critical path
- 01
The essential difference between flow-line construction (the flow method of organising work) and network planning techniques, an element-by-element comparison of the two systems (principle / presentation tool / optimisation objective / applicable scenario) and the ways the two are combined (GB/T 50502-2009 clauses 5.2.2, 6.2.2, 6.3.1; JGJ/T 121-2015 clauses 3.2.14, 3.2.17, 4.5.1, 6.2 to 6.4)
Flow-line construction is a method of organising work: it decides how sp…
GB/T 50502-2009 · Code for Construction Organization Planning of Building Works 第 5.2.2、6.2.2、6.3.1 条JGJ/T 121-2015 · Specification for Engineering Network Planning Technology 第 3.2.14、3.2.17、4.4.1、4.5.1、5.4.1、6.2.2、6.3.1、6.3.4、6.4.2、8.2.3 条2026-11-01 - 02
Distinguishing claims for extension of time from cost claims: an axis-by-axis comparison of the two independent remedies, time and money, on causation threshold (critical path), basis of calculation (delay duration / total float vs actual-cost method / total-cost method), whether profit is claimable, evidence and time limits, plus the rules of combined calculation and joint approval where both are claimed together
An EOT claim asks for time, a cost claim asks for money; both are econom…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.31条、第8.11.1~8.11.13条T ZBD 100.5-2023 建设工程结算审核作业指引 第3.1.9条T ZBD 100.4-2023 建设工程造价鉴定作业指引 第4.7.3~4.7.5条2026-11-01 - 03
Five elements of substantive review and the assessment boundaries of critical path analysis opinions in delay assessment (validity of the baseline programme, the critical path identification algorithm, placement of delay events, the dynamic network as at each event, and no overstepping into findings of liability)
A critical path analysis opinion can and must be reviewed substantively…
GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.7.5条、第5.7.6条GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11.7条、第8.11.8条JGJ/T 121-2015 · Specification for Engineering Network Planning Technology 第2.1.35条、第4.5.1条、第4.5.2条2026-10-29 - 04
Checklist of elements of proof for an employer claiming liquidated damages for delay (late completion) and the measurement of the days of delay: the liquidated damages clause; the commencement date and the contract period; determination of the actual completion date under three scenarios; deduction of approved extensions; attribution of the delay and apportionment of concurrent delay; and the rule of sharing concurrent delays in proportion to liability
Claimable, but the amount is not fixed directly by 'how many days late i…
《中华人民共和国民法典》(主席令第45号)第五百八十五条、第五百八十四条、第八百零三条、第八百零四条《中华人民共和国民事诉讼法》(2023修正)第六十七条法释〔2015〕5号《最高人民法院关于适用〈中华人民共和国民事诉讼法〉的解释》(2022修正)第九十条2026-10-29 - 05
Extension of time caused by late delivery of employer-supplied (free-issue) materials: the statutory right to an extension (Civil Code Articles 803 / 804), three-tier quantification through the critical path and total float, an affirmative / negative scenario matrix, and procedural forfeiture of claims
Yes. Where employer-supplied materials fail to arrive at the time and to…
《中华人民共和国民法典》第八百零三条《中华人民共和国民法典》第八百零四条GB/T 50500-2024 建设工程工程量清单计价标准 第3.6.5条、第8.11.3条、第8.11.7条、第8.11.8条、第8.11.9条、第8.11.10条2026-10-29 - 06
Rules and workflow for determining the extendable days of time from the critical path and total float after the works programme changes (GB/T 50500-2024, Article 8.11.8 three tiers + Article 8.11.7 event-by-event independent accounting)
The extendable days equal 'the actual increment of the overall duration…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11.3、8.11.5、8.11.7、8.11.8、8.11.9、8.11.10条GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.7.5条JGJ/T 121-2015 · Specification for Engineering Network Planning Technology 第2.1.33、5.5.1条2026-10-29 - 07
Allocating liability when employer-cause and contractor-cause events delay completion concurrently or in succession: attribution by time segment, extension of time only for the net delay on the critical path, overlapping periods shared in proportion to responsibility, and delay damages charged only on the residual delay left after extension
Neither a 50/50 split nor full liability on either party: the governing…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.33、8.7.4、8.11.7、8.11.8、8.11.10、8.11.15、8.11.18、8.11.19条GB/T 51262-2017 建设工程造价鉴定规范 第5.7.4、5.7.6条T/ZBD 100.4-2023 建设工程造价鉴定作业指引 第4.9.7条2026-10-29 - 08
Determining extension of time for works suspended by adverse weather: the three-gate test of force majeure or abnormally adverse climatic conditions (event nature -> critical-path causation -> claim procedure), measurement of the critical path and total float, and positive-versus-negative scenario comparison
An extension of time can be granted, but not on the basis that 'the weat…
《中华人民共和国民法典》(主席令第45号)第一百八十条《中华人民共和国民法典》(主席令第45号)第五百九十条GF-2017-0201《建设工程施工合同(示范文本)》第7.6项、第7.7项(异常恶劣的气候条件)2026-10-29 - 09
Time parameters of activity-on-node networks: the recursion of time lag LAG(i,j), free float FF = min LAG and total float TF = min(LAG + TF of successors); the virtual end node's duration value and critical path identification (JGJ/T 121-2015 clauses 5.3.5~5.3.9, 5.5.1, 5.5.2)
Per JGJ/T 121-2015 clauses 5.3.7~5.3.9: for adjacent activities, LAG(i,j…
JGJ/T 121-2015 工程网络计划技术规程 第5.3.5条JGJ/T 121-2015 第5.3.6条JGJ/T 121-2015 第5.3.7条2026-10-18 - 10
Early-time activity-on-arrow time-scaled networks: the drawing rules, direct reading of ES/EF/free float off the diagram, the right-to-left recursion of total float, and the criterion that a path with no wave line from start to end is the critical path (JGJ/T 121-2015 clauses 4.4.1~4.4.3, 4.5.1, 4.5.2)
Per JGJ/T 121-2015: time-scaled networks draw activities as solid arrows…
《工程网络计划技术规程》JGJ/T 121-2015 第4.4.1条《工程网络计划技术规程》JGJ/T 121-2015 第4.4.2条《工程网络计划技术规程》JGJ/T 121-2015 第4.4.3条(式4.4.3-1~4.4.3-4)2026-10-18 - 11
Computing the six time parameters (ES/EF/LS/LF/TF/FF) of activity-on-arrow networks by the activity method: the recursions, the order of computation, identifying critical activities, and the TF >= FF self-consistency check
Per JGJ/T 121-2015 clause 4.3.1: forwards along the arrows take max (sta…
JGJ/T 121-2015 · Specification for Engineering Network Planning Technology 第4.3.1条(按工作计算法)JGJ/T 121-2015 第4.3.2条(节点最早时间)JGJ/T 121-2015 第4.5.1条(关键工作和关键线路)2026-10-18 - 12
Delay claims for design changes: critical-path determination, the time/cost double ledger, and the 28-day procedure
Delay caused by events not attributable to the contractor, such as desig…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51262-2017 建设工程造价鉴定规范TB 10402-2019 铁路建设工程监理规范2026-09-25 - 13
FIDIC Red Book 2017 EOT (8.5/20.2) vs GB/T 50500-2024 Section 8.11 delay-claim regime: the 28-day cadence, cost-and-time in one case, three-way liability, and the critical-path causation threshold
FIDIC 2017 Red Book EOT (Sub-Clause 8.5; procedure per 20.2) and GB/T 50…
FIDIC Conditions of Contract for Construction, 2nd Edition 2017, Sub-Clause 8.5/8.7/20.2, Clause 18GB/T 50500-2024 建设工程工程量清单计价标准 第8.11节2026-09-25 - 14
Calculating schedule deviations by the earned-value method (SV/SPI) and the four-step analysis procedure
Schedule deviations are calculated by earned value: SV = BCWP − BCWS (ne…
JGJ/T 121-2015 工程网络计划技术规程GB/T 50358-2017 建设项目工程总承包管理规范GB/T 50326-2017 建设工程项目管理规范2026-09-25 - 15
Identifying the critical path and the effect of critical-activity delays on total duration and duration claims
A critical activity = the activity with the least total float; the criti…
JGJ/T 121-2015 工程网络计划技术规程GB/T 50500-2024 建设工程工程量清单计价标准2026-09-25