Girder erection safety risk control (bridge-erecting machine placement of precast girders): hazard identification and five-layer control points

Erection control is implemented in five layers, "method statement acceptance -> equipment -> girder transport -> erection -> personnel and environment": erection requires a dedicated method statement for high-risk works and acceptance of construction conditions for major hazard sources (expert panel review when height > 10 m / single span > 20 m / single girder > 600 kN); erecting-machine stability factor >= 1.3 during erection and >= 1.5 during span crossing; transport limited to <= 5 km/h on ordinary sections, <= 3 km/h in tunnels and on curves and ramps, <= 3 m/min near the machine's legs; loaded girder same-end support height difference <= 2 mm; stop loading and transporting in force-6 winds.

Applicable Codes

  • TB 10303-2020 铁路桥涵工程施工安全技术规程
  • CJJ/T 275-2018 市政工程施工安全检查标准
  • DB11/T 1885-2021 桥梁工程施工安全技术规程
  • DBJ/T 15-140-2018 广东省市政基础设施工程施工安全管理标准
  • GB 26469 架桥机安全规程
  • GB/T 28264 起重机械安全监控管理系统

Topic Positioning

This card summarizes the mandatory safety-control requirements for precast girder erection (bridge-erecting machine + girder transporter) under the railway and municipal systems: hazard identification lists, dedicated method statements for high-risk works and acceptance procedures, and equipment and process control parameters — for compiling dedicated method statements for high-risk works, safety inspections, and risk briefings.

Core Conclusions

Control in five layers: (1) Method statement and acceptance: erection must have a dedicated method statement for high-risk works reviewed and approved; where a major hazard, construction-condition acceptance is organized as required; erecting-machine method statements with height > 10 m, single span > 20 m, or single girder > 600 kN require expert panel review (CJJ/T 275-2018); before implementation, written safety briefings are recorded, and modifications must be re-reviewed. (2) Equipment: erecting machines must have manufacturing licenses, certificates, and registration, pass load tests, and be fitted with safety monitoring per GB/T 28264 before use; complete safety devices — load limiter, leg mechanical locking, anti-wind anti-slip, interlock protection, anemometer — checked before each shift with records. (3) Transport: girder supports kept on one plane, same-end height difference <= 2 mm, longitudinal deviation <= 10 mm, transverse <= 5 mm; uniform speed loaded — <= 5 km/h on ordinary sections, <= 3 km/h in tunnels/curves/ramps, <= 3 m/min approaching the machine's legs; a dedicated guide ahead, one full stop before approaching the machine, sudden braking forbidden. (4) Erection: erecting-machine overturning stability factor >= 1.3 during erection and >= 1.5 during span crossing with the trolley in the stable position; synchronization test of the carrying trolley and lifting trolley before feeding; legs vertically packed, lifted synchronously; piers fitted with railings, cages, and stairs. (5) Environment: stop loading and transporting at force-6 winds and above; protection across roads and waterways; anti-slip in rain, snow, and ice; winter anti-slip and insulation.

Applicable Boundaries

Railway projects follow TB 10303-2020 Chapter 6 (box girders) and Chapter 7 (T girders), whose hazards and requirements differ slightly; municipal projects reference CJJ/T 275-2018 Clause 8.4.3 assurance-item evaluation and the use provisions of DB11/T 1885-2021 and DBJ/T 15-140-2018. The parameters are code minimums — stricter design documents govern; precast girder fabrication, prestress tensioning, and special provisions for erecting over operating lines are not covered.

Further Reading

TB 10303-2020 Sections 6.1, 6.5, 7.1; CJJ/T 275-2018 Clause 8.4.3 erecting-machine assurance items; DB11/T 1885-2021 Clause 30.2.15; DBJ/T 15-140-2018 Clause 9.11.9. Companion standards: GB 26469 "Safety regulations for bridge erecting machines", GB/T 28264 "Managing and monitoring system of safety for lifting appliances", GB/T 5905 load tests.