Basic content composition of a project execution plan (construction methodology and site organization): eight components and two-level standard references (GB/T 50502-2009, GB/T 50903-2013)
GB/T 50502-2009 Clause 3.0.4 requires a project execution plan (construction methodology and site organization) to contain eight parts: basis of preparation, project overview, site deployment strategy, programme (of works), construction preparation and resource allocation plans, main construction methods, construction site layout, and main construction management plans; content may be added or reduced per the project's actual conditions, chapter order is not mandatory, and the site deployment strategy is the programmatic part around which all other parts are prepared.
Applicable Codes
- GB/T 50502-2009 · Code for Construction Organization Planning of Building Works 第 2.0.6、3.0.1、3.0.4、4.3.1、4.4.1、4.6.2、5.4.1 条
- GB/T 50903-2013 · Code for Construction Organization Planning of Municipal Works 第 3.0.4 条
- DB22/JT 127-2017《建筑工程资料管理标准》第 6.2.2 条
Topic Positioning
Basic content composition of a project execution plan (construction methodology and site organization) and the two-level standard requirements (GB/T 50502-2009, GB/T 50903-2013).
Core Conclusions
Eight basic parts: basis of preparation, project overview, site deployment strategy, programme (of works), construction preparation and resource allocation plans, main construction methods, construction site layout, and main construction management plans (GB/T 50502-2009 Clause 3.0.4); content may be added or reduced per the project's actual conditions, and chapter order is not mandatory. The site deployment strategy (objectives, sequence and spatial organization, organizational arrangements) is the programmatic core around which all other parts are prepared (Clause 2.0.6). By object of preparation there are three levels: overall project execution plan, execution plan for individual structures, and construction method statement (Clause 3.0.1): the overall project execution plan emphasizes overall deployment, the general programme of works, general construction preparation, and phased general site layout drawings (Clauses 4.3.1, 4.4.1, 4.6.2); the execution plan for individual structures emphasizes technical preparation (method statement preparation, testing and equipment commissioning, mock-up plans), on-site temporary works and site establishment, and funding plans (Clause 5.4.1). Approval: the overall project execution plan by the technical responsible person of the main (general) contracting organization, the execution plan for individual structures by the technical responsible person of the construction contractor or an authorized person (DB22/JT 127-2017 Clause 6.2.2).
Applicable Boundaries
Based on GB/T 50502-2009 (building construction). Municipal works follow GB/T 50903-2013 Clause 3.0.4: prepared under the leadership of the project manager, may be prepared in sections, with a six-chapter reference table of contents (project overview, overall deployment, site layout, construction preparation, technical schemes, assurance measures). The eight items are a basic checklist, not mandatory; the bidding stage emphasizes responsiveness to tender documents, and the implementation stage emphasizes operability.
Further Reading
GB/T 50502-2009 Clauses 2.0.6, 3.0.1, 3.0.4, 4.3.1, 4.4.1, 4.6.2, 5.4.1; GB/T 50903-2013 Clause 3.0.4; DB22/JT 127-2017 Clause 6.2.2.
Keywords
- project execution plan (construction methodology and site organization)
- 基本内容
- site deployment strategy
- 施工进度计划
- 施工现场平面布置
- GB/T 50502-2009
- GB/T 50903-2013
- execution plan for individual structures