Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-29

Extension of time caused by late delivery of employer-supplied (free-issue) materials: the statutory right to an extension (Civil Code Articles 803 / 804), three-tier quantification through the critical path and total float, an affirmative / negative scenario matrix, and procedural forfeiture of claims

Yes. Where employer-supplied materials fail to arrive at the time and to the requirements agreed, for causes attributable to the employer, the contractor may under Civil Code Article 803 extend the date of the works and claim compensation for suspension and idle-resource losses; the extension days are quantified under GB/T 50500-2024 cl. 8.11.8 - where the delayed activity is on the critical path, the delay time is the extension claimed (in full); where a non-critical activity overruns its total float and thereby becomes critical, the extension = delay time minus total float; where it remains non-critical after the delay, no extension claim arises. For causes within the employer's responsibility profit may also be claimed (cl. 8.11.10), but a Notice of Claim must be issued within the period agreed in the contract or 28 days, failing which the claim may per the contract be treated as waived; where no written confirmation of the extension was obtained but the contractor proves it applied in time on grounds conforming to the contract, courts still support the extension (Judicial Interpretation [2020] No. 25 Article 10).

Applicable Codes

  • 《中华人民共和国民法典》第八百零三条
  • 《中华人民共和国民法典》第八百零四条
  • GB/T 50500-2024 建设工程工程量清单计价标准 第3.6.5条、第8.11.3条、第8.11.7条、第8.11.8条、第8.11.9条、第8.11.10条
  • GF-2017-0201 建设工程施工合同(示范文本)第8.1、8.3.1、16.1.1、16.1.2、19.1、19.2、19.5项
  • 法释〔2020〕25号 第十条、第四十条
  • 法释〔2026〕12号 第十七条、第二十三条(2026年6月30日起施行)
  • https://www.gov.cn/zhengce/zc_flfg.htm

Positioning

Late delivery of employer-supplied (free-issue) materials is a high-frequency trigger for extensions of time. This card deals only with the 'time account': whether an extension is available (statutory right and contractual basis), how many days (quantification through the critical path and total float), which scenarios reverse the conclusion (an affirmative / negative matrix), and the procedural forfeiture risk of the extension claim. The detailed measurement of costs and profit and the itemised evidentiary requirements are in the companion card on the basis of claim and evidentiary requirements for suspension caused by late delivery of employer-supplied materials.

Core conclusions

I. The right to an extension is statutory; written confirmation is not a condition of its existence

Civil Code Article 803: 'Where the employer fails to provide raw materials, equipment, the site, funds or technical data at the agreed time and to the agreed requirements, the contractor may extend the date of the works and has the right to claim compensation for losses from suspension, idle resources and the like.'

Civil Code Article 804: 'Where the works are halted or slowed mid-course for reasons attributable to the employer, the employer shall take measures to make good or reduce the loss and compensate the contractor for the suspension, idle-resource, re-handling, plant relocation, and material and component stockpiling losses and the actual costs thereby caused.'

II. Quantifying the extension days: the critical path and total float as the dividing line

GB/T 50500-2024 cl. 8.11.8: 'When a delay event occurs, it may be determined from the approved construction progress programme whether the event lies on the critical path and whether it causes delay to the critical path; the parties shall compute the extension claimed in accordance with the following: 1 where the delaying event is an activity on the critical path, the delayed time is the extension claimed; 2 where the delaying event is an activity off the critical path and the activity becomes one on the critical path because the delay exceeds its total float, the difference between the delay time and the total float is the extension claimed; 3 where the activity remains off the critical path after the delay, no extension claim arises.'

The commentary to the same clause: activities on the critical path have a decisive influence on the progress of the whole project and determine its overall duration; prolongation of activities off the critical path should not be counted as an extension claim; where a non-critical activity becomes critical through delay, the prolongation after it becomes critical is the extension claimed.

Cl. 8.11.7: the activity corresponding to the extension claimed must be an activity on the critical path, or an activity whose claim event changes the critical path; the extension the employer approves to the contractor under the contract is the extension of the contract time for completion; each claim event is assessed independently and shall not include cost claims for the corresponding delay caused to later works by earlier delays - that is, extension days are accounted event by event, without stacking knock-on effects.

III. Affirmative / negative scenario matrix (scenario -> conclusion -> basis)

Scenario Conclusion Basis
Free-issue materials arrive later than the dates agreed in the contract and the Schedule of Employer-Supplied Materials and Equipment, the cause lies with the employer, and the affected activity is on the critical path Extension granted; extension days = the delay time of that activity (in full, in calendar days) Civil Code art. 803; GB/T 50500-2024 cl. 8.11.8 item 1; GF-2017-0201 cl. 8.3.1, cl. 16.1.1 item (4)
The affected activity is non-critical, the delay exceeds its total float and it thereby becomes critical Extension granted; days = delay time - total float GB/T 50500-2024 cl. 8.11.8 item 2
The affected activity is non-critical, the delay does not exceed the total float No extension; idle costs, reduced efficiency, plant standby and similar cost losses remain claimable cl. 8.11.8 item 3; cl. 8.11.9
Free-issue materials are non-conforming in specification, quality or quantity, or the employer changes the delivery place / delivery mode, causing prolongation Extension + cost + profit claimable GB/T 50500-2024 cl. 3.6.5 ('if the contractor's time for the works is prolonged thereby, the affected duration shall be reasonably extended under Chapter 8 of this standard and the contractor's losses, including profit, compensated') and cl. 8.11.10 item 3
The delay arises because the contractor failed to give 30 days' prior written notice of the free-issue delivery plan per the progress programme, or the plan was wrong, or it failed to check, inspect and take delivery in time or stored the materials poorly No extension; the added costs and / or delay are borne by the contractor GF-2017-0201 cl. 8.1, cl. 8.3.1; GB/T 50500-2024 cl. 3.6.4
The contractor applied for the extension within the agreed period on grounds conforming to the contract, but obtained no written confirmation from the employer / the supervising engineer The extension claim still stands and the people's court shall support it Judicial Interpretation [2020] No. 25 Article 10 para 1
The contract says 'failure to apply within the agreed period means no extension', the contractor applied late, the employer did not consent afterwards and the contractor has no reasonable justification Handled as agreed; no extension Judicial Interpretation [2020] No. 25 Article 10 para 2
The contractor failed to issue the Notice of Claim within the agreed / 28-day period May per the contract be treated as having waived the claim (procedural forfeiture) GB/T 50500-2024 cl. 8.11.3 final para; GF-2017-0201 cl. 19.1 item (1)
The employer fails to reply within 28 days of receiving the claim report Deemed approval of the contractor's claim (including the extension) GF-2017-0201 cl. 19.2 item (2)
The delay is caused by government authorities (area-wide work stoppages, transport restrictions, etc.) The time is extended accordingly; the economic losses are borne by each party itself, with no profit claim for employer breach GB/T 50500-2024 cl. 8.11.9 final para, cl. 8.11.10 final para
The contractor raises the claim only after accepting the completion payment certificate Treated as no longer entitled to claims for events arising before issue of the works acceptance certificate GF-2017-0201 cl. 19.5
The materials were late, but the contractor re-sequenced and worked in parallel so the overall duration was not actually affected No extension; claim only the reduced efficiency, second mobilisation and similar costs actually incurred GB/T 50500-2024 cl. 8.11.8, cl. 8.11.9

IV. Claimable scope and procedure (key points)

  • Costs: GB/T 50500-2024 cl. 8.11.9 lists the losses and costs claimable for causes not attributable to the contractor (losses of labour, materials, plant and water and electricity consumption during stoppage, standstill, reduced efficiency and prolongation; preliminaries costs of maintaining the site during stoppage and restart; direct costs of rework, demolition and repair; extra inspection and testing costs; the reasonably extended duration; etc.), and gives four heads for stoppage and idle-resource losses: idle costs of personnel already mobilised who cannot work, losses on materials already delivered that cannot be brought into use, standby costs of plant already on site that cannot work, and other cost losses.
  • Profit: cl. 8.11.10 - where the events listed there occur for causes within the employer's responsibility (including item 3, 'works failing to conform because the employer-supplied materials are of unqualified quality, delivered late, or the delivery place is changed'), the contractor may also claim profit in addition to economic loss, costs and / or time; losses caused by government authorities are borne by each party itself.
  • Procedure: submit a written Notice of Claim within the period agreed in the contract (28 days if none) after the event, then the claim report within the same period; for events with continuing effect, submit continuing notices at intervals of no more than 28 days, and the final report after the event ends; late submission may per the contract be treated as waiver (cl. 8.11.3).
  • Evidence priorities: the contractual basis of the free-issue scope and delivery dates (the Schedule of Employer-Supplied Materials and Equipment); actual delivery records (delivery notes, site acceptance sheets, the supervising engineer's daily log); written proof that the contractor submitted the free-issue delivery plan and its revisions 30 days in advance; the approved construction progress programme and network diagram (to prove the critical path / total float); original records of the start and end of the stoppage and of idle labour and plant.
  • Risk point: stoppage and idle-resource losses may be sued for but do not enjoy the contractor's statutory priority right to payment out of the project (Judicial Interpretation [2026] No. 12 Article 17 para 2; Judicial Interpretation [2020] No. 25 Article 40 excludes interest, liquidated damages and damages from the priority right).

Boundaries

  • The premise is that the free-issue scope and delivery times are clearly fixed in the contract (particular conditions and the Schedule of Employer-Supplied Materials and Equipment); where the contract makes the contractor procure the materials, supply is the contractor's risk and this card's extension rules do not apply.
  • Extension presupposes attribution of the delay to the employer; delay caused by the contractor's own failure to submit the delivery plan on schedule, wrong plans, failure to check and take delivery in time, or poor storage is at the contractor's own cost in both time and money.
  • The critical path and total float must be established on the approved construction progress programme (network plan); bar charts and milestone lists show no logic links and cannot directly support float computation.
  • GB/T 50500-2024 is a recommended standard; its procedural clauses bind the parties once incorporated by the contract; contrary contractual agreements (including forfeiture clauses in the particular conditions) prevail.
  • The Construction Interpretation (II) (Judicial Interpretation [2026] No. 12) takes effect on 2026-06-30: it applies to first-instance construction contract dispute cases newly accepted after that date; where SPC interpretations issued earlier conflict with it after that date, it prevails.

Further reading

  • Civil Code Articles 803 and 804 (employer failing to provide materials, equipment, the site and funds on time; compensation for mid-course halt or slowdown).
  • GB/T 50500-2024 cl. 3.6.5 (treatment of free-issue materials not conforming to the contract or to the delivery plan, and reasonable extension), cl. 8.11.3 (claim procedure and time limits), cl. 8.11.7 (event-by-event independent assessment), cl. 8.11.8 (the three-tier critical path / total float rule), cl. 8.11.9 (claimable heads and the four stoppage / idle heads), cl. 8.11.10 (profit claimable for employer responsibility).
  • GF-2017-0201 cl. 8.1 (employer-supplied materials and equipment; 30 days' prior written notice by the contractor), cl. 8.3.1 (24-hour notice before delivery, checking and acceptance, non-conformity handled under cl. 16.1), cl. 16.1.1 item (4) and cl. 16.1.2 (employer's breach events and liability), cl. 19.1-19.5 (claim procedure, reply periods, time limits for claims).
  • Judicial Interpretation [2020] No. 25, SPC Interpretation (I) on Construction Contract Disputes, Article 10 (judicial relief without an extension confirmation; agreed 'late application means no extension') and Article 40 (scope of the priority right).
  • Judicial Interpretation [2026] No. 12, SPC Interpretation (II) on Construction Contract Disputes, Article 17 (stoppage and idle losses carry no priority right) and Article 23 (effective date and scope of application to newly accepted cases).
  • The network-plan basis for computing extension days (critical path identification, total and free float, the computation flow of the three-tier rule) is in the companion card cited; the deduction and claw-back of free-issue materials at settlement is covered by the related card on settlement treatment of free-issue materials.
  • Verification of original texts: the laws and regulations database of the Chinese Government https://www.gov.cn/zhengce/zc_flfg.htm (search the Civil Code and the relevant judicial interpretations and administrative regulations).

Keywords