Erection sequence for multi-story / high-rise steel structures: zone-level "survey -> correct -> initial bolt tightening" vs overall-level "overall correction -> final tightening -> welding -> post-weld re-survey" (DB11/T 1832.5-2023 Clause 10.4.2, JGJ 276-2012 Clause 6.3.4)
Multi-story / high-rise steel structures are organized as "parallel zone erection + height-wise flow segments": after a zone is erected, first perform survey, correction, and initial tightening of high-strength bolts; only after several zones are erected are the overall survey, correction, bolt substitution, initial and final tightening, and welding done, followed by post-weld re-survey before erecting the next column tier. Welding and overall final tightening are not done at zone level, to avoid accumulated deviation from welding before correcting (DB11/T 1832.5-2023 Clause 10.4.2); overall frame correction follows completion of hoisting in the main flow segments and covers axes, elevation, and plumbness, and only after tabulating data and passing intermediate acceptance may high-strength bolt tightening begin (JGJ 276-2012 Clause 6.3.4).
Applicable Codes
- DB11/T 1832.5-2023 建筑工程施工工艺规程 第5部分:钢结构工程 第10.4.2条
- JGJ 276-2012 建筑施工起重吊装工程安全技术规范 第6.3.4条
Topic Positioning
Hoisting organization and work sequence for erecting multi-story / high-rise steel structures: parallel zone erection, flow-segment division, and the ordering between zone-level steps (survey -> correction -> initial tightening of high-strength bolts) and overall-level steps (overall correction -> bolt substitution -> initial / final tightening -> welding -> post-weld re-survey -> next tier erection). Based on Clause 10.4.2 of DB11/T 1832.5-2023 "Construction work procedure specifications for building works, Part 5: steel structure works" and Clause 6.3.4 of JGJ 276-2012 "Code for safety technology of building hoisting and lifting operations".
Core Conclusions
Key points of DB11/T 1832.5-2023 Clause 10.4.2 (hoisting sequence of steel members): 1 Hoisting areas shall be delineated and steel hoisted in parallel order by area; after one zone is hoisted, surveying, correction, and initial tightening of high-strength bolts shall be carried out; after several zones are erected, the overall surveying, correction, substitution, initial and final tightening of high-strength bolts, and welding are performed; after the post-weld re-survey, hoisting of the next column tier proceeds, along with lifting and partial laying of this tier's metal deck as site conditions allow. 2 The allowable offset of embedded bolt centers is preferably +/-5mm, and of bearing surfaces +/-3mm. 3 Divide flow segments by height for the whole building, preferably one frame section per tier (one column, N floors); within each segment divide flow zones on plan: the concrete core and tower-crane climbing zone as the main flow zone, the remainder as secondary; with two or more tower cranes, divide areas by operating radius, placing principal parts in the earlier zones.
Process chain (flow logic): zone hoisting complete -> (1) survey (axes / elevation / plumbness) -> (2) correction -> (3) initial tightening of high-strength bolts -> (after several zones erected) -> (4) overall survey and correction -> (5) bolt substitution, initial and final tightening -> (6) joint welding -> (7) post-weld re-survey -> (8) next column-tier hoisting (this tier's metal-deck lifting / laying). Welding and overall final tightening are not done at zone level - the zone only does "survey, correction, initial tightening" to form a stable frame; once several zones (flow segments) form a whole, correct and weld uniformly, avoiding accumulated deviation from welding before correcting.
Key points of JGJ 276-2012 Clause 6.3.4: overall frame correction follows completion of hoisting in the main flow segments. Correction covers axes, elevation, and plumbness; reference columns: square frames take the 4 corner columns, rectangular frames take 6 columns when the aspect ratio exceeds 2, polygonal frames take the corner columns; reference columns are plumbed by laser theodoliter from datum points and corrected at the top, other columns corrected by measurement. After frame correction, tabulate the data and obtain an intermediate acceptance verdict before high-strength bolt tightening begins.
Flow-segment details (commentary to Clause 10.4.2): multi-story / high-rise steel structures must be divided height-wise into flow segments, one frame section per tier (one column, N floors); hoisting must ensure both the stiffness of each frame section and frame stability during climbing of self-climbing (especially internal-climbing) tower cranes; columns are usually sectioned every 2-3 floors, shortened for heavy bottom-tier columns.
Applicable Boundaries
- Applies to multi-story and high-rise steel erection; DB11/T 1832.5-2023 is a Beijing local standard mandatory within Beijing and referential elsewhere (local valid standards take precedence).
- Single-story portal frames and long-span structures are not covered - consult the corresponding chapters and other codes.
- JGJ 276-2012 Clause 6.3.4 also notes: no explicit national rules yet govern high-rise steel erection correction quality, so tolerances are set by the designer per project with reference to relevant provisions - execution follows the design documents and the approved work plan.
- If the hoisting qualifies as a larger-than-standard-risk project, the special work plan must be prepared and approved before hoisting.
Further Reading
- DB11/T 1832.5-2023 Clause 10.4.2 and Figure 10.4.1 (flow chart of multi-story / high-rise erection); Chapter 11 of the same code has matching workmanship clauses on high-strength bolting and welding.
- JGJ 276-2012 "Code for safety technology of building hoisting and lifting operations" Clause 6.3.4 (steel hoisting chapter).
- Tightening stages (initial -> re- -> final, initial / re-tightening torque about 50% of final, final torque computation): see JGJ 82-2011 and GB 50755-2012; friction-surface treatment and the 2-3 exposed-thread rule: GB 50205-2020, GB 55006-2021.