Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Content composition of safety assurance measures in construction schemes: the seven-item safety-management plan framework and the three-piece set of dangerous sub-part special schemes

Safety assurance measures of ordinary construction schemes are compiled per the seven items of the safety-management plan of GB/T 50502-2009 Clause 7.4.2 (hazard identification and safety objectives, organization and responsibilities, safety resource allocation, management systems and education/training, safety-technical measures, seasonal measures, safety inspection and accident handling); the standard caliber of "construction safety assurance measures" in special schemes for dangerous sub-part works consists of three parts — organizational safeguards, technical measures, and monitoring/surveillance — with specific measures additionally including emergency plans, etc.

Applicable Codes

  • GB/T 50502-2009 建筑施工组织设计规范
  • 建办质〔2021〕48号 危大工程专项施工方案编制指南
  • T/CBDA 35-2019 建筑装饰装修工程施工组织设计标准
  • JGJ 59-2011 建筑施工安全检查标准
  • JGJ 33-2012 建筑机械使用安全技术规程

Topic Positioning

Answers "what the safety assurance measures in a construction method statement should contain", giving directly applicable lists at two levels: ordinary construction method statements and dedicated method statements for sub-divisional works involving significant hazards.

Core Conclusions

Ordinary method statements are written per the seven items of the safety-management plan of GB/T 50502-2009 Clause 7.4.2: (1) hazard identification and occupational health and safety management objectives; (2) safety-management organization and responsibilities; (3) safety resource allocation; (4) work-safety management systems and staff education/training systems; (5) safety-technical measures targeting the hazards (sub-divisional works involving significant hazards and special trades require separate dedicated safety-technical measure plans); (6) seasonal safety measures; (7) safety inspection systems and accident-handling provisions. The "construction safety assurance measures" of dedicated method statements for sub-divisional works involving significant hazards (Jianban Zhi [2021] No. 48) are a three-part set: organizational safeguard measures, technical measures, and monitoring/surveillance measures (deformation monitoring and early warning of supports and of adjacent buildings/structures and pipelines), and may additionally include emergency plans (T/CBDA 35-2019 Clause 7.1.3). The complete nine items of dedicated method statements are: project overview, basis of preparation, construction plan, construction technology, construction assurance measures, staffing and division, acceptance requirements, emergency-response measures, calculation books and drawings.

Applicable Boundaries

Ordinary method statements use the seven-item framework; dedicated method statements for sub-divisional works involving significant hazards must be prepared specifically per the three-part set and incorporated into the nine-item framework. JGJ 59-2011 lists the work-safety responsibility system, dedicated method statements, safety-technical disclosure, safety inspection, safety education, and emergency rescue as assurance items for inspection and assessment; signatures must be completed during implementation. Specialized method statements have dedicated content (e.g., lifting-machinery method statements include process details such as wire-rope routing and winch fixing, JGJ 33-2012 Clause 4.5.3).

Further Reading

GB/T 50502-2009 Clauses 7.1.1, 7.4.2; Jianban Zhi [2021] No. 48 "Guide for preparing dedicated method statements for sub-divisional works involving significant hazards"; T/CBDA 35-2019 Clauses 7.1.2, 7.1.3, 5.9.3; JGJ 59-2011 Clauses 3.1.2, 3.1.3; JGJ 33-2012 Clause 4.5.3.