Drift pins and temporary (erection) bolt counts in steel-structure pre-assembly and high-strength bolt erection: GB 50205-2020 Clause 9.2.2, GB 50755-2012 Clauses 10.2.6 / 7.4.3

Two scenarios: (1) Physical pre-assembly (GB 50205-2020 Clause 9.2.2, GB 50755-2012 Clause 10.2.6): first use not fewer than 10% of the total number of bolt holes of drift pins for positioning, temporary bolts in one group of holes shall be not fewer than 20% of the number of bolt holes and not fewer than 2, and the plies shall be brought into close contact; bolt holes are checked with try pins - a try pin 1.0mm smaller than the nominal hole diameter passes >= 85% of each group of holes, and a try pin 0.3mm larger than the nominal bolt diameter passes 100%. (2) Site erection (GB 50755-2012 Clause 7.4.3): the number of erection bolts plus drift pins is determined by calculation of erection loads, shall be not less than 1/3 of the total number of erection holes, erection bolts shall be not fewer than 2, drift pins inserted should not exceed 30% of the number of erection bolts, and high-strength bolts must not double as erection bolts.

Applicable Codes

  • GB 50205-2020 · Standard for Acceptance of Construction Quality of Steel Structures 第9.2.2条
  • GB 50755-2012 · Code for Construction of Steel Structures 第10.2.6条
  • GB 50755-2012 · Code for Construction of Steel Structures 第7.4.3条

Topic Positioning

Count-control provisions for drift pins and temporary bolts (erection bolts) during physical pre-assembly and high-strength bolt site erection of building steel structures (GB 50205 / GB 50755 system). A general workmanship requirement in steel construction for preventing member displacement and ensuring ply contact and connection quality.

Core Conclusions

Two scenarios apply, with different figures - do not mix them:

Scenario 1: physical pre-assembly (shop / yard)

  • GB 50205-2020 "Standard for construction quality acceptance of steel structure works" Clause 9.2.2: "In physical pre-assembly, drift pins numbering not less than 10% of the total bolt holes should first be used for positioning, followed by temporary bolts for tightening. Temporary bolts in one group of holes shall be not fewer than 20% of the number of bolt holes and not fewer than 2." Inspection quantity: all pre-assembly units; method: visual inspection.
  • GB 50755-2012 "Code for construction of steel structures" Clause 10.2.6 (same requirement, supplemented): where multi-ply stacks are connected with high-strength or ordinary bolts, first use drift pins numbering not less than 10% of the total bolt holes for positioning, then tighten with temporary bolts; temporary bolts in one group of holes shall be not fewer than 20% of the bolt-hole count and not fewer than 2; "during pre-assembly the plies shall be brought into close contact".
  • Try-pin check of bolt holes (GB 50755-2012 Clause 10.2.6): (1) with a try pin 1.0mm smaller than the nominal hole diameter, the pass rate of each group of holes shall be not less than 85%; (2) with a try pin 0.3mm larger than the nominal bolt diameter, the pass rate shall be 100%.

Scenario 2: site erection (fastener-connection stage)

  • GB 50755-2012 Clause 7.4.3: when erecting high-strength bolts, erection bolts and drift pins shall be used first; the number inserted at each node is determined by calculation of the loads borne during erection and shall: (1) be not less than 1/3 of the total number of erection holes; (2) erection bolts not fewer than 2; (3) the number of drift pins inserted should not exceed 30% of the number of erection bolts; (4) high-strength bolts must not double as erection bolts.
  • Commentary points: drift pins position (tapered, mid-length diameter equal to the hole diameter); erection bolts clamp and eliminate gaps; high-strength bolts must not double as erection bolts to prevent thread damage and torque-coefficient drift from changed assembly surface condition.

Worked example (a group of 30 holes): pre-assembly: >= 3 drift pins, >= 6 temporary bolts; site erection: erection bolts + drift pins together >= 10, drift-pin cap = erection-bolt count x 30% - with 8 erection bolts, at most 2 drift pins (10 total); to place 3 drift pins, at least 10 erection bolts are needed (>= 13 total). Locations with few holes are backstopped by the "not fewer than 2" rule.

Applicable Boundaries

  • Applies to physical pre-assembly and high-strength bolt site erection of building steel structures (GB 50205-2020 / GB 50755-2012 system).
  • The site-erection "not less than 1/3 of erection holes" is the joint lower bound for erection bolts plus drift pins; drift pins are separately capped at "not more than 30% of erection bolts" - both must hold simultaneously.
  • Pre-assembly double-controls drift pins and temporary bolts at 10% and 20% (with >= 2) respectively - a different caliber from the site-erection 1/3 joint rule; do not confuse them.
  • Railway steel truss girder erection follows the stricter TB 10415-2018 (falsework method: drift pins + high-strength bolts >= 1/3 of total holes with drift pins making up 2/3, and not fewer than 6 where holes are few; cantilever method: drift pins >= half the holes, evenly arranged) - those figures do not apply here.

Further Reading

  • GB 50205-2020 "Standard for construction quality acceptance of steel structure works" Section 9.2 (steel member pre-assembly) - original text and inspection requirements of Clause 9.2.2.
  • GB 50755-2012 "Code for construction of steel structures" Clause 10.2.6 (pre-assembly, incl. try-pin pass rates) and Clause 7.4.3 (high-strength bolt erection) with their commentaries.
  • Railway-bridge extension: TB 10415-2018 "Standard for constructional quality acceptance of railway bridge and culvert engineering" Clause 11.2.5 (drift pin and high-strength bolt provisions for assembly on falsework / cantilever assembly); compare with the "key points of curved steel truss girder assembly and erection" card referenced here.