Complete content checklists of the three-tier project execution plan documents and the project technical director's duties (RISN-TG017-2014 Clause 4.5.2)
RISN-TG017-2014 "Guidelines for practice of construction project technical directors", Clause 4.5.2, lists the contents tier by tier: overall project execution plan 12 items (basis, overview, deployment, master schedule, preparation and resource plans, main methods, site layout, schedule/quality/safety/environment/cost management plans); execution plan for individual structures 13 items (adds the finished-products protection plan); construction method statements 10 items incl. arrangement, methods and process requirements, with calculation books and drawings appended for dedicated method statements for high-risk works. The technical director manages submission/approval of the project execution plan, preparation and expert panel review management of dedicated method statements for high-risk works, and approves ordinary method statements.
Applicable Codes
- RISN-TG017-2014《建设工程项目技术负责人执业导则》第4.5.2条
- GB/T 50502-2009 · Code for Construction Organization Planning of Building Works 第2.0.6、3.0.1、3.0.4、3.0.5条
- GB/T 50903-2013 · Code for Construction Organization Planning of Municipal Works 第3.0.4条
- 《建设工程安全生产管理条例》(国务院令第393号)
- 住建部令第37号《危险性较大的分部分项工程安全管理规定》(第47号令修正)
- 建办质〔2018〕31号
- 建办质〔2021〕48号
Topic Positioning
A directly checkable "completeness checklist" for the three-tier documents - overall project execution plan, execution plan for individual structures, and construction method statements (incl. dedicated method statements for high-risk works): what each must cover, plus the technical director's duties in the submission-approval chain, per RISN-TG017-2014 Clause 4.5.2 used with GB/T 50502-2009 - for self-check and review.
Core Conclusions
I. Duties (Clause 4.5.2): the project technical director is responsible for the project execution plan's submission and approval; for preparing dedicated method statements for high-risk works and managing their review and expert panel review; and approves ordinary method statements. When submitting, assist the project manager in reviewing content; content and format per GB/T 50502-2009. II. Overall project execution plan (12 items): 1 basis; 2 project overview; 3 overall deployment; 4 master schedule; 5 overall preparation and main resource plans; 6 main construction methods; 7 general site layout; 8 master schedule management plan; 9 quality plan; 10 safety plan; 11 environment plan; 12 cost plan. III. Execution plan for individual structures (13 items): 1 basis; 2 overview; 3 deployment; 4 schedule; 5 preparation and resource plans; 6 main construction method statements; 7 site layout; 8 schedule plan; 9 quality plan; 10 safety plan; 11 environment plan; 12 cost plan; 13 finished-products protection plan - one more than the overall plan (protection), and "main methods" refined into "main construction method statements". IV. Construction method statements: 1 basis; 2 overview; 3 arrangement; 4 schedule; 5 preparation and resources; 6 methods and process requirements; 7 schedule plan; 8 quality plan; 9 safety plan; 10 environment plan; 11 calculation book and drawings - the last item applying to dedicated method statements for high-risk works. V. Underlying basis: the lists expand the eight basic contents of GB/T 50502-2009 Clause 3.0.4 (basis, overview, deployment, schedule, preparation and resources, main methods, site layout, and main management plans); contents may be added or removed per the project, order not mandated; "deployment" is programmatic and the rest is built around it (Clause 2.0.6). The technical director should promote the "four news" (new technologies) and cite current standards, with compliant figures, tables, and symbols. Approval flows per Guide Figures 4.5.2-1 (overall and individual-structure plans), -2 (dedicated method statements for high-risk works), -3 (ordinary method statements).
Applicable Boundaries
- RISN-TG017-2014 is a practice-guide document; its duty split matches GB/T 50502-2009 Clause 3.0.5 (project-head-chaired preparation, staged preparation and approval, tiered approval) - approval subjects follow the GB clause and the contract; local or employer requirements prevail.
- Suits the building-works system; municipal works follow GB/T 50903-2013 Clause 3.0.4 (overview, deployment, layout, preparation, technical schemes, main safeguards - six parts with a six-chapter reference list), prepared under the project head and possibly staged.
- Only a content checklist - the scope of sub-divisional works involving significant hazards (Jianbanzhi [2018] No. 31 Annexes 1/2) and the content of high-risk-works method statements (Jianbanzhi [2021] No. 48's 9-item frame) are separate; sign-off and expert panel review procedures have their own cards.
Further Reading
- RISN-TG017-2014 Clause 4.5.2 and Figures 4.5.2-1/2/3.
- GB/T 50502-2009 Clauses 2.0.6 (deployment term), 3.0.1 (three tiers), 3.0.4 (eight contents), 3.0.5 (preparation/approval); 3.0.5 commentary citing the Safety Regulations (Decree No. 393): sub-divisional works involving significant hazards above a certain scale (excavation support and dewatering, earthworks, formwork, lifting, scaffolds, demolition/blasting) need dedicated method statements with safety verification results, signed by the contractor's technical head and the chief supervision engineer; deep excavations, underground mining, and high formwork need expert panel review.
- GB/T 50903-2013 Clause 3.0.4.
- Current rules on sub-divisional works involving significant hazards: MOHURD Order No. 37 (as amended by No. 47), Jianbanzhi [2018] No. 31 (scope), Jianbanzhi [2021] No. 48 (method statement guide).