Engineering Knowledge Cards.
Confidence HighUpdated 2026-08-11

Curved steel truss girder assembly and erection points (assembly sequence, drift-pin and bolt counts, alignment survey and monitoring, allowable deviations)

Steel truss girder (incl. curved bridges) assembly and erection: main truss members assembled symmetrically left-right into closed triangles, each panel immediately checked and adjusted for position and camber; on supports, drift pins + high-strength bolts >= 1/3 of total holes (pins 2/3); cantilever/semi-cantilever >= 1/2 evenly distributed; final-torque under/over-tightening <= 10% of the specified value, bolt-group pass rate >= 80%; centerline and node deflection measured per panel, cantilever monitoring preferably 1-3 a.m.

Applicable Codes

  • TB 10415-2018 铁路桥涵工程施工质量验收标准 第12.3节
  • TB 10752-2018 高速铁路桥涵工程施工质量验收标准 Table 11.2.8
  • TB 10303-2020 铁路桥涵工程施工安全技术规程 第11.2、11.5节
  • TB 10601-2009 高速铁路工程测量规范 第7.6节
  • GB/T 51234-2017 城市轨道交通桥梁设计规范 第3.4.2条
  • ZJQ08-SGJB 018-2018 桥梁工程施工技术标准 第11.3.3、13.7.3条

Topic Positioning

This card summarizes construction and quality-acceptance points for curved steel truss girder (steel girder) assembly and erection: assembly sequence, drift-pin/high-strength bolt count rules, timing of alignment survey monitoring, erection allowable deviations, and final-torque control.

Core Conclusions

  1. Assembly sequence: per design requirements; absent design, panel by panel in order; main truss members assembled symmetrically on both sides into closed triangles, and after each panel or span, immediately check and adjust position and camber (TB 10415-2018, Clause 12.3.1). On curved bridges member dimensions differ, so members must be assembled per the manufacturer's numbering — swapping, swapping sides, or flipping is forbidden.
  2. Drift pins and bolts: on supports, pins + bolts total >= 1/3 of holes with pins 2/3, and >= 6 at sparse-hole locations; in cantilever/semi-cantilever assembly >= 1/2, pins determined by the load carried and installed evenly with bolts (Clauses 12.3.2, 12.3.3).
  3. Final-torque control: by the torque method, under- and over-tightening each no more than 10% of the specified value; pass rate >= 80% per bolt group or node; under-tightened bolts retightened, over-tightened pairs replaced and re-tightened (Clause 12.3.7); in cantilever erection, final tightening of main-truss bolts must not lag two panels, and bottom/top lateral bracing and cross frames must not lag 3 panels (TB 10303-2020, Clause 11.5.2).
  4. Survey monitoring: after each panel is installed, measure the girder centerline and node deflections, compared with alignment and stress monitoring; during cantilever erection, the camber curve and centerline maps are best drawn between 1 and 3 a.m. to eliminate solar temperature effects (TB 10601-2009, Section 7.6).
  5. Allowable deviations (TB 10752-2018, Table 11.2.8): cross-beam centerline at piers offset from the design line <= 10 mm, adjacent cross-beams relative deviation <= 5 mm; chord node offset from the line joining span-end node centers <= 1/5000 of span; vertical member offset <= 1/700 of theoretical length; with design camber <= 60 mm, camber deviation +/-4 mm.

Applicable Boundaries

Applies to on-support and cantilever/semi-cantilever assembly and erection of steel truss girders for railway, high-speed rail, and urban bridges. The pin-ratio rules follow the railway standard (TB 10415-2018); the highway system (ZJQ08-SGJB 018-2018) has the same values with slightly different wording. Steel truss bridges should not be placed on vertical curves or transition curves (GB/T 51234-2017, Clause 3.4.2, urban rail transit); where unavoidable, all member dimensions differ and construction difficulty rises sharply — a special scheme is required. The deviation table applies to high-speed rail acceptance; highway bridge deviations are in their respective acceptance standards.

Further Reading

TB 10415-2018 Section 12.3 (assembly dominant items, pin/bolt counts, final-torque checks, weld testing); TB 10752-2018 Table 11.2.8 (erection allowable deviations); TB 10303-2020 Sections 11.2, 11.5 (support/cantilever safety, final-torque pacing, counterweight-beam overturning stability factor > 1.3, safety nets and life-saving facilities); TB 10601-2009 Section 7.6 (cantilever survey timing); GB/T 51234-2017 Clause 3.4.2 (curved alignment restrictions); ZJQ08-SGJB 018-2018 Clauses 11.3.3, 13.7.3 (steel bridge assembly process, effect of full-framing foundation settlement on camber adjustment).

Keywords

Cited By