Layered breakdown of the total duration into milestone, monthly and weekly plans
The total duration is decomposed in a two-level "controlling -> operational" system: first cut construction stages and fix milestone nodes (controlling plans), then break the works down by month against milestone deadlines and arrange work by week (operational plans), forming the rolling control chain "weekly secures monthly, monthly secures milestones, milestones secure the total duration"; operational plans prefer network planning to identify the critical path.
Applicable Codes
- GB/T 50326-2017 建设工程项目管理规范
- GB/T 51235-2017 建筑信息模型施工应用标准
- RISN-TG 012-2011 建设工程项目经理执业导则
- DB37/T 5164-2020 建筑施工现场管理标准
Topic Positioning
This card explains the layered preparation of construction schedules: how the total duration is decomposed top-down into the milestone plan (controlling), the monthly progress plan and the weekly work plan (operational), and how the levels connect and roll forward under control.
Core Conclusions
Schedules fall into two levels: controlling progress plans (project total, stage, sub-project/single-building, annual/quarterly plans) and operational progress plans (work-item, monthly/weekly plans). The decomposition chain: total duration -> divide construction stages -> determine milestone nodes (key control events + explicit target dates) -> prepare the monthly progress plan (monthly tasks broken down by work items with milestones as the back wall) -> prepare the weekly work plan (the month plan detailed for one week). The milestone plan is the core output of the controlling level and the rigid constraint the monthly/weekly plans must align with. Method selection: controlling plans use milestone tables and quantity tables; operational plans prefer network planning with critical-path determination, preferably prepared and tracked with project-management software. Level of detail increases downward: controlling plans record only start/finish times; operational (weekly) plans go down to work faces, labor crews and headcounts. During execution, check and correct on a rolling basis per "weekly secures monthly, monthly secures milestones, milestones secure the total duration".
Applicable Boundaries
Applies to preparing and decomposing construction schedules for building works under a contract-duration constraint, assuming project progress targets, milestone events and resource allocation are already defined. Not applicable to rough planning without duration constraints, single-point duration queries, or bar-chart-only schedules that do not identify the critical path; stage division can vary by industry, but the two-level decomposition and rolling-control logic are universal.
Further Reading
See GB/T 50326-2017, Code for Construction Project Management, Clause 9.2.2 (two-level plan types) and Clause 9.2.5 (method selection); GB/T 51235-2017, Standard for Construction Application of Building Information Modeling, Clause 8.1.2 (level-of-detail differences between controlling and implementation plans); RISN-TG 012-2011, Guideline for Practice of Construction Project Managers, Clause 6.2.1 (plan forms and the critical path); DB37/T 5164-2020, Standard for Construction Site Management of Buildings, Clause 7.2.2 (monthly/weekly plan preparation requirements).