Mandatory content of dedicated safety construction schemes for higher-risk works: the 9-item general framework and specific requirements for deep excavations, high formwork supports and lifting operations
Per the Compilation Guide for Dedicated Safety Construction Schemes of Higher-risk Works (Jian Ban Zhi [2021] No. 48), such a scheme must contain 9 general items: project overview, compilation basis, construction plan, construction technology, assurance measures, staffing and division of duties, acceptance requirements, emergency response, and calculation sheets with drawings; deep excavations (JGJ 311-2013, Clause 5.2.2, 8 items, plus the mandatory national code GB 55003-2021, Clause 7.4.1), high formwork supports (GB 50666-2011, Clause 4.1.1, plus HNLJQ-SGJB 001-2021, Clauses 4.5.1/4.8.1/4.9.1) and lifting operations (JGJ 33-2012, Clause 4.5.3, 7 items) each have their own specific content requirements.
Applicable Codes
- 建办质〔2021〕48号 危险性较大的分部分项工程专项施工方案编制指南
- JGJ 311-2013 建筑深基坑工程施工安全技术规范
- GB 55003-2021 建筑与市政地基基础通用规范
- GB 50666-2011 混凝土结构工程施工规范
- HNLJQ-SGJB 001-2021 高大模板支撑系统施工方案编制与实施技术标准
- JGJ 33-2012 建筑机械使用安全技术规程
- T XCIA 3-2023 危险性较大的分部分项工程施工安全管理规程
Topic Positioning
This card summarizes the mandatory content of dedicated safety construction schemes for higher-risk works: first the general framework covering all higher-risk works, then the specific requirements for deep excavations (excavation works), high formwork supports (formwork support systems) and lifting operations - directly usable as a scheme-preparation checklist and for compliance checks.
Core Conclusions
I. General framework - 9 items (applicable to all higher-risk works) - per the MOHURD Office Compilation Guide for Dedicated Safety Construction Schemes of Sub-divisional Works with Relatively High Risk (Jian Ban Zhi [2021] No. 48; likewise T XCIA 3-2023, Clause 5.2.3): 1 Project overview: characteristics of the higher-risk works, site and surrounding environment, construction layout, construction requirements, hazard identification and grading, responsible parties of all participants and technical assurance conditions; 2 Compilation basis: relevant laws and regulations, standards and codes, normative documents, project design documents, the special design (only for works subject to special design), construction contract, project execution plan, etc.; 3 Construction plan: construction schedule, materials and equipment plan, labor plan; 4 Construction technology: technical parameters, process flow, construction methods, operation requirements, use requirements, inspection requirements; 5 Construction assurance measures: organizational assurance, technical measures, monitoring and measuring measures; 6 Site management and staffing: construction management personnel, full-time safety officers, special-operation personnel and other workers; 7 Acceptance requirements: acceptance criteria, procedures, content and personnel; 8 Emergency response: composition and duties of the emergency leadership group and rescue groups (rescue, security, logistics, medical aid, aftercare; rescue workflow and countermeasures; contact numbers), emergency events (major hazards and accidents) and countermeasures, contact details of the owners of adjacent buildings/structures, roads and underground utilities, rescue hospital information (name, phone, rescue route), and emergency supplies; 9 Calculation sheets and relevant drawings.
II. Deep excavation schemes - JGJ 311-2013, Clause 5.2.2, 8 items: (i) project overview (excavation location, scale, safety grade, site investigation and environmental survey results, retaining structure type with drawings); (ii) geotechnical and hydrogeological conditions and analysis of factors adverse to construction safety; (iii) hazard source analysis (safety of the excavation itself, safety of the surroundings, safety of construction equipment and personnel); (iv) safety-technical measures matched to hazard control at each construction stage (hazard control for retaining structure construction, support system installation and removal, earthwork excavation, dewatering, etc.; power supply, fire, typhoon and flood safety measures at each stage; safety measures for large construction machinery at each stage); (v) implementation rules of the observational (informational) construction method (release, analysis, decision and command system for monitoring results); (vi) safety-control technical measures and contingency plans; (vii) safety management measures (safety organization and personnel education/training); (viii) emergency response mechanism for sudden events (information reporting, initial handling, activation and termination). The mandatory general engineering code GB 55003-2021, Clause 7.4.1: before excavation works begin, a dedicated construction scheme shall be prepared covering technical parameters of the retaining structure, groundwater control, earthwork excavation and backfill, the construction process flow, construction methods, safety-technical measures, emergency plans and monitoring requirements; the project execution plan or dedicated scheme shall be complete, accurate and operable, and may be implemented only after approval. Deep-excavation schemes must satisfy both JGJ 311-2013 and GB 55003-2021.
III. High formwork supports (formwork support systems) - GB 50666-2011, Clause 4.1.1, plus HNLJQ-SGJB 001-2021, Technical Standard for Preparation and Implementation of Tall Formwork Support System Construction Schemes: The overview must state the supported area, elevation, height, beam cross-section dimensions, spans, slab thicknesses and support foundation conditions; the calculation sheets (Clause 4.8.1) mainly cover: section properties of the formwork and support system, design values and combinations of all loads, beam side-formwork force calculations, strength and stiffness calculations of beam and slab support systems, stability of uprights under beams and slabs, bearing verification of upright foundations, of the supported floor and of the floor below transfer levels - each calculation with a calculation sketch and cross-section detail noting member sizes, specifications and longitudinal/transverse support spacing; the construction drawings (Clause 4.9.1) mainly include: layout plans of uprights and longitudinal/transverse horizontal tubes in the supported area, elevation and section views of the support system, layout plans of horizontal diagonal bracing and projected layouts of vertical bracing, beam and slab formwork details, monitoring layout plans of the support system, and positions and details of wall-tie connections; the construction safety assurance measures (Clause 4.5.1) mainly include: the support pre-loading organization design, the management organization for the formwork erection and concrete-pouring zones, construction technical measures, safety-technical measures for formwork installation and removal, and monitoring measures during erection, reinforcement installation, concrete pouring and before/after final setting. Sliding formwork, climbing formwork and other tool-type forms, and tall formwork works, require technical demonstration.
IV. Lifting operations (construction hoisting machinery) - JGJ 33-2012, Clause 4.5.3, 7 items: (i) project overview and construction layout; (ii) compilation basis (laws and regulations, normative documents, standards and codes, drawings and national standard detail albums, project execution plan, etc.); (iii) construction plan; (iv) technical parameters and process flow (wire-rope routing and fixing methods, winch fixing positions and methods, mast-crane base installation and fixing, etc.); (v) construction safety-technical measures (organizational assurance, technical measures, emergency plans, monitoring, inspection and acceptance, etc.); (vi) labor plan (full-time safety officers, special-operation personnel, etc.); (vii) calculation sheets and relevant drawings.
Applicable Boundaries
The 9-item general framework applies to all higher-risk works; the three sets of specific requirements apply respectively to deep excavation works, formwork support systems and lifting operations. Whether the scheme requires expert review follows the exceeding-scale criteria for higher-risk works (e.g., excavation depth of 5 m or more, formwork support height of 8 m or more or span of 18 m or more - see Jian Ban Zhi [2018] No. 31, Annex 2 and local supplements). GB 55003-2021 is a fully mandatory engineering construction code, and excavation schemes must meet its Clause 7.4.1; HNLJQ-SGJB 001-2021, DB13(J) T 8377-2020 etc. are local technical standards - where the project location provides otherwise, those provisions govern.
Further Reading
See the Compilation Guide for Dedicated Safety Construction Schemes of Sub-divisional Works with Relatively High Risk (Jian Ban Zhi [2021] No. 48); T XCIA 3-2023, Clause 5.2.3; JGJ 311-2013, Technical Code for Safety of Construction of Building Deep Excavation Works, Clause 5.2.2; GB 55003-2021, General Code for Foundations of Buildings and Municipal Engineering, Clause 7.4.1; GB 50666-2011, Code for Construction of Concrete Structures, Clause 4.1.1; HNLJQ-SGJB 001-2021, Clauses 4.5.1, 4.8.1 and 4.9.1; JGJ 33-2012, Specification for Technical Safety of Building Machinery Use, Clause 4.5.3; for the exceeding-scale scope see the annexes of Jian Ban Zhi [2018] No. 31 and local appendices.