Engineering Knowledge Cards.
Confidence HighUpdated 2026-08-30

Erection of steel plate composite girders (steel-concrete composite beams): reference framework and construction safety operation points

Composite girder erection schemes are organized around four links: "temporary support checking — hoisting — splicing — deck slab casting": railway projects follow TB 10303-2020 Section 11.6 (safety) + TB 10415-2018 Section 11.2 (quality acceptance); municipal works follow CJJ 2-2008 Chapter 15 (construction supports must simultaneously account for the concrete structure and construction loads); operational details reference ZJQ08-SGJB 018-2018 Chapter 13. Key figures: high-strength bolt pair torque-coefficient retest average 0.110~0.150 with standard deviation no more than 0.0100 (15~25 C, RH 50%~70%, 2 h+ in the environment, retest if stored over 6 months, at least 8 pairs per batch); support assembly drift pins + high-strength bolts >= 1/3 of total holes (pins 2/3, at least 6 at sparse-hole locations), cantilever pins >= 1/2 of holes; 25% of site-welded transverse tension butt welds radiographic-tested; twin-crane lifting end height difference <= 30 cm; cantilever assembly counterweight-beam overturning stability factor > 1.3; 4 jacks per intermediate support, stroke <= 80% of effective stroke.

Applicable Codes

  • TB 10303-2020 铁路桥涵工程施工安全技术规程
  • TB 10415-2018 铁路桥涵工程施工质量验收标准
  • CJJ 2-2008 城市桥梁工程施工与质量验收规范
  • ZJQ08-SGJB 018-2018 桥梁工程施工技术标准
  • GB/T 1231 钢结构用高强度大六角头螺栓、大六角螺母、垫圈技术条件
  • GB 50917-2013 钢-混凝土组合桥梁设计规范
  • DB11/T 1885-2021 桥梁工程施工安全技术规程
  • DBJ 43/T 302-2024 预制拼装桥梁技术标准

Topic Positioning

A quick reference for the standards framework of steel plate composite girder (steel-concrete composite beam) erection: the division of labor among railway/municipal/local/enterprise standards, and the key safety, quality, and operational points of the four links "temporary support checking — hoisting — splicing — deck slab casting" (including bolt retest, drift-pin counts, stud weld acceptance figures).

Core Conclusions

  1. Railway safety: TB 10303-2020 "Technical code for safety of railway bridge and culvert construction" Section 11.6 — before hoisting, check the strength, stiffness, and stability of temporary supports and the steel girder structure under different loading states; use dedicated lifting appliances; the girder must not twist, warp, or tilt laterally; high-strength bolt splicing per Section 11.2; welding shielded from wind, box-girder interior welding ventilated and protected; cast-in-place deck casting sequence and concrete strength age during girder lowering per design, continuous composite beams cast in segments per positive/negative moment; inspection items per Table 11.6.4 (including pre-shift safety talks 3.0.12, over-water work 16.2, lightning protection 11.1.8, construction power 11.1.6/11.1.10, severe weather 11.1.9, major-hazard construction-condition acceptance 11.1.2).
  2. Railway quality acceptance: TB 10415-2018 "Standard for constructional quality acceptance of railway bridge and culvert engineering" Section 11.2 steel girder assembly and erection — 11.2.1 factory-made girder dimensions, welds, base coating, shear connector quantity and quality, site bolted plate surfaces, and site-weld joint end grooves must comply with design and related standards (fully checked by construction and supervision); 11.2.2 site welds must meet design and welding-procedure requirements, the contractor performs ultrasonic testing and radiographic-tests 25% of site-welded transverse tension butt welds; 11.2.3 before bolted assembly, test the slip-factor specimens shipped with the girder — assembly only when meeting design; 11.2.4 after arrival, promptly re-test high-strength bolt pairs for specification, quality, and torque coefficient: average 0.110~0.150, standard deviation no more than 0.0100; re-tests preferably at 15~25 C and RH 50%~70%, with testing instruments and bolt pairs kept in that environment 2 h or more; re-test if stored on site over 6 months; check in batches of at least 8 pairs per manufacturer lot number, complying with GB/T 1231; 11.2.5 when assembling on supports, drift pins + high-strength bolts total no less than 1/3 of holes, with pins 2/3, and no fewer than 6 at sparse-hole locations; in cantilever assembly, pins at joints are determined by the load carried but no fewer than half the holes, with bolts in the rest, evenly distributed; 11.2.6 site-welded shear connectors (studs): absent design requirements, the average weld height along the stud axis >= 0.2 x diameter and minimum >= 0.15 x diameter, average peripheral weld diameter >= 1.25 x stud diameter, longitudinal root and top deviations within +/-3 mm, transverse root +/-3 mm and top +/-5 mm.
  3. Municipal system: CJJ 2-2008 "Code for construction and quality acceptance of urban bridge engineering" Chapter 15 — construction supports must simultaneously account for the concrete structure and construction loads in addition to girder splicing loads (15.2.2); municipal safety follows CJJ/T 275-2018 and JGJ 266-2011 (bridge-erecting machine trial-lift weight no less than the actual lifted weight).
  4. Local and enterprise standards: DB11/T 1885-2021 (Beijing) Chapter 20 requires composite-beam supports/formwork/rebar/prestress/concrete works to comply with the corresponding chapters; DBJ 43/T 302-2024 Section 7.6 specifies composite girder fabrication per CJJ 2, JTG/T D64-01, JTG/T 3650; ZJQ08-SGJB 018-2018 "Technical standard for bridge engineering construction" Chapter 13 has the finest operational details — 13.7.2 during hoisting the girder must not twist, warp, or topple; keep beam synchronization, stable packing, correct seating; 13.7.3 full framing assembly must consider support foundation settlement and support deformation when adjusting girder camber, reserving positions for camber adjustment and jacking; cantilever assembly requires a counterweight beam and a main-member assembly sequence diagram, with the counterweight-beam overturning stability factor > 1.3; also twin-crane lifts with end height difference <= 30 cm, 4 jacks per intermediate support with stroke <= 80% of effective stroke, safety timber stacks under jacked girders, and cleaning of rust and oil from shear connector surfaces before deck casting.
  5. Design basis: GB 50917-2013 "Code for design of steel and concrete composite bridges" (road simply supported composite girder bridges with single span <= 120 m; Clause 4.2.2 is mandatory), GB 50017-2017 Chapter 14, GB 55004-2021 "General code for composite structures" (composite deck systems must consider member length and weight against the erection scheme and lifting equipment to prevent excessive deformation during transport and erection).

Applicable Boundaries

Select by system: railway projects follow the two railway codes (high-speed rail uses TB 10752-2018, whose clauses correspond to TB 10415's chapters); highway projects follow JTG/T D64-01 "Specification for design and construction of highway steel-concrete composite bridges", JTG D64, JTG/T 3650; municipal projects follow CJJ 2-2008 and CJJ/T 275-2018; local safety codes per the project location. The enterprise standard ZJQ08-SGJB 018, its counterweight-beam stability factor > 1.3, and twin-crane height difference <= 30 cm are operational references and cannot replace mandatory codes; deck precast lifting points, wet joints, and prestress tensioning still follow the design documents; the bolt torque-coefficient retest environment (15~25 C, RH 50%~70%, 2 h+ conditioning) and 6-month storage re-test are railway-system acceptance provisions of TB 10415.

Further Reading

TB 10303-2020 Section 11.6 (incl. Table 11.6.4 composite beam erection safety checklist); TB 10415-2018 Chapter 11, 11.2.1~11.2.6 (steel girder assembly dominant items, incl. torque-coefficient retest, drift-pin counts, stud weld dimensions); CJJ 2-2008 Chapter 15, 15.2.2; DB11/T 1885-2021 Chapter 20; DBJ 43/T 302-2024 Section 7.6; ZJQ08-SGJB 018-2018 Chapter 13, 13.4.2, 13.7.2, 13.7.3; bolt retest basis GB/T 1231 "Specifications of high strength bolts with large hexagon head, large hexagon nuts and plain washers for steel structures". For the highway system, see JTG/T D64-01 and "Technical specification for construction of highway bridges and culverts" JTG/T 3650.

Keywords

Cited By