Engineering Knowledge Cards.
Confidence HighUpdated 2026-11-08

Itemisation attribution and measurement coverage of valves, flanges, strainers and expansion joints in pipe erection: the boundary between the two regimes of GB/T 50856-2024 Annex K pipe accessories (031002) and Annex H valves and flanges (030807~030812), the 'included in pipe erection vs itemised separately' boundary, and the quota rate build-up conversions

Valves, flanges, strainers and expansion joints are all pipe accessories and must not be merged into pipe erection items; they must be itemised separately by works category: building water supply and drainage, heating and gas follow GB/T 50856-2024 Annex K Table K.2.1 pipe accessories (code 031002); industrial piping follows Annex H (valves 030807~030809, flanges 030810~030812, valves counted per unit from the design-drawn quantity); municipal pipe networks follow GB/T 50857-2024 Table E.2.1 (040502). Pipe length never deducts the length occupied by valves, pressure reducers, steam traps, water meters, expansion joints and other accessories or by chambers of any kind; the square expansion loop is the only reverse exception (its occupied length merges into the pipe and its fabrication and erection are already in the all-in unit rate); a valve's work content excludes flanges and flanged accessories, and where fittings are flange-connected they are measured as flange items and the fitting item ceases.

Applicable Codes

  • GB/T 50856-2024 · Standard for measurement of general mechanical, electrical, plumbing and fire services App. K Table K.1.1(031001 给排水、采暖、燃气管道)、Table K.2.1(031002 管道附件)、K.9.6、K.9.7
  • GB/T 50856-2024 App. H Table H.7.1(030807 低压阀门)、Table H.10.1(030810 低压法兰)、H.15.6、H.15.7、H.15.9、H.15.11
  • GB/T 50856-2024 App. J J.11.3(消防管道阀门按App. K 列项)
  • GB/T 50857-2024 · Standard for Measurement of Quantities of Municipal Works App. E Table E.2.1(040502 管件、阀门及附件安装)
  • 京建发〔2021〕201号 2021 预算消耗量标准 通用安装工程第十册《给排水、采暖、燃气工程》第五章 阀门及管道附件
  • 天津市安装工程工程量清单计价指引(2025)表H.7 低压阀门(编码030807)

Topic positioning

This card resolves a high-frequency dispute in pipe quantity take-off and itemisation: whether the valves, flanges, strainers (dirt separators) and expansion joints (compensators, flexible joints) on a pipeline count as already included in the pipe erection item, and, when itemised separately, which code set applies and by what measurement unit and rules. Based on GB/T 50856-2024 'Quantity take-off standard for general building services works', Annex K (water supply and drainage, heating, gas) and Annex H (industrial piping), checked against GB/T 50857-2024 'Quantity take-off standard for municipal works' Annex E and the rate build-up coverage of local consumption standards.

Core conclusions

I. Fix the regime first: accessories and pipes sit in two separate tables, mutually exclusive

  • Building water supply and drainage, heating, gas (Annex K): pipes in Table K.1.1 (code 031001), accessories in Table K.2.1 pipe accessories (code 031002). Table K.2.1 provides that the item setting, item description content, units of measurement and quantity take-off rules of pipe accessories shall follow Table K.2.1.
  • Industrial piping (Annex H): pipes in Tables H.1.1~H.3.1 (030801 low / 030802 medium / 030803 high pressure piping); accessories in separate tables - Table H.7.1 low-pressure valves (030807), Table H.8.1 medium-pressure valves (030808), Table H.9.1 high-pressure valves (030809), Table H.10.1 low-pressure flanges (030810), Table H.11.1 medium-pressure flanges (030811), Table H.12.1 high-pressure flanges (030812). Directly buried pre-insulated pipes are itemised under the corresponding codes of Annex H industrial piping works (K.9.6 item 10).
  • Municipal pipe networks: GB/T 50857-2024 Annex E Table E.2.1 'erection of fittings, valves and accessories' (code 040502); item setting, descriptions, units and rules follow that table.
  • Fire protection works: valves on fire-protection piping are itemised under the corresponding codes of Annex K water supply and drainage, heating and gas works (Annex J J.11.3).

II. The four boundaries of 'included in pipe erection / itemised separately'

  1. The pipe work content includes fittings, not accessories. The work content of Table K.1.1 piping (031001) is pipe erection + fitting erection (or fabrication and erection of fittings) + pipe clip fabrication and erection + pressure testing + blowing and flushing (drainage pipes also include the riser inspection eye and the vent cap); valves, flanges, strainers and expansion joints are not included and must be listed separately under 031002. Industrial piping likewise: fittings 030804~030806, valves 030807~030809 and flanges 030810~030812 each listed separately.
  2. Pipe length does not deduct accessory occupancy (do not reverse this). K.9.6 explanatory note 8 verbatim: 'in measuring pipes, no deduction is made for the length occupied by valves, pressure reducers, steam traps, water meters, expansion joints and other fittings, or by chambers of any kind; the length occupied by the square expansion loop is included in the pipe erection quantity, and the pipe erection all-in unit rate includes its fabrication and erection.' Industrial piping to the same effect, H.15.6 item 1 verbatim: 'pipe quantity take-off deducts no length for valves, fittings or square expansion loops; buried outdoor pipes deduct no length for ancillary structures (chambers).'
  3. The square expansion loop is the only reverse exception: its occupied length merges into the pipe quantity, but no separate fabrication and erection item is raised - the fabrication and erection are already in the pipe erection all-in unit rate.
  4. Accessories do not contain one another either (against double counting). K.9.7 item 1 verbatim: 'valve types include threaded valves, threaded-flange valves, welding-flange valves and grooved valves; where a flange is on one side only, describe it in the item description. The work content of valves excludes flanges and flanged accessories.' On the industrial side, H.15.7 item 5: 'where fittings are flange-connected, calculate under the corresponding items of Table H.10.1 low-pressure flanges and Table H.11.1 medium-pressure flanges, and do not further calculate the fitting items' - once flange-connected, the flange item replaces the fitting item and the two must not double count.

III. Itemisation and measurement points per accessory

Valves

  • Specification and type: the valve type (threaded / threaded-flange / welding-flange / grooved), material, model and specification, connection form and welding method form the item description; for plastic valves the connection form means fusion jointing, solvent cement jointing, hot-gas welding etc. (K.9.7 item 2).
  • Unit and rule: counted per unit from the design-drawn quantity. The BOQ guide splits industrial low-pressure valves into 030807001 low-pressure threaded valves, 030807002 low-pressure welding valves, 030807003 low-pressure flanged valves, 030807004 low-pressure gear, hydraulic and power-operated valves, 030807005 low-pressure safety valves, 030807006 low-pressure control valves, 030807301 low-pressure plastic valves and 030807302 low-pressure glass valves, all measured per unit by the rule 'calculated from the design-drawn quantity'; work content is erection + operating device erection + shell pressure test (the shell test is already included in body erection), with combinable budget base-price line items listed separately for valve operating device erection and for temporary spool erection and removal for control valves.
  • Industrial piping special notes (H.15.9): 'pressure reducing valves are sized by the high-pressure side diameter'; 'the work content of power-operated valves includes motor erection'; 'operating device erection follows the code or the design technical requirements'. Annex K to the same effect: the specification of pressure reducers is described by the high-pressure side pipe specification (K.9.7 item 3).

Flanges

  • Separate listing (H.15.11 item 1): 'where flanges are welded, list separately by connection form as slip-on flanges, butt-weld flanges, loose lapped flanges, loose weld-ring flanges etc.'
  • Interface with blind plates (H.15.11 item 2): 'welded blind plates (heads) are calculated as fitting connections under the rules of Annex H.4 low-pressure fittings and Annex H.5 medium-pressure fittings. Blind plates supplied with flanges are not calculated.'

Strainers (dirt separators)

  • Under Annex K, the strainer / dirt separator items sit in Table K.2.1 pipe accessories (031002); where industrial piping Annex H sets no dedicated strainer table, itemise under valve items (threaded / welding / flanged valves) or submit as a supplementary item for approval - no duplicate separate listing.
  • Consumption standard coverage (Beijing 2021 general building services Volume 10 Chapter 5): 'strainer erection follows the corresponding valve erection line items by connection form, with labour multiplied by 1.2.'

Expansion joints (compensators, flexible joints)

  • Compensator types include square expansion loops, welded ready-made compensators and flanged ready-made compensators (K.9.7 item 5); the square loop coverage is as above (length merges into the pipe, fabrication and erection not counted again); sleeve and bellows ready-made expansion units are itemised as compensators, rubber and metal flexible joints as flexible joint (hose) items, all counted from the design-drawn quantity.
  • Quota coverage: 'ready-made hoses of any material may follow the flexible joint erection line items'; 'dirt separators, bellows (sleeve) compensators and flexible joints are calculated by connection form and specification'; 'square expansion loops are calculated by fabrication method and specification'.

IV. Conversion coverage on the consumption standard (rate build-up) side (Beijing 2021 general building services Volume 10 Chapter 5 'valves and pipe accessories', 12 sections, 223 line items)

  • 'Threaded valve line items apply to the erection of valves with any internal or external threaded connection.' 'Flanged valve line items apply to the erection of any flange-connected valve; where only one side is flange-connected, follow the flanged valve erection line item with the flange and bolt quantities halved, all else unchanged.'
  • 'Solenoid valve erection follows the valve erection line items by connection form, with labour multiplied by 1.1.' 'Steam trap and pressure reducing valve erection follows the corresponding valve erection line items by connection form.' 'Medium- and high-pressure valve erection follows the corresponding line items of Volume 8, industrial piping works.'
  • 'Water meter erection applies to cold and hot water meters and covers meter erection only; valves and other accessories are calculated separately.' 'Heat meter erection is by connection form... valves and accessories on both sides of the meter are calculated separately.'
  • 'Backflow preventer erection is compiled without a bypass; the bypass is calculated separately; where the design configuration differs from the line item, the strainer and flexible joint quantities may be adjusted to the design usage, all else unchanged.'
  • 'Float valve erection already includes the erection of the lever and float and must not be counted again.'
  • 'The valve erection work content of this chapter includes the spot strength and tightness testing carried out before erection.'
  • Quantity take-off rules: 'all valves and pipe accessories are calculated from the design-drawn quantity'; 'valves are calculated by connection form and specification, pressure reducing valves by the high-pressure side specification'; 'flanged valves (with short pipes A and B) by specification'; 'backflow preventers, heat meters and water meters by connection form, specification and model'; 'water meter boxes and heat meter boxes by the outer frame dimensions of the box'; 'water hammer arrestors by connection form and specification'.

Applicable boundaries

  • Fix the works category first, then the table. Annex K (building water supply and drainage, heating, gas, HVAC water) and Annex H (industrial piping, including directly buried pre-insulated pipes and piping beyond the first flange of the equipment body) are two mutually exclusive regimes and must not be mixed within one work; yard industrial piping and city networks belong respectively to GB/T 50856 Annex H and GB/T 50857 Annex E and must not be cross-applied.
  • Fittings and accessories are different problem domains: whether fittings are listed separately runs in opposite directions in Annex K and Annex H (K merges into the pipe, H must list separately) - do not mix this with the accessory rules.
  • Units follow the verbatim tables: Annex K accessories to Table K.2.1, industrial piping to Tables H.7.1 / H.10.1 etc., municipal to Table E.2.1; what this card has verified two-way between the BOQ guide and the quota rules is 'valves per unit from the design-drawn quantity' - the units of the other accessories must be checked in their own tables and never assumed across tables.
  • The coefficients and conversions (labour x 1.1, x 1.2, flange and bolt quantities halved) are local consumption standard coverage only; changing province or version requires checking the current local standard, and none of it carries over directly to other regions or to BOQ pricing.
  • Where industrial piping has no dedicated item (e.g. strainers, flexible joints) the fallback depends on the configuration shown on the design drawings and on local pricing documents; supplementary items must be submitted for approval and codes must not be invented.

Further reading

  • GB/T 50856-2024 'Quantity take-off standard for general building services works', Annex K: Table K.1.1 water supply and drainage, heating and gas piping (031001), Table K.2.1 pipe accessories (031002), K.9.6 explanatory notes 7-11 (tie-ins, no length deduction, pressure testing and blowing, directly buried pre-insulated pipes, protective piping), K.9.7 notes 1-6 (valves, plastic valves, pressure reducers, steam traps and backflow preventers, compensators, water meters).
  • Annex H: Table H.7.1 low-pressure valves (030807), Table H.10.1 low-pressure flanges (030810), H.15.6 (no pipe length deduction), H.15.7 (fittings and flange interface), H.15.9 (valve notes), H.15.11 (flange and blind plate notes).
  • Annex J J.11.3: valves on fire-protection piping itemised under Annex K.
  • GB/T 50857-2024 'Quantity take-off standard for municipal works', Annex E Table E.2.1 erection of fittings, valves and accessories (040502).
  • Local pricing bases: Beijing 2021 budget consumption standard, general building services Volume 10 'Water supply, drainage, heating and gas works' Chapter 5 'Valves and pipe accessories' (notes + quantity take-off rules + line items); Tianjin installation works BOQ pricing guide (2025), Table H.7 low-pressure valves (030807) and its column of combinable budget base-price line items.