: the pipe side adjusts centreline length (no deduction for chamber length), the earthworks side adjusts cross-section x length together with the chamber additions or removals -- so neither side adjusts while the other misses out.
Applicable boundaries
- Clause 3.0.4 is a catch-all referral applying 'unless otherwise provided in this standard': work content already itemised within the installation appendices (e.g. the Appendix K pipe items already include pressure testing, purging and cleaning) still follows the installation standard itself and is not referred out.
- The clause settles only coding and itemisation; it does not alter contract interfaces or cost allocation. The indoor-outdoor boundaries (water supply and heating at 1.5 m outside the external wall face; drainage at the first inspection chamber out of the building; the tie-in point with the municipal mains) are judged per the corresponding notes of Appendix K.
- Waste incinerator and auxiliary equipment installation is itemised under GB/T 50857 -- a municipal exception within installation works; do not misplace it in an installation appendix.
- The same work content must not be itemised twice under two standards in one project; once referred, the referred standard's measurement rules, units and item description requirements apply (including calibre differences over working space and batter accounting).
Further reading
- GB/T 50856-2024, Standard for Measurement of General Installation Works: Clause 3.0.4 and its commentary; Appendix K Table K.1.1 and its explanatory notes.
- GB/T 50854-2024, Standard for Measurement of Building and Decoration Works: Appendix A (earthworks; concrete and masonry related items).
- GB/T 50857-2024, Standard for Measurement of Municipal Works: Appendix A and the appendices for wells, precast pipelines and thrust blocks.
- GB/T 50858-2024, Standard for Measurement of Landscape and Greening Works: fountain, misting and irrigation items.