Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Pre-meeting material preparation and organization requirements for expert panel review of sub-divisional works involving significant hazards that exceed a certain scale

Before the expert panel review meeting, the special scheme must already have passed the construction unit's technical responsible person's review-signature + company seal and the Engineer's (chief supervising engineer under China's supervision regime) review-signature + practice seal (prerequisite of Article 12 of Order No. 37); then assemble the special scheme (9 content items), the submission-for-review form, and basic materials such as the survey report/construction drawings/special design scheme; experts are selected from the housing and construction authority's expert database, no fewer than 5, with interested parties recused, and participants are constituted per Article 3 of Jianban Zhi [2018] No. 31; after the review, the revised scheme is implemented only after signature by the construction unit's technical responsible person, the Engineer, and the construction employer's project manager, and major modifications require re-verification by the expert panel.

Applicable Codes

  • 住房和城乡建设部令第37号 危险性较大的分部分项工程安全管理规定
  • 住房和城乡建设部令第47号(2019修正)
  • 建办质〔2018〕31号
  • 建办质〔2021〕48号 危大工程专项施工方案编制指南

Topic Positioning

Material and organization preparation before the expert panel review meeting for sub-divisional works involving significant hazards that exceed a certain scale: statutory prerequisites, material checklist, participants, and post-review procedure.

Core Conclusions

  1. Prerequisites: before the meeting the special scheme must have passed the construction unit's technical responsible person's review-signature + company seal and the Engineer's (chief supervising engineer under China's supervision regime) review-signature + practice seal (MOHURD Order No. 37 Article 12; Order No. 47 amendment Article 11).
  2. Core materials: (1) the nine content items of the special scheme (overview, basis of preparation, construction programme, process technology, safety assurance measures, personnel division, acceptance requirements, emergency response, calculation books and drawings); (2) submission-for-review form and expert panel review form; (3) construction drawings, survey report (essential for geology-involved works such as deep excavation and mined tunnelling), project execution plan (construction methodology and site organization), special design scheme and its review documents, and surrounding environment and utility information.
  3. Organization: experts are selected from the local housing and construction authority's expert database, no fewer than 5, with interested parties recused; participants include the experts, the construction employer's project manager, the survey and design units' project technical responsible persons, the main (general) contractor's and subcontractors' technical responsible persons (or authorized delegates), the project manager/technical responsible person/scheme compiler/full-time safety officer, and the Engineer and discipline supervision engineers; the scheme is delivered to participants in advance for review.

Applicable Boundaries

Applies only to "exceeding a certain scale" sub-divisional works involving significant hazards in building and municipal engineering, with scope per Annex 2 of Jianban Zhi [2018] No. 31 (deep excavation >= 5 m, formwork supports >= 8 m in height or >= 18 m in span, etc.); provincial rules may tighten and expand — check the national list plus local rules together; review records, reports, and signed documents should be archived in the sub-divisional works involving significant hazards file.

Further Reading

MOHURD Order No. 37 Article 12 and Order No. 47 amendment Article 11; Jianban Zhi [2018] No. 31 Article 3 and Annexes 1/2; Jianban Zhi [2021] No. 48 compilation guide; DB37/T 5160-2020 Appendix E Form SG-T-4 (expert panel review opinion form).