Compilation, review, and approval responsibility chain for dedicated method statements for high-risk works concerning sub-divisional works involving significant hazards (MOHURD Order No. 37)
The dedicated method statement for high-risk works concerning sub-divisional works involving significant hazards is compiled by the contractor, which organizes engineering technical personnel (under main (general) contracting, by the main (general) contractor; where subcontracted, by the specialist subcontractor). It may be implemented only after the technical responsible person of the contractor has checked and signed it and the contractor's official seal has been affixed, and the Engineer (chief supervising engineer under China's supervision regime) has reviewed and signed it with the practice seal affixed. A subcontracted method statement must be jointly checked, signed, and sealed by the technical responsible persons of both the main (general) contractor and the subcontractor. Works exceeding a certain scale must first pass the check and review; the main (general) contractor then organizes expert panel review (no fewer than 5 experts selected from the expert database, interested parties recused). After modification, the sign-off procedure is performed again.
Applicable Codes
- 住房和城乡建设部令第37号(2019年47号令修正)第十、十一、十二条
- 建办质〔2018〕31号 附件1/2
- 建办质〔2021〕48号 专项施工方案编制指南
Topic Positioning
This card sets out the statutory "compilation—review—approval" responsibility chain for dedicated method statements for high-risk works concerning sub-divisional works involving significant hazards and the expert panel review procedure for works exceeding a certain scale, per MOHURD Order No. 37 (amended by Order No. 47 in 2019), Articles 10-12.
Core Conclusions
Compilation: before construction of sub-divisional works involving significant hazards, the contractor organizes engineering technical personnel to compile the method statement; under main (general) contracting, the main (general) contractor compiles it; where subcontracted, the specialist subcontractor may compile it. Dual sign-off: (1) the technical responsible person of the contractor checks and signs it with the contractor's official seal affixed; (2) the Engineer (chief supervising engineer under China's supervision regime) reviews and signs it with the practice seal affixed — both steps complete before implementation. A subcontracted method statement must be jointly checked, signed, and sealed by the technical responsible persons of both the main (general) contractor and the subcontractor, then submitted to the Engineer for review. Additional for exceeding-scale works: the method statement must first pass the contractor's check and the Engineer's review, then the construction main (general) contractor organizes expert panel review (experts selected from the expert database of the housing and construction department, no fewer than 5, interested parties recused); if the conclusion is "pass after modification", the sign-off procedure is performed again after modification; if "fail", re-verification by the expert panel is organized. Adjustments during implementation must be re-submitted under the original procedure; implementing without sign-off is illegal.
Applicable Boundaries
Applies to building and municipal works. Determination of sub-divisional works involving significant hazards / works exceeding a certain scale follows Annexes 1/2 of Jianban Zhi [2018] No. 31, and is supplemented by provincial supplementary rules (Article 3 of Order No. 37 authorizes provincial supplementation — only tightening, never loosening, e.g., T/XCIA 3-2023 Clause 3.3.3). Expert panel review is mandatory only for sub-divisional works involving significant hazards exceeding a certain scale; ordinary sub-divisional works involving significant hazards need only the dual sign-off.
Further Reading
MOHURD Order No. 37 Article 10 (compilation), Article 11 (check, signature, and seal), Article 12 (expert panel review); Jianban Zhi [2018] No. 31 Annexes 1/2; Jianban Zhi [2021] No. 48 compilation guide; T/XCIA 3-2023 Clause 3.3.3.