Identifying the critical path and the effect of critical-activity delays on total duration and duration claims

A critical activity = the activity with the least total float; the critical path = in AOA networks the path composed of critical activities or with the longest total duration (in AON networks, adjacent critical activities must also have zero time interval), and it determines the project duration. Identification methods: total-float method, longest-path method, time-scaled network wave-line method, and node-labeling method. A critical activity delayed by however long extends the total duration by that long, claimable duration = delay time; when a non-critical activity is delayed beyond its total float and turns critical, claimable duration = delay − total float; within total float, no duration claim arises (GB/T 50500-2024, Clause 8.11.8).

Applicable Codes

  • JGJ/T 121-2015 工程网络计划技术规程
  • GB/T 50500-2024 建设工程工程量清单计价标准

Topic Positioning

Methods of identifying the critical path in network plans (total-float method, longest-path method, wave-line method, node-labeling method) and the effect of critical-activity delays on the total duration and duration claims, covering AOA (double-arrow), AON (single-arrow), and time-scaled networks.

Core Conclusions

① Definitions: a critical activity is one with the least total float; the critical path is, in AOA networks, the path composed of critical activities or with the longest total duration, and in AON networks the path of critical activities whose adjacent time intervals are zero; it determines the project duration and should be marked with bold, double, or colored lines on the diagram. ② Identification methods: total-float method (TF = LS − ES; the least-float activities are critical); longest-path method (the path with the greatest sum of durations); time-scaled network wave-line method (the path from start to finish without wave lines — the most intuitive); node-labeling method (label nodes by bj = max{ETi + Di-j}; the terminal label is the calculated duration, then trace back from the terminal along source nodes to find the critical path — no need to compute all time parameters, ideal when only the duration and critical path are needed). ③ Delay effects (GB/T 50500-2024, Clause 8.11.8): a delay on the critical path → the delay time is the claimable duration and the total duration extends equally; a non-critical activity delayed beyond total float becomes critical → claimable duration = delay − total float; within total float → total duration unaffected and no duration claim arises. ④ Adjustment methods (JGJ/T 121-2015, Clauses 7.3.2–7.3.3): where the duration may not be extended, compress among unfinished critical activities those with low resource intensity or low direct-cost rate, and recalculate per duration optimization; where extension is allowed, treat the unfinished portion as a new plan and recalculate; non-critical adjustments are limited to total float, with time parameters recalculated after each adjustment.

Applicable Boundaries

Applies to schedules prepared by AOA, AON, and time-scaled network methods, assuming activity logic and durations are fixed. Not applicable to bar charts or milestone tables that do not show logic (no critical path can be judged) or rough planning without duration constraints. Duration-claim rules give priority to contract agreement; the standard is the general basis absent agreement.

Further Reading

See JGJ/T 121-2015, Specification for Engineering Network Planning Technique, Clauses 2.1.33 and 2.1.35 (terminology), Clause 4.5.1 (AOA critical activities/paths and the node-labeling method), Clause 4.5.2 (time-scaled wave-line method), Clauses 5.5.1–5.5.2 (AON), Clauses 7.3.2–7.3.3 (critical/non-critical adjustments); GB/T 50500-2024, Standard for Valuation of Construction Works with Bills of Quantities, Clause 8.11.8 (delay claim duration calculation).