Scope determination of higher-risk works and higher-risk works exceeding a certain scale, and the expert-review requirement
Per Annexes 1/2 of Jian Ban Zhi [2018] No. 31: higher-risk works require a dedicated safety construction scheme with review and approval; works exceeding a certain scale (e.g., excavation depth of 5 m or more, formwork support height of 8 m or more or span of 18 m or more, segmented cantilevered scaffolding height of 20 m or more, etc.) additionally require an expert review of the scheme organized by the general contractor, with no fewer than 5 experts selected from the housing-construction authority's expert pool.
Applicable Codes
- 危险性较大的分部分项工程安全管理规定(住建部令第37号,47号令修正)
- 建办质〔2018〕31号附件1、附件2
- DBJ04/T 253-2021 附录B
Topic Positioning
This card summarizes the two-tier scope criteria for 'higher-risk works' (sub-divisional works with relatively high risk) and 'higher-risk works exceeding a certain scale', and the expert-review procedure, for use in compiling, approving and compliance-checking dedicated safety construction schemes.
Core Conclusions
Per the Measures for the Safety Management of Sub-divisional Works with Relatively High Risk (MOHURD Decree No. 37) and Annexes 1 and 2 of Jian Ban Zhi [2018] No. 31:
- Higher-risk works (Annex 1) require a dedicated safety construction scheme with review and approval: excavation depth of 3 m or more (or less than 3 m but with complex ground and environmental conditions); formwork support height of 5 m or more, or span of 10 m or more, or total construction load of 10 kN/sq m or more, or concentrated line load of 15 kN/m or more; floor-standing scaffolding height of 24 m or more; non-routine lifting of single pieces of 10 kN or more; underground excavation (mining method, shield method, pipe-jacking method), etc. - seven major categories.
- Works exceeding a certain scale (Annex 2) additionally require an expert review of the scheme: excavation depth of 5 m or more; formwork support height of 8 m or more, span of 18 m or more, total load of 15 kN/sq m or more, or line load of 20 kN/m or more; segmented cantilevered scaffolding body height of 20 m or more; floor-standing scaffolding of 50 m or more; attached lifting scaffolding raising height of 150 m or more; non-routine lifting of single pieces of 100 kN or more; steel-structure span of 36 m or more, space frames and cable-membrane structures of 60 m or more; curtain-wall work height of 50 m or more; hand-dug pile depth of 16 m or more; integral jacking, translating or rotating of large structures of 1000 kN or more; etc.
- Review procedure (Decree No. 37, Article 12): under general contracting, the general contractor organizes the review meeting; before the review, the scheme must pass the contractor's internal review and the chief supervising engineer's examination; experts are selected from the housing-construction authority's expert pool, no fewer than 5, with interested parties recused; the scheme is revised per the review report and implemented only after signature by the contractor's technical director, the chief supervising engineer and the employer's project manager; major revisions require a new review.
Applicable Boundaries
Applies to building and municipal-infrastructure works; provincial housing-construction authorities may supplement the scope of higher-risk works in light of local conditions - where local standards provide more detail, the local provisions prevail (e.g., the higher-risk works summary table in local appraisal-standard annexes). Note that all loads refer to design values (fundamental combinations of load effects). Erection of prefabricated components is a higher-risk work but is not on the exceeding-scale list; if the scope documents are subsequently revised, the latest version governs.
Further Reading
See the Measures for the Safety Management of Sub-divisional Works with Relatively High Risk (MOHURD Decree No. 37, as amended by MOHURD Decree No. 47), Article 3 (definitions and scope-setting authority) and Article 12 (expert-review procedure); Jian Ban Zhi [2018] No. 31, Annex 1 (scope of higher-risk works) and Annex 2 (scope of works exceeding a certain scale); for local details see Table 6.1.12 of the Hunan green-construction appraisal standard technical details and DBJ04/T 253-2021, Annex B.