Management of sub-divisional works involving significant hazards - overview: scope determination, dedicated method statement with dual-signature approval, expert review, implementation, monitoring and acceptance, three-party liabilities (MOHURD Order No. 37 framework)
The hazardous-works chain: scope per MOHURD Order No. 37 plus the Jian Ban Zhi [2018] No. 31 lists, with expert panel review beyond the scale line; the dedicated scheme is compiled before construction (organised by the main contractor; a specialist subcontractor may compile), with safety calculations attached; dual sign-off gives it effect (art. 11): the contractor's technical director plus the chief supervising engineer. The panel: at least five experts from the local authority's panel, interested persons excluded, tri-state conclusion (arts. 12-13). Implementation: two-stage briefing plus the safety-condition check; the supervisor compiles a dedicated plan and patrols, reporting to the housing authority if the contractor refuses to rectify (arts. 18-19); after acceptance passes and the project technical leader and chief supervising engineer sign, the next process may begin (art. 21). Supervisory defaults draw an order to correct plus RMB 10,000-30,000, and RMB 1,000-5,000 on the responsible person (art. 37).
Applicable Codes
- 住建部令第37号(第47号令修正)危险性较大的分部分项工程安全管理规定(第十至十三、二十一、三十六、三十七条)
- 建办质〔2018〕31号 关于实施危大工程安全管理规定有关问题的通知(范围清单与论证组织)
- GB/T 50319-2013 建设工程监理规范
- GB/T 50502-2009 建筑施工组织设计规范
An entry card for the domain of sub-divisional works involving significant hazards ("wei-da gongcheng"): it strings together the whole procedure chain — scope identification → dedicated scheme compilation → dual sign-off approval → expert panel review → briefing and implementation → condition checks → acceptance → liabilities and penalties — the system being rooted in MOHURD Order No. 37 (as amended by Order No. 47) and its implementing notice Jian Ban Zhi [2018] No. 31. What readers look up most: what counts as hazardous and what exceeds the scale thresholds; who compiles and who approves the dedicated scheme; how the expert panel is convened and what happens on failure; who signs at acceptance; and what the supervisor and the contractor each answer for, at what fines. The card gives the procedural framework and navigates this domain's cards.
Concept and mechanism
System position and identification. The regime consists of MOHURD Order No. 37 on the safety management of sub-divisional works with relatively high safety risks (as amended by Order No. 47) and Jian Ban Zhi [2018] No. 31 (scope lists and implementation requirements), and applies to building and municipal-infrastructure works. Identification is two-layered: sub-divisional works on the hazardous-works list (excavation retention and dewatering, formwork, lifting and hoisting, scaffolding, demolition and blasting, underground excavation, etc.) must have a dedicated method statement; those beyond the stated scale additionally require expert panel review — the exact scopes and scale lines follow the annex to the 2018 notice, and local standards may only tighten the national lines, never relax them.
Compilation and approval. The contractor must organise its engineering and technical personnel to compile the dedicated scheme before construction of the hazardous works begins (art. 10); under main contracting the main contractor organises compilation, and where the works are subcontracted the relevant specialist subcontractor may compile. The required contents follow the general nine-item framework, with special requirements for deep excavations, high formwork and lifting, plus the safety-calculation results. Dual sign-off gives the scheme effect (art. 11): the contractor's technical director checks and signs with the company seal, and the chief supervising engineer reviews and signs with the practitioner's seal; where a subcontractor compiled it, the main and specialist contractors' technical directors jointly check and sign with their company seals.
Expert panel review. For hazardous works beyond a certain scale, the contractor must convene the expert panel (the main contractor where main contracting applies), and before the panel sits the scheme must have passed the contractor's own check and the chief supervising engineer's review (art. 12). Experts are drawn from the panel established by the local housing and urban-rural development authority, meet the professional requirements and number not fewer than five; persons with an interest in the works may not sit as experts. Attendees include the experts, the employer's project leader, the survey and design units' project technical leaders, the main and specialist contractors' technical directors (or authorised persons), the project leader and project technical leader, the compiler, the full-time safety officers, and the chief supervising engineer and supervising engineers. The conclusion is tri-state (art. 13): pass; pass after revision — revise per the panel report and re-run the art. 11 procedure; or fail — revise and reconvene the panel. The experts sign and answer for the panel report; breaches of the review procedure carry separate penalties.
Implementation and acceptance. Before construction: two-stage briefing and a check of the construction-safety conditions (the contractor inspects, the supervisor audits, the result goes to the employer for confirmation, and changed conditions re-trigger the check), with the hazardous-works notice board posted on site and the project leader leading on site. The supervision organisation compiles a dedicated supervision implementation plan and makes dedicated patrol inspections of the hazardous works; on finding work off-scheme it requires rectification or suspension, and where the contractor refuses to rectify or stop, it reports to the employer and the local housing authority (arts. 18-19). Hazardous works requiring acceptance are accepted by the contractor and the supervisor with the relevant personnel (the main and specialist contractors' technical directors, the project leader and project technical leader, the compiler, the full-time safety officers, the chief supervising engineer and supervising engineers, and the survey, design and monitoring units' project technical leaders); only after acceptance has passed and the contractor's project technical leader and the chief supervising engineer have signed confirmation may the next process begin (art. 21), with the acceptance sign board posted prominently on site showing the acceptance time and responsible persons; panel-review results, the supervision implementation plan, patrol records, and acceptance and rectification documents all go into the hazardous-works safety management file.
Liabilities and penalties. Supervision side (arts. 36-37): where the chief supervising engineer failed to review the dedicated scheme as required, failed to require rectification or suspension upon finding work off-scheme, or failed to report when the contractor refused to comply, the unit is punished under the Work Safety Law and the Regulation on Work Safety Management of Construction Projects, and the directly responsible person is fined RMB 1,000-5,000; failing to compile the dedicated supervision plan, to make the dedicated patrols, to participate in organising acceptance as required, or to keep the hazardous-works file draws an order to correct within a time limit plus a fine of RMB 10,000-30,000, and RMB 1,000-5,000 on the directly responsible person. Contractor side: failing to compile, review by panel, approve, implement, brief or accept the dedicated scheme as required is punished under the corresponding articles of Order No. 37; and an employer failing to pay the statutory safety provisions on time bears corresponding responsibility for accidents so caused.
International mapping (FIDIC)
FIDIC contracts have no counterpart to China's hazardous-works regime: no graded list of sub-divisional works, no mandatory expert panel review, and no dual sign-off approval within the contract machinery. Construction safety is handled overall as the contractor's contractual obligation, and government-mandated supervision enters through the obligation to comply with applicable Laws.
| Chinese institution | FIDIC mechanism | Relation | Point |
|---|---|---|---|
| Hazard list + dedicated scheme | Sub-Clause 4.8 [Health and Safety Obligations] | distinct | the Contractor complies with applicable health-and-safety regulations and the contractual safety obligations, cares for the health and safety of everyone on site, keeps the site free of unnecessary obstruction, and provides fencing, lighting, safe access and guarding, and temporary protection for the public and adjoining property |
| Expert panel review (administrative procedure) | no counterpart; absorbed via compliance with local law | distinct | 4.8 requires compliance with all applicable health and safety regulations and Laws — the host country's mandatory safety procedures enter the contract here |
| Scheme submission / dual sign-off | the safety manual under 4.8 (submitted within 21 days) | adjacent | within 21 days after commencement, and before starting work on site, the Contractor submits a safety manual prepared specifically for the works — for the Engineer's information, not an object of approval |
| Safety check on variations | Clause 13.1 right to object to a variation | adjacent | new in the 2017 editions: the Contractor may object to a variation instruction that would adversely affect its obligations under 4.8 |
Usage warning: do not assume the "dual sign-off + expert panel" procedure exists when reading a FIDIC contract — the Engineer requires only that the safety manual be submitted for information and has no power to approve it; safety responsibility is carried by the contractor's obligations, the applicable law and the Employer's Requirements. Where a FIDIC-type form is chosen for a domestic project, hazardous-works controls must be built into the Particular Conditions — the Order No. 37 administrative procedure does not flow into the contractual machinery by itself.
Card-group navigation
Identification and scope
- Hazardous-works and beyond-scale scopes: identification and the panel-review requirements (card_b5c12d8f)
- Which works need a dedicated method statement: a layered test (card_4017bb4a)
- Local lines extending the national scope (the Xi'an rules as an example) (card_f78eb891)
Scheme compilation
- The high-risk scheme chain: compile, check, approve — who does what (card_fa62024d)
- Required contents of high-risk schemes: nine general items plus the specials (card_1728c4ab)
- The eleven emergency-response items of a high-risk scheme (card_f2e2910e)
- The safety-assurance trio for high-risk schemes (card_ed0317ab)
- AI-assisted scheme drafting: the statutory sign-off chain and human review (card_981d683e)
- Spotting obvious gaps in a method statement (card_60363ca0)
Expert panel review
- Before the panel sits: document preparation and organisational requirements (card_4b202163)
- When the panel says no (fail / pass after revision): the handling procedure and the penalties (card_497b9f63)
Implementation and adjustment
- Pre-construction technical and safety procedures for hazardous works: the full chain (card_ae289ff9)
- The project leader's statutory duties during hazardous works and the consequences of breach (card_a60d2f09)
- High-risk schemes after design or construction-condition changes: re-check and re-review by the panel (card_a9d9d453)
- Re-approval after construction-condition changes: ordinary vs high-risk, graded handling (card_35830741)
- May the method statement survive a design change? Graded answers (card_efb9f06a)
- Technical briefing vs method statement vs actual practice: the hierarchy of force (card_34736416)
Acceptance and records
- After acceptance passes: forming and archiving the records (card_54acc44b)
Penalties and related
- No high-risk scheme compiled: legal liability and penalties (card_5049b47c)
- The supervisor's review of execution plans and (dedicated) method statements (card_e1220a72)
- Crew sizing for a method statement (card_d8c67a12)
- The three tiers of plan documents: the full content checklist (card_396e4d0f)
- Girder-erection safety risk control (card_db1362f2)