Project execution plan and construction method statements - life-cycle overview: classification, preparation, approval, implementation, dynamic management and changes
Execution plans divide into three tiers by object (overall project execution plan / unit-works execution plan / method statement), each compiled under the project manager's leadership, framed on the eight basic contents and approved by tier (the contracting enterprise's technical director / the contractor's technical director / the project technical director). High-risk dedicated schemes need the dual sign-off of the contractor's technical director plus the chief supervising engineer, and beyond a stated scale an expert panel of at least five, with the tri-state conclusion pass / pass after revision / fail. Before implementation: tiered briefing, supervisory review and signature, dedicated patrol inspection; five statutory triggers (major design modification, legal and standards change, major changes of method or resources, major change of environment) require revision and re-approval in principle at the original level (GB 55032-2022 cl. 3.1.4, mandatory: changes follow the original approval procedure); a materially changed high-risk scheme must be recompiled and re-reviewed by the panel, and after an adjusted scheme passes approval it is briefed again.
Applicable Codes
- GB/T 50502-2009 建筑施工组织设计规范(第3.0.1、3.0.5、3.0.6条)
- GB 55032-2022 建筑与市政工程施工质量控制通用规范(第3.1.4条,全文强制)
- 住建部令第37号(第47号令修正)危险性较大的分部分项工程安全管理规定(第十至十三条)
- 建办质〔2018〕31号 关于实施危大工程安全管理规定有关问题的通知
- GB/T 50319-2013 建设工程监理规范(第5.1.6、5.5.3、5.5.5条)
- JGJ 147-2016 建筑拆除工程安全技术规范(第6.0.1条)
- DB37/T 5164-2020、DB11/T 1745-2020、T/XCIA 3-2023、T/ZSQX 018-2022(地方/团体动态管理与变更细则)
An entry card for the domain of the project execution plan (shigong zuzhi sheji) and construction method statements, running the whole life cycle — classification, compilation, approval, implementation and change — across three parallel procedures: ordinary execution plans, method statements, and dedicated method statements for high-risk works. What readers look up most: how the three tiers divide and who compiles and approves each; what the eight basic contents are; how dual sign-off and expert panel review run for high-risk schemes; what briefing and supervisory review do during implementation; and when a plan must be revised and re-approved, and when a high-risk scheme must go back to the panel. The card gives the full-cycle framework and navigates this domain's cards.
Concept and mechanism
Classification. Three tiers by object of compilation (GB/T 50502-2009 cl. 3.0.1): the overall project execution plan — for group projects of several unit works or extra-large projects, master-planning and exercising key control over the whole project; the execution plan for individual structures (unit works) — guiding and constraining the construction of that unit; and the construction method statement — for sub-divisional or dedicated works, directly guiding their execution. By stage they divide into tender-stage plans (complying with the tender documents, aiming at the award) and execution-stage plans (emphasising constructability and encouraging technical innovation); dynamic management constrains the execution-stage documents.
Compilation. Each tier is compiled under the leadership of the project manager and may be compiled and approved in stages as needed (cl. 3.0.5). The eight basic contents: basis of compilation; project overview; site deployment strategy; construction programme; preparation and resource plans; principal construction methods; site layout; and principal construction management plans. Method statements for critical, difficult or dedicated sub-divisional works are reviewed by relevant experts organised by the contractor's technical department and approved by the contractor's technical director; schemes executed by specialist subcontractors are approved by the specialist subcontractor's technical director (or an authorised person) and filed for record with the main contractor's project technical director; larger sub-divisional schemes are compiled and approved as unit-works execution plans.
The special procedure for high-risk works. Before construction, engineering and technical personnel compile a dedicated method statement for high-risk works (MOHURD Order No. 37, art. 10); under main contracting the main contractor organises compilation, and where the high-risk works are subcontracted the specialist subcontractor may compile. The scheme takes effect by dual sign-off (art. 11): the contractor's technical director checks and signs with the company seal, and the chief supervising engineer reviews and signs with the practitioner's seal; where a subcontractor compiled it, the main and specialist contractors' technical directors jointly check and sign. Works beyond a certain scale additionally require expert panel review (art. 12): experts are drawn from the local housing and urban-rural development authority's panel, number not fewer than five, and persons with an interest in the project may not take part; before the panel sits, the scheme must have passed the contractor's own check and the chief supervising engineer's review. The panel's conclusion is tri-state (art. 13): pass; pass after revision — revise per the panel report and re-run the art. 11 procedure; or fail — revise and reconvene the panel.
Implementation and supervisory review. Before construction the plan is briefed tier by tier, and during execution compliance is checked, analysed and adjusted in good time (cl. 3.0.6(3)). The supervision organisation reviews the compilation-and-approval procedure, the programme, quality measures, resource plans, safety-technical measures and site layout; when satisfactory, the chief supervising engineer signs it and forwards it to the employer, and construction proceeds per the approved documents (GB/T 50319-2013 cl. 5.1.6); review of dedicated schemes covers the approval procedure and the safety-calculation results, and beyond-scale schemes are checked for the expert panel review (cl. 5.5.3); the supervisor makes dedicated patrol inspections of the implementation of high-risk schemes and, on finding work off-scheme, issues a supervising engineer's notice requiring rectification (cl. 5.5.5).
Dynamic management and change. Five statutory triggers require timely revision or supplement of the plan (cl. 3.0.6(1)): major design modification (change of foundation or principal structural form, major change of fit-out, major MEP reconfiguration — ordinary changes are supplemented as needed, minor ones need no revision); implementation, revision or repeal of relevant laws, regulations and standards; major adjustment of the principal construction method; major adjustment of the principal resource allocation; and major change of the construction environment. A revised or supplemented plan must be re-approved before implementation, in principle at the original approval level (cl. 3.0.6(2)); GB 55032-2022 (full-text mandatory) cl. 3.1.4: plans and schemes, once approved per the prescribed procedure, are executed accordingly, and any change follows the original approval procedure. Graded handling: where a local design change or a construction-condition or weather effect does not touch the scheme itself, only the original briefer amends and supplements the technical briefing and re-briefs; where the method, process parameters or safety are affected, the scheme is revised, re-approved at the original authority and re-reviewed by the supervisor; a major adjustment of a high-risk scheme is re-checked and re-reviewed and re-verified by the expert panel as required, and where timing, design, the construction environment or the process change materially the scheme is recompiled and the panel reconvened — a demolition-type scheme reviewed by a panel may change only with the original panel experts' consent. After an adjusted scheme passes approval it is briefed again; before approval is obtained, work may not proceed by the new method.
Card-group navigation
Classification and content
- Compiling and approving the execution plan: the three tiers, who leads, and tiered approval authority (card_c5d69f01)
- The basic contents of an execution plan: the eight components (two code references) (card_2149eb44)
- The unit-works execution plan: the seven parts of chapter 5 (card_74df2773)
- The three tiers of plan documents: the full content checklist and the project technical director's duties (card_396e4d0f)
Compilation methods and elements
- The method-statement programme: procedure, duration calculation, bar chart / network diagram (card_2969f955)
- Fixing the construction sequence: position, basis, principles and steps (card_e8b1dc6f)
- Plant selection: model — number of units — machine-shifts (card_5753f2ea)
- Plant allocation: choose the type → back-calculate the count → mobilisation sequence (card_8bff36b4)
- Crew sizing: quantities × quota norms for labour demand, duration back-calculated to headcount (card_d8c67a12)
- Dividing the works into flow sections: less idle time, fewer cross-trade clashes (card_05ea6eaa)
- Emergency measures: three blocks for ordinary schemes, eleven items for high-risk schemes (card_f2e2910e)
- How deep the work-method write-up should go (card_8f20961b)
- Quality assurance measures: management + technical measures + inspection interfaces (card_236aebd4)
- Safety assurance measures: the seven-item framework and the high-risk trio (card_ed0317ab)
- Spotting obvious gaps in a statement: lock the type → compare frameworks → four-property check (card_60363ca0)
- AI-assisted scheme drafting: the statutory sign-off chain and the human review points (card_981d683e)
- Wet-season inputs: the percentage-rate method and the quantities method (card_d39550bf)
- Temporary works: scale and cost under three bases and three methods (card_8faa0938)
Review and consistency
- The supervisor's review of execution plans and (dedicated) method statements: basis, contents and procedure (card_e1220a72)
- Technical briefing vs method statement vs actual practice: the hierarchy of force (card_34736416)
- Statement off-step with the work on site: the handling procedure (card_74b1bf52)
Links to high-risk works
- Hazardous-works and beyond-scale scopes: identification and the panel-review requirements (card_b5c12d8f)
- Which works need a dedicated method statement: a layered test (card_4017bb4a)
- The high-risk scheme chain: compile, check, approve — who does what (card_fa62024d)
- Required contents of high-risk schemes: nine general items plus the specials for deep excavations / high formwork / lifting (card_1728c4ab)
- Pre-construction technical and safety procedures for hazardous works: the full chain (card_ae289ff9)
- Before the expert panel sits: document preparation and organisational requirements (card_4b202163)
- When the panel says no: the handling procedure and the penalties for procedural breaches (card_497b9f63)
- High-risk schemes after design or construction-condition changes: re-check and re-review by the panel (card_a9d9d453)
- Re-approval after construction-condition changes: ordinary vs high-risk, graded handling (card_35830741)
- No high-risk scheme compiled: legal liability and penalties (card_5049b47c)
- May the method statement survive a design change? Graded answers (card_efb9f06a)
Change and cost linkage
- Adjusting responsibility-centre cost after a major execution-plan change: the procedure (card_df70f057)
- Girder-erection safety risk control: hazard identification and five layers of control (card_db1362f2)
Keywords
- project execution plan (construction methodology and site organization)
- construction method statement
- dedicated method statement for high-risk works
- overall project execution plan
- 分级审批
- sub-divisional works involving significant hazards
- expert panel review
- 逐级交底
- ongoing (dynamic) cost management
- 重新审批
- re-verification by the expert panel
- GB/T 50502-2009