High-strength bolt assemblies stored over 6 months require re-testing (torque coefficient / fastening axial force): GB 50755-2012 Clause 5.4.2, JGJ 82-2011 Clause 6.1.5, DB11/T 1832.5-2023 Clause 11.1.5
High-strength bolt assemblies (large-hex-head and torshear-type) shall not be stored longer than 6 months; beyond 6 months, they must be re-tested for torque coefficient (large-hex assemblies) or fastening axial force/preload (torshear assemblies) before use, and used only if qualified. Basis: GB 50755-2012 Clause 5.4.2, JGJ 82-2011 Clause 6.1.5 (the 6-month shelf life originates from GB/T 1231 and GB/T 3632, premised on intact as-delivered condition); Beijing adds DB11/T 1832.5-2023 Clause 11.1.5 to the same effect.
Applicable Codes
- GB 50755-2012 钢结构工程施工规范 第5.4.2条
- JGJ 82-2011 钢结构高强度螺栓连接技术规程 第6.1.5条
- GB/T 1231 钢结构用高强度大六角头螺栓、大六角螺母、垫圈技术条件
- GB/T 3632 钢结构用扭剪型高强度螺栓连接副
- DB11/T 1832.5-2023 建筑工程施工工艺规程 第5部分:钢结构工程 第11.1.5条
Topic Positioning
Storage period and overdue re-testing of high-strength bolt assemblies (large-hex-head, torshear) in steel construction: after over 6 months of storage, torque-coefficient or axial-force (preload) tests must be repeated before use, and only qualified lots may be used. National, industry, and local codes agree - general knowledge for incoming-material storage and re-testing management.
Core Conclusions
GB 50755-2012 "Code for construction of steel structures", Clause 5.4.2: Large-hex-head and torshear high-strength bolt assemblies shall carry factory-qualified inspection reports of torque coefficient and fastening axial force (preload) respectively, delivered with each box. When assemblies have been stored over 6 months before use, the torque-coefficient or axial-force test shall be repeated as required, and they may be used only after passing.
JGJ 82-2011 "Technical specification for high strength bolt connections of steel structures", Clause 6.1.5: Storage of bolt assemblies shall not exceed 6 months. Beyond 6 months, the torque-coefficient or axial-force test must be repeated as required, and only qualified lots may be used. Basis: GB/T 1231 (large-hex bolts, nuts, washers - technical requirements) and GB/T 3632 (torshear-type assemblies) set a 6-month shelf life; assemblies beyond 6 months may be reused after re-testing only if the as-delivered condition is intact.
DB11/T 1832.5-2023 "Construction work procedure specifications for building works, Part 5: steel structure works", Clause 11.1.5 (directly applicable in Beijing): storage shall not exceed six months; otherwise re-sample and re-test torque coefficient or fastening axial force, and use only if qualified.
Re-test content: large-hex assemblies - re-test torque coefficient; torshear assemblies - re-test fastening axial force (preload).
Supporting storage rules (JGJ 82-2011 Clause 6.1.4): store by batch number and size marked on the boxes, indoors, protected from rust, moisture, and dirt; opening boxes arbitrarily before installation is strictly prohibited - keeping the as-delivered condition is the premise of the "re-test and reuse" path after the deadline.
Applicable Boundaries
- Applies to high-strength large-hex-head and torshear bolt assemblies (incl. matched nuts and washers) in steel works.
- The 6-month shelf life is per GB/T 1231 and GB/T 3632; "re-test and reuse" after expiry presumes intact as-delivered condition (unopened, unrusted, unmixed lots).
- If opened, mixed, rusted, or with damaged surface treatment, the re-test-and-reuse path does not apply - scrap or return.
- Where a local standard exists (e.g., Beijing DB11/T 1832.5-2023), its wording matches this conclusion; local provisions take precedence in execution.
- Covers only overdue-storage re-testing; acceptance index values for torque coefficient/axial force (e.g., mean coefficient range) are in GB/T 1231, GB/T 3632, and JGJ 82 and outside this card.
Further Reading
- GB 50755-2012 Clause 5.4.2 (incoming inspection and storage).
- JGJ 82-2011 Clauses 6.1.4-6.1.5 and the referenced GB/T 1231, GB/T 3632.
- DB11/T 1832.5-2023 Clause 11.1.5 (Beijing basis).
- For acceptance values: JGJ 82-2011 test methods and criteria for torque coefficient and axial force (sampling, mean, standard deviation).