Bases of claim and evidentiary elements for suspension caused by late delivery of employer-supplied (free-issue) materials: the claim bases in Civil Code Arts. 803/804, costs and profit under GB/T 50500-2024 cl. 3.6.1/3.6.5, judicial relief where extension of time is uncertified, an elements table with itemised evidence, the 28-day claim procedure, and exclusion from the priority right
Yes, a claim lies, and it goes beyond an extension of time: under Civil Code Art. 803 the contractor may extend the works date and claim damages for suspension, idle time and like losses; Art. 804 lists the recoverable scope as 'losses and actual costs from suspension, idle labour and plant, double handling, relocation of plant and machinery, and accumulation of materials and components'; GB/T 50500-2024 cl. 3.6.5 goes further: where delivery dates are delayed for reasons attributable to the employer, the affected duration shall be reasonably extended and 'the contractor's losses compensated, including profit' (cl. 8.11.10 likewise allows profit to be claimed for events within the employer's responsibility). The claim must prove three links of causation (late employer-supplied delivery -> suspension of critical-path activities -> losses actually incurred). The elements are: (1) the employer-supply scope and delivery deadlines are defined; (2) the employer actually delivered late; (3) the delay falls on the critical path and caused suspension; (4) the start and end of the suspension are fixed; (5) the losses are real and quantifiable (actual-expenditure method first, rule-based standard method as fallback); (6) the contractor mitigated; (7) the claim was lodged under the 28-day two-stage procedure. Even without a certified extension of time, the contractor may still claim the extension if it applied within the contract period and the ground qualifies under the contract (Fa Shi [2020] No. 25 Art. 10). Suspension and idle-time losses are payable on action but enjoy no priority right of payment out of the works price (Fa Shi [2026] No. 12 Art. 17(2)).
Applicable Codes
- 《中华人民共和国民法典》第八百零三条、第八百零四条、第五百八十四条、第五百九十一条
- GB/T 50500-2024 第3.6.1条、第3.6.5条、第8.11.3条、第8.11.5条、第8.11.9条、第8.11.10条
- 法释〔2020〕25号《建工解释(一)》第十条、第四十条
- 法释〔2026〕12号《建工解释(二)》第十七条、第二十三条(自2026年6月30日起施行)
- T/YJXB 0001-2023 第3.0.3条、第4.0.12条、第4.0.19条、第6.0.3条、第6.0.5条、第6.0.8条
- T/ZBD 100.4-2023 第4.9.7条
- 《中华人民共和国民事诉讼法》(2023修正)第六十七条
- 法释〔2015〕5号《民诉法解释》(2022修正)第九十条
- https://www.court.gov.cn/zixun/xiangqing/504201.html
- https://www.court.gov.cn/zixun/xiangqing/504211.html
- https://www.court.gov.cn/zixun/xiangqing/504221.html
Positioning
Where employer-supplied (free-issue) materials are not delivered at the agreed time, quality or delivery conditions, causing suspension and idle time: the contractor's bases of claim for extension of time and recovery of costs / profit, the elements to be established, the itemised evidence list, and the procedural time limits. For claims, settlement and construction cost expert assessment during the performance stage of construction contracts.
Core conclusion
1. Bases of the claim (statutory texts)
- Civil Code Art. 803: 'Where the employer fails to provide raw materials, equipment, the site, funds or technical data at the agreed time and to the agreed requirements, the contractor may extend the works date and is entitled to claim damages for suspension, idle time and like losses.'
- Civil Code Art. 804: 'Where the works are stopped or slowed mid-course for reasons attributable to the employer, the employer shall take measures to remedy or reduce the loss, and shall compensate the contractor for the losses and actual costs so caused, including suspension, idle labour and plant, double handling, relocation of plant and machinery, and accumulation of materials and components.'
- Limits of the loss scope: Civil Code Art. 584 -- damages shall be equivalent to the loss caused by the breach, including benefits obtainable after performance of the contract, but shall not exceed the loss the breaching party foresaw or should have foreseen at the time of contracting; Art. 591 -- after breach the other party shall take appropriate measures to prevent enlargement of the loss, and may not claim damages for enlarged loss caused by its failure to do so; reasonable expenses incurred to prevent enlargement of the loss are borne by the breaching party.
2. Employer-supply specific rules in the pricing standard (GB/T 50500-2024)
- Cl. 3.6.1: 'The employer shall specify in the tender documents the quality and delivery conditions of the materials it supplies; when the contractor tenders, the price of the employer-supplied materials is not included in the all-in unit rate of the corresponding items. Where the employer-supplied materials fail to meet the contract, or delivery conditions change for reasons attributable to the employer, the employer shall bear the costs and (or) delay so caused and shall pay the contractor a reasonable profit.' The clause also requires the tender documents to specify the name, grade, specification and model, delivery method and place of the employer-supplied materials, and to describe them in the item descriptions of the tender BOQ.
- Cl. 3.6.5: 'Where the employer-supplied materials (e.g. specification, model, quality) fail to meet the contract or the delivery plan, or delivery dates are delayed, or the delivery place or method is changed for reasons attributable to the employer, the contractor shall assist the employer in coordinating with the supplier to remove the non-conforming materials from the site and to supply conforming materials per the delivery plan; where the contractor's duration is extended as a result, the affected duration shall be reasonably extended under the relevant provisions of Chapter 8 of this standard and the contractor's losses shall be compensated, including profit.'
- Cl. 8.11.9: for suspension, waiting, reduced efficiency, extension of duration and the like causing loss for reasons not attributable to the contractor, the contractor may claim; the losses include (1) idle labour costs of site personnel unable to work; (2) loss costs of materials on site that cannot be put to use; (3) plant standby costs of construction plant on site unable to work; (4) other cost losses.
- Cl. 8.11.10: where events within the employer's responsibility (including 'the employer's late provision of construction drawings or the construction site', 'employer-supplied materials being non-conforming in quality, provided late, or with the delivery place changed, causing the works to be non-conforming', 'employer-caused delay of duration, suspension of the works, or failure to resume on time after suspension') cause the contractor economic loss and added costs and (or) extension of duration, the contractor may, in addition to claiming the losses under cl. 8.11.9, also claim profit.
- Itemised calculation of suspension losses (idle costs, plant standby costs, suspension overheads, suspension profit) is covered by a companion card; where suspension extends the duration and material prices rise, the material price-rise cost, and the site withdrawal (demobilisation) cost after more than 30 days of suspension to avoid enlarged loss, are computed per T/YJXB 0001-2023 cl. 4.0.19 and cl. 4.0.12 (the withdrawal cost is not included in the works price).
3. Elements table (element x basis x evidence)
| # | Element | Statutory / standard basis | Evidence (ranked by probative force) |
|---|---|---|---|
| 1 | Employer-supply scope and delivery deadlines defined | Civil Code Art. 803; GB/T 50500-2024 cl. 3.6.1 | Special conditions of the construction contract; schedule of employer-supplied materials and equipment (variety, specification, quantity, delivery place, delivery date); tender documents and BOQ item descriptions; the contractor's employer-supply mobilisation schedule submitted per the programme, with receipt |
| 2 | Employer actually delivered late | Civil Code Art. 803; GB/T 50500-2024 cl. 3.6.5 | Delivery acceptance notes / consignment notes (showing actual arrival date); supervisor and construction logs; expediting letters with proof of service (EMS waybill plus receipt, email acknowledgements, original WeChat records); supplier dispatch notices; the employer's written instruction changing the delivery date |
| 3 | Delay caused suspension on the critical path | Civil Code Art. 804; GB/T 50500-2024 cl. 8.11.9 | Approved master programme / network diagram (showing the activity is on the critical path with no alternative work front); commencement order and suspension order; continuous site imagery with time stamps; records of labour and plant on site; contemporaneous records of other activities (to exclude the 'the works could have been resequenced' defence) |
| 4 | Start and end of the suspension fixed | Civil Code Art. 804; GB/T 50500-2024 cl. 8.11.3 | Suspension notice / stop order and resumption order; supervisor meeting minutes; duration certification; day-by-day construction log entries (no retrospective or back-dated entries) |
| 5 | Losses real and quantifiable | Civil Code Art. 584; GB/T 50500-2024 cl. 8.11.9; T/YJXB 0001-2023 ch. 5-6 | Labour: meeting minutes, construction logs, labour contracts / service agreements, written employment agreements, attendance sheets, payroll, wage payment records, site clock-in records (cl. 6.0.5); plant standby: mobilisation / demobilisation acceptance notes, lease contracts, construction plant inventories, project execution plan, rental settlement statements, reconciliations (cl. 6.0.3); overheads: bidding documents, budget, drawings, contract and project execution plan showing total overheads against the contract duration (cl. 6.0.8, proving the daily overhead amount) |
| 6 | Contractor discharged the duty to mitigate | Civil Code Art. 591 | Records of expediting and coordinating alternative supply; records of resequencing / releasing crews; withdrawal plan and cost vouchers where suspension exceeded 30 days |
| 7 | Claim lodged per the procedure | GB/T 50500-2024 cl. 8.11.3, 8.11.5; Fa Shi [2020] No. 25 Art. 10 | Notice of Claim, claim report with itemised cost calculations, proof of receipt / EMS receipts; even without a certified extension of time, proof that application was made within the contract period on qualifying grounds supports the extension |
| 8 | No contractor fault; concurrent delay apportioned by responsibility | T/ZBD 100.4-2023 cl. 4.9.7 | Proof of no unauthorised resequencing, no payment arrears causing supply stoppage, no unreasonable refusal to take delivery; for concurrent delay or multi-cause events, the costs are computed in proportion to the responsibility as determined |
| 9 | Effective confirmation already obtained (may replace part of the evidence) | T/YJXB 0001-2023 cl. 3.0.3; GB/T 50500-2024 cl. 8.11.5 | Site instruction records, meeting minutes, correspondence; where a site record exists it prevails; only in its absence does the standard's calculation apply; where the employer fails to respond to the claim report within the time limit and the contract is silent, it may be deemed approved |
4. Procedure and time limits (fallbacks where the contract is silent)
- GB/T 50500-2024 cl. 8.11.3: within the period agreed in the contract (28 days if none) after the claim event occurs, submit a written Notice of Claim for the works; within the period agreed in the contract (28 days if none) after the notice is issued, submit the claim report (with the cause, contractual basis, cost or days of extension, records and supporting materials, and the itemised cost calculation); claims involving both cost and duration shall be raised together; for events of continuing effect, further notices at intervals of no more than 28 days, and the final claim report within 28 days after the event ends. Where the aggrieved party fails to claim within the agreed time after the event, it may be deemed to have waived the works claim, save where the contract provides otherwise or laws and regulations provide otherwise.
- GB/T 50500-2024 cl. 8.11.5: the employer shall, within the agreed period (14 days if none) after receiving the notice, request supplementary supporting materials in writing; within the agreed period (28 days if none) after receiving the claim report or supplementary materials, reply in writing with its handling opinion; where it fails to reply within the time limit and the contract is silent, it may be deemed to have approved the works claim by the contractor; claim costs are paid at the agreed payment percentage in the current progress payment and the interim settlement by construction stage, with the balance paid in the final account.
- Fa Shi [2020] No. 25 Art. 10: 'Where the parties agree that an extension of time must be confirmed by the employer or the supervisor by certification or similar means, and the contractor, though lacking such confirmation, can prove that it applied to the employer or the supervisor for the extension within the period agreed in the contract and the ground for extension qualifies under the contract, the contractor's claim for the extension on that basis shall be supported by the people's court. Where the parties agree that failure by the contractor to apply within the agreed period means no extension of time, the agreement governs, except where the employer agrees to the extension after the agreed period or the contractor raises a reasonable defence.'
5. Exclusion from the priority right (application cut-off by date of act)
- Fa Shi [2026] No. 12 Art. 17(2): 'Where the contractor claims a priority right of payment out of the works price for suspension, idle time and like losses caused by the employer, the people's court shall not support it.' Paragraph 1 requires the court to ascertain the amount of works price enjoying the priority right and the corresponding works, and to state them in the operative part of the judgment.
- Fa Shi [2020] No. 25 Art. 40(2): a contractor's claim to priority for interest, liquidated damages or damages for late payment of the works price is not supported by the people's court.
- Time cut-off: Fa Shi [2026] No. 12 Art. 23 -- 'This Interpretation takes effect on 30 June 2026. For first-instance construction contract dispute cases newly accepted by the people's courts after this Interpretation takes effect, this Interpretation applies. After this Interpretation takes effect, where earlier judicial interpretations of the Supreme People's Court are inconsistent with it, this Interpretation prevails.' First-instance cases newly accepted after 30 June 2026 apply Interpretation II; cases accepted earlier follow Interpretation I.
6. Allocation of the burden of proof Civil Procedure Law Art. 67: a party has the responsibility to provide evidence for its own claims; evidence that a party cannot collect for objective reasons, or that the court deems necessary for the trial, shall be collected by the court. Art. 90 of the SPC Interpretation on the Application of the Civil Procedure Law: a party must provide evidence to prove the facts on which its claims rest or on which it rebuts the other party's claims; where, before judgment is rendered, it fails to produce evidence or the evidence is insufficient to prove its factual claims, the party bearing the burden of proof suffers the adverse consequence -- hence 'how much suspension loss' is proven by the contractor asserting the loss, and cannot rest on unilateral ledgers alone.
Scope and limits
- Applies only to delivery breaches by the employer (the supplying party); a material supplier's own late delivery is a breach of the sales contract: the contractor pursues the supplier, while proceeding against the employer for the extension of time under the contract (different responsible parties and different bases of claim).
- Suspension losses caused by the contractor itself (unauthorised resequencing, arrears of payments to subcontractors causing supply stoppage, unreasonable refusal to take delivery) are borne by it; concurrent delay is apportioned by responsibility per T/ZBD 100.4-2023 cl. 4.9.7; economic losses caused by force majeure or by government authorities are borne by each party itself, with the duration extended accordingly.
- Costs are taken in the order 'actual-expenditure method first, rule-based standard method as fallback'; costs that objectively need not be paid out or were not actually incurred are not counted; suspension overheads should be no higher than in the normal construction period, nor reduced to zero.
- Extensions are bounded by the critical path: a non-critical delay must exceed the total float and turn the activity critical before the excess, 'delay time minus total float', is recoverable; if it remains non-critical, time is not recoverable but the cost losses may still be claimed.
- GB/T 50500-2024 is a recommended national standard and T/YJXB 0001-2023 an association standard: where not incorporated by the contract they serve as calculation references; contract agreement or site records prevail.
- Suspension and idle-time losses are ordinary claims, payable on action but without priority ranking, and their nature is unchanged even if certified or included in the settlement total.
Further reading
- Civil Code of the PRC (Presidential Decree No. 45) Arts. 803, 804, 584, 591.
- GB/T 50500-2024 China national pricing standard for BOQ, cl. 3.6.1 and 3.6.5 (employer-supplied materials), cl. 8.11.3 (claim procedure), cl. 8.11.5 (employer handling), cl. 8.11.9 and 8.11.10 (loss scope and profit).
- Fa Shi [2020] No. 25, SPC Interpretation on Construction Contract Dispute Cases (I), Arts. 10 and 40; Fa Shi [2026] No. 12, Interpretation (II), Arts. 17 and 23.
- T/YJXB 0001-2023, Standard for Calculating Contractor's Costs upon Suspension of Construction Works, cl. 3.0.3 (site records prevail), cl. 4.0.12 (site withdrawal cost), cl. 4.0.19 (material price-rise cost), ch. 5 (calculation methods), cl. 6.0.3 / 6.0.5 / 6.0.8 (calculation source documents).
- T/ZBD 100.4-2023, Guidelines for Construction Cost Expert Assessment Practice, cl. 4.9.7 (principles for assessing delay losses and apportioning concurrent delay).
- Civil Procedure Law of the PRC (2023 amendment) Art. 67; Fa Shi [2015] No. 5, SPC Interpretation on the Application of the Civil Procedure Law (2022 amendment) Art. 90.
- SPC official pages on the release and interpretation of Fa Shi [2026] No. 12: https://www.court.gov.cn/zixun/xiangqing/504201.html ; https://www.court.gov.cn/zixun/xiangqing/504211.html ; https://www.court.gov.cn/zixun/xiangqing/504221.html
Keywords
- employer-supplied (free-issue) materials
- 发包人提供材料
- 交货日期延误
- costs of suspension
- 窝工索赔
- 工期顺延签证
- 举证材料
- 建工解释二第十七条