Work suspension caused by suppliers' delayed delivery: the contractor's loss composition, calculation methods, and legal boundaries (T/YJXB 0001-2023)

A supplier's delayed delivery is a breach of the sales contract; suspension losses are calculated item by item as "idle labor + plant standby + material losses + suspension management fee + suspension profit + site maintenance + increased statutory fees": the actual-expenditure method first, the rule-standard method as fallback (T/YJXB 0001-2023, Chapters 4, 5; GB/T 50500-2024, Clause 8.11.9). Claims are triple-limited by the Civil Code's foreseeability rule (Article 584), the duty to mitigate (Article 591), and the evidence chain, and the contractor simultaneously runs the 28-day extension procedure with the employer.

Applicable Codes

  • T/YJXB 0001-2023 建设工程停工承包人费用计算标准
  • GB/T 50500-2024 建设工程工程量清单计价标准
  • 中华人民共和国民法典 第584、591条

Topic Positioning

The claimable item list, calculation methods, and legal boundaries for a contractor claiming losses from a supplier when delayed delivery suspends the works. Applies to suspensions caused by suppliers/third parties (not by the employer).

Core Conclusions

Legal characterization: delayed delivery is breach of contract; compensation covers actual losses + lost profits (e.g., suspension profit), limited by the Civil Code Article 584 foreseeability rule and Article 591 duty to mitigate; agreed liquidated damages below actual losses may be increased on request, and those excessively above (judicial practice usually caps at 30% above the loss) may be reduced on request. Loss composition and algorithms (T/YJXB 0001-2023, Chapters 4, 5; GB/T 50500-2024, Clause 8.11.9): ① Idle on-site production labor: wages actually paid, or by reference to published labor price information (government guidance prices)/quota rates (5.0.5); ② Plant standby costs: rented plant at actual rent, owned plant at shift quota rates (5.0.3); ③ Scrapping, wastage, and demobilization losses of materials already on site that cannot be used; ④ Suspension management fee: daily management fee = total contract management fee ÷ contract duration, × suspension days × a reasonable ratio, neither exceeding the normal construction period nor zero (4.0.8/5.0.8); ⑤ Suspension profit: daily profit = total contract profit ÷ contract duration, × suspension days × a reasonable ratio — a lost-profit loss (4.0.9/5.0.9); ⑥ Site maintenance costs: utilities, watch and guard, and resumption measures (8.11.9, item 3); ⑦ Increased statutory fees: accrued on the labor cost extended by the suspension at statutory rates (4.0.22). Triple boundaries: indirect losses beyond the supplier's foreseeable scope (lost bids, reputation) are not supported; losses from failure to actively mitigate (emergency re-sourcing, reasonable demobilization) are not claimable; the evidence chain — suspension notices, idle-time attendance, rental contracts and rent vouchers, wage payment records, schedule comparisons — is indispensable.

Applicable Boundaries

Applies to supplier/third-party-caused suspensions; employer-caused suspensions have different claim targets and bases (see the cited card). The actual-expenditure method first, rule-standard method as fallback; costs not actually incurred are not counted. Contract terms on liquidated damages and price adjustment prevail. The claimed amount may be calculated fully by the rules to leave negotiation room.

Further Reading

T/YJXB 0001-2023, Standard for Calculating Contractor's Costs upon Work Suspension of Construction Works, Chapter 4 (4.0.3/4.0.8/4.0.9/4.0.22) and Chapter 5 (5.0.3/5.0.5/5.0.8/5.0.9); GB/T 50500-2024, Standard for Valuation of Construction Works with Bills of Quantities, Clause 8.11.9; Civil Code, Article 584 (foreseeability rule), Article 591 (duty to mitigate); claim procedures per the 28-day dual-node rules.