Compressing total duration by combining the critical path method with flow-line construction: the division of labour between time skeleton and spatial rhythm, the overlapped-network form, the quantitative rules of sectioning and compressing critical activities, the linkage of resource continuity with critical-path control, and applicability

CPM and flow-line construction are not parallel plans but a coupling of 'time skeleton + spatial rhythm': take 'section x trade' as the network activity and express the flow step by the four lags FTS/STS/FTF/STF (JGJ/T 121-2015 clause 5.4.2), the rhythm t being the duration D. Two channels compress duration: 1) organisational / spatial measures - even-rhythm flow T = T0[1+(n-1)/m], the gain per added section diminishing in (n-1)/m with the floor T0, requiring m >= n for crew continuity, balanced section quantities and natural section joints, plus reducing K, adding crews n', same-section overlaps; 2) time / logic measures - the six steps of clause 6.2.2 compressing critical activities, choosing per 6.2.3 those with working space, ample resources and least added cost, a compressed activity turning non-critical being lengthened back. Linkage rules: compress critical activities only, recompute the critical path after every change, never break m >= n or the non-inversion of K; on resource peaks switch to the 6.3.3 / 6.3.4 adjustments.

Applicable Codes

  • JGJ/T 121-2015 · Specification for Engineering Network Planning Technology 第6.2.2条、第6.2.3条、第5.4.2条、第5.5.1条、第6.3.3条、第6.3.4条
  • GB/T 50502-2009 · Code for Construction Organization Planning of Building Works 第2.0.8条、第5.2.2条、第6.3.1条、第7.2.1条
  • GB/T 50326-2017 · Code for Construction Project Management 第9.2.5条
  • 《建设工程质量管理条例》第十条

Positioning

How CPM and flow-line construction combine to compress total duration: their division of labour (time skeleton vs spatial rhythm), the merged overlapped network, the quantitative rules of the two compression channels (organisational/spatial and critical-activity compression), the four linkage conditions, and applicability. Basis: JGJ/T 121-2015 and GB/T 50502-2009 (the project execution plan code).

Core conclusions

1. Complementary roles: CPM the time skeleton, flow the spatial rhythm

  • CPM yields the computed duration, floats and the critical path - "which chain controls delivery"; flow yields the rhythm t, the step K, the sections m and crew continuity - "how one work face in series becomes m faces staggered in parallel".
  • Standard anchors: GB/T 50502-2009 clause 7.2.1 - progress management "shall ensure the works connect in time and space per the technical logic and sound sequence"; clause 5.2.2 - "flow sections shall be divided in stages per the works", stating the basis and flow direction for balanced flow; clause 6.3.1 - the plan shows the overlaps, durations and start/finish of sections and trades; term 2.0.8 defines the construction schedule as "the coordinated planning of sequence, timing and interfacing of the construction processes to meet the duration target".
  • Method choice: GB/T 50326-2017 clause 9.2.5 - milestones, quantity schedules, bar charts or networks may be used, "operational schedules should prefer network methods", aided by software.

2. The merged form: "section x trade" as the activity, flow expressed by lags JGJ/T 121-2015 clause 5.4.2: "activity-on-node overlapped networks are drawn per sections 5.1 and 5.2, overlaps expressed by time lags" - four lags: FTS, STS, FTF, STF. The rhythm t is the activity's duration D, the flow step K the lag between adjacent activities (commonly FTS or STS); the two plans merge into one AON overlapped network. Criticality (clause 5.5.1): "activities with the least total float are critical"; "the critical path runs wholly of critical activities with zero lag between adjacent ones". Special note (5.4.2): "the duration of an overlapped network may depend not on the activities ending at the terminal but on intermediate activities" - after overlapping, do not read the duration off the last trade alone.

3. Channel A (spatial / organisational, no process change): quantitative rules Even-rhythm flow T = (m + n - 1)t with t = T0/m (T0 the days of the leading process at maximum continuous resourcing), i.e. T = T0 x [1 + (n-1)/m] Three rules: 1 the gain per added section scales with (n-1)/m, diminishing, with the absolute floor T0: at T0 = 12 days and n = 3, m = 3 gives 20 days, m = 6 gives 16 (-4), m = 12 gives 14 (-2 more); m tending to infinity approaches 12. 2 m >= n is the precondition of crew continuity; with m < n some crew idles and the gain is eaten by idle costs. Section quantities should be broadly balanced (spread within about 50%), joints at movement joints, post-cast strips and other natural breaks. 3 adding sections is not boundlessly effective: inter-section intervals Z and crew transfer times accumulate - past a point the duration rises again. Other channel-A means: reduce K (bounded by working faces and technical intervals); add crews n' (multiplied rhythm: K0 = gcd of rhythms, n' = sum ti/K0, T = (m + n' - 1)K0); same-section overlap (STS/FTF lags; FTS = 0 or negative). Technical intervals (curing, strength growth, watertightness and pressure tests) are hard constraints; organisational intervals can be negotiated.

4. Channel B (time / logic): the six steps of clause 6.2.2 1 compute the initial duration, critical activities and path; 2 the time to shorten against the required duration; 3 each critical activity's shortenable duration; 4 choose and compress per 6.2.3 and recompute - "when a compressed critical activity turns non-critical, lengthen it back to criticality"; 5 repeat 1-4 while the requirement is unmet; 6 when all critical activities are at their limits, adjust the technical or organisational scheme per 1.0.3 or re-examine the required duration. Compression targets per 6.2.3: "prefer activities with working space, ample standby resources and least added cost".

5. Linkage rules (four constraints keeping the two consistent) 1 compress critical activities only - non-critical ones gain float, not time. 2 recompute after every change: any organisational measure (sections, K, crews, overlaps) changes durations and lags - back to CPM; the critical path may shift wholesale. 3 lengthen back activities compressed non-critical (6.2.2 item 4) - no resources spent on paths no longer controlling. 4 compression must not break flow continuity: m >= n and non-inverted K; on resource peaks switch to 6.3.3 "limited resources, shortest duration" (parallel activities ordered by dT = EF(m) - LS(n)) or 6.3.4 "fixed duration, levelled resources" (peak shaving, dT = TF - (T(h) - ES)), then return to the duration iteration.

6. Applicability

  • Channel A leads where: the works are sectionable, quantities per section similar, trades repeat across sections (multi-storey, linear, group works), the constraint is face-rhythm mismatch, crews can run continuously.
  • Channel B leads where: monolithic works without repeated sections (long spans, special structures), the critical path concentrates in a few long activities (deep foundations, major erections, steel lifting), resources or multi-shift work can be added, and the binding constraint is the contract duration.
  • Sequence: run CPM for the path and floats - check for repeatable sectioned trades on the path - if yes, move organisational parameters first (sections / crews / K / overlaps); if no, compress critical durations - recompute and check resources and cost each round. The channels iterate, not alternate blindly.
  • The failure boundary: with every critical activity at its shortenable limit and the duration still unmet, only the technical / organisational scheme changes or a re-examined required duration remain - and compressing the required duration must respect the red line that the employer may not arbitrarily shorten a reasonable duration (Quality Management Regulation Article 10).

Applicable boundaries

  • T = T0[1+(n-1)/m] assumes even rhythm, equal section rhythms, continuous crews and no intervals or overlaps; uneven or non-rhythmic flows need the "cumulative stagger subtraction" step K and T = sum K + the last process's run + sum Z - sum C.
  • "Section x trade" as the activity unit presupposes clear section joints and transferable faces; unsectionable monoliths fall back to pure network compression.
  • Technical intervals, code-mandated standstills and acceptance nodes are incompressible; where compression cuts efficiency, added resources do not shorten durations proportionally.
  • Compressed schemes still pass legality: compare against duration norms, justify overruns, price acceleration - never arbitrarily shortening a reasonable duration.
  • Methods and rules here replace neither the resource, cost and contract inputs of a real project nor its computations.

Further reading

JGJ/T 121-2015 clauses 5.4.2, 5.5.1, 6.2.2, 6.2.3, 6.3.3-6.3.4, 1.0.3; GB/T 50502-2009 clauses 2.0.8, 5.2.2, 6.3.1, 7.2.1; GB/T 50326-2017 clause 9.2.5; Quality Management Regulation Article 10.