Torque-method tightening of large-hex-head high-strength bolts: stages (initial/re-second/final), initial torque at 50% of final, final torque Tc = k x Pc x d
Torque-method tightening of large-hex high-strength bolts: ordinary joints in two stages (initial -> final), large joints in three (initial -> re-second -> final); JGJ 82-2011 Clause 6.4.14 - "joints with more than 15 bolts in a single row may be considered large and require re-second tightening". Initial and re-second torque are about 50% of final torque (GB 50755-2012: re-second torque equals initial torque); final torque Tc = k x Pc x d, where k is the mean torque coefficient of the assembly (0.110-0.150, from lot re-testing), Pc the construction preload (= design preload x 1.1). Wrenches: working wrench relative error <= +/-5%, calibration wrench <= +/-3%; initial/re-second/final tightening preferably completed within one day.
Applicable Codes
- GB 50755-2012 钢结构工程施工规范 第7.4.6条
- JGJ 82-2011 钢结构高强度螺栓连接技术规程 第6.4.13条、第6.4.14条
- DB11/T 1832.5-2023 建筑工程施工工艺规程 第5部分:钢结构工程 第11.4.6条
Topic Positioning
Staging, initial/re-second/final torque values, final-torque formula, and supporting requirements for torque-method tightening of large-hex-head high-strength bolt assemblies (grades 8.8S/10.9S), per GB 50755-2012 Clause 7.4.6, JGJ 82-2011 Clauses 6.4.13/6.4.14, and Beijing DB11/T 1832.5-2023 Clause 11.4.6 - the three standards agree.
Core Conclusions
- Staging: ordinary joints in two stages - initial -> final; large joints in three - initial -> re-second -> final. JGJ 82-2011 Clause 6.4.14: "when a single row has more than 15 bolts, the joint may be considered large and requires re-second tightening"; GB 50755-2012 Clause 7.4.6: "tightening shall be divided into initial and final; large joints shall add re-second tightening between them".
- Initial torque: initial and re-second torque are about 50% of final (JGJ 82-2011 and DB11/T 1832.5-2023 agree); GB 50755-2012 words it as "initial torque may be 50% of the construction final torque" and "re-second torque shall equal initial torque".
- Final torque calculation (prerequisite for the initial value): Tc = k x Pc x d, where Tc = final construction torque (N.m); k = mean torque coefficient of the assembly - GB 50755-2012 sets 0.110-0.150, JGJ 82-2011 requires it from the Clause 6.3.1 lot re-test; Pc = construction preload (kN) of large-hex bolts per JGJ 82-2011 Table 6.4.13 (same as GB 50755-2012 Table 7.4.6-1, DB11/T 1832.5-2023 Table 11.4.6-1) by grade 8.8S/10.9S and nominal diameter; d = nominal bolt diameter (mm). Construction preload is 10% above design preload to compensate post-tightening losses (JGJ 82-2011 Clause 6.4.13).
- Supporting points: (1) working torque wrenches shall be calibrated before use, relative error not greater than +/-5%; calibration wrenches not greater than +/-3%; (2) apply torque on the nut; (3) after initial/re-second tightening, mark nuts with one color; after final, another color; (4) initial, re-second, and final tightening preferably completed within one day (JGJ 82-2011 Clause 6.4.14); (5) the standard wrench used for final-torque checks and wrench calibration shall be calibrated by a metrology body, within validity, and be the same wrench for both checking and calibrating.
- Turn-of-nut alternative: with the turn method, the final rotation after initial (re-second) tightening is per code tables (GB 50755-2012 Table 7.4.6-2; DB11/T 1832.5-2023 Table 11.4.6-2); the rotation is relative between nut and bolt shank; when bolt length l exceeds 12d, the final rotation shall be set by test.
Applicable Boundaries
- Applies only to torque/turn-method tightening of large-hex-head assemblies; torshear bolts are final-tightened by shearing the spline with a专用 wrench - different control, outside this card.
- k must be taken from the lot's torque-coefficient re-test report - it differs per lot; never reuse fixed example values; final and initial torques follow accordingly.
- Construction preload values are per the original code tables (e.g., JGJ 82-2011 Table 6.4.13); this card does not replace them.
Further Reading
- GB 50755-2012 Clause 7.4.6, Tables 7.4.6-1 (construction preload) and 7.4.6-2 (final rotation after initial/re-second);
- JGJ 82-2011 Clause 6.3.1 (torque-coefficient test), 6.4.11 (wrench calibration), 6.4.13 (formula and Table 6.4.13), 6.4.14 (staging and large-joint criterion);
- DB11/T 1832.5-2023 Clause 11.4.6, Tables 11.4.6-1/2 (Beijing, consistent with national/industry).
Keywords
- high-strength friction-grip (HSFG) bolts
- 大六角头螺栓
- 扭矩法
- 初拧
- 复拧
- 终拧
- torque coefficient
- 施工预拉力
- 转角法