Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Evolution of the 28-day time limit for construction claims: GB 50500-2013 'forfeiture of the right to claim' vs GB/T 50500-2024 'may be deemed waived', and the 28-day fallback where the contract is silent

GB 50500-2013 (abolished), Clause 9.13.2: the contractor shall submit a Notice of Claim within 28 days after knowing, or ought to have known, of the claim event; 'if the contractor fails to issue the Notice of Claim within the time limit, it forfeits the right to claim' (hard forfeiture). GB/T 50500-2024 (current, recommendatory), Clause 8.11.3, changes this to submission of the Notice of Claim 'within the period agreed in the contract (28 days if not agreed)', and where overdue, it 'may be handled as agreed in the contract' (soft treatment - the strength of forfeiture is delegated to the contract), plus a catch-all clause: 'where the aggrieved party fails to lodge a claim within the agreed time after the claim event arises, it may be deemed to have waived the relevant construction claim, unless otherwise agreed in the contract or provided by laws and regulations.' Where the contract sets no period, the 28-day limit still applies as fallback (Notice of Claim then report, dual nodes), and the overdue consequence falls under 'may be deemed waived', leaving room for exemption through contrary contract agreement, other provisions of laws and regulations, and the discretionary word 'may'.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 第8.11节
  • GB 50500-2013 建设工程工程量清单计价规范 第9.13.2条(已废止)

Topic Positioning

Compares the provisions on the 28-day claim time limit between GB 50500-2013 (abolished mandatory national standard) and GB/T 50500-2024 (current recommendatory national standard), answering two practical questions: 'does a late Notice of Claim still forfeit the right to claim?' and 'what applies if the contract sets no period?'

Core Conclusions

2013 edition (GB 50500-2013, Clause 9.13.2; mandatory national standard, abolished): the period was locked at 28 days - 'the contractor shall, within 28 days after knowing, or ought to have known, that a claim event has occurred, submit to the employer a Notice of Claim stating the grounds of the claim event; if the contractor fails to issue the Notice of Claim within the time limit, it forfeits the right to claim.' Subsequent nodes: within 28 days after issuing the Notice of Claim, formally submit the claim notice (with records and supporting documents); for continuously affecting events, submit successive claim notices; within 28 days after the influence of the claim event ends, submit the final claim notice.

2024 edition (GB/T 50500-2024, Section 8.11; recommendatory national standard, current) - three key changes:

  1. Basis of the period: from a standard-locked 28 days to 'the period agreed in the contract (28 days if the contract is silent)' - contractual agreement takes precedence and 28 days becomes a fallback;
  2. Consequence of a late Notice of Claim: from 'forfeits the right to claim' to 'handled as agreed in the contract' - the standard itself no longer directly divests the right; the strength of forfeiture is left to the contract;
  3. New catch-all clause (end of Clauses 8.11.3 and 8.11.4): 'where the aggrieved party fails to lodge a claim within the agreed time after the claim event arises, it may be deemed to have waived the relevant construction claim, unless otherwise agreed in the contract or otherwise provided by laws and regulations' - 'may be deemed' plus the 'unless' proviso leaves room for exemption.

2024 procedure chain (where the contract is silent):

  • Contractor's claims (8.11.3): submit a written Notice of Claim within 28 days after the event; then submit the construction claim report within 28 days after the Notice of Claim (detailing causes, the contract clauses relied on, and the cost and/or extension of time claimed, with records, supporting documents and a calculation schedule of the claimed cost); cost increases and extensions of time are claimed together; for continuous influence, submit successive Notices of Claim at contract-agreed intervals (not exceeding 28 days if not agreed) or at reasonable intervals, listing cumulative amounts/days; within 28 days after the continuous influence ends, submit the final construction claim report.
  • Employer's counter-claims (8.11.4): the same nodes apply to construction claims other than delay damages.
  • Employer's handling of the contractor's claim (8.11.5): if additional materials are considered necessary, the employer requests them in writing within the contract-agreed period (14 days if not agreed) after receiving the Notice of Claim; after receiving the claim report or supplementary materials, the employer replies in writing with its handling opinion within the contract-agreed period (28 days if not agreed); if no reply is given within that period, it 'may be deemed approval' (China's deemed-approval rule upon lapse of the response period); claims involving both cost and time are approved together; agreed claim costs are paid at the contractual payment ratio in the current progress payment and interim settlement by construction stage (China's 2020 milestone-based interim settlement regime, which has no exact international equivalent), with the balance paid in the final account.

What if the contract sets no period: on the period level, the 28 days still applies as fallback (Notice of Claim then report, dual nodes); on the consequence level, the catch-all 'may be deemed to have waived the relevant construction claim' applies - no agreed period does not mean no period, and a late claim may still be found waived, though the room for remedy is wider than under the 2013 edition (the contract may provide otherwise, other laws and regulations may exempt, and the word 'may' leaves latitude).

Applicable Boundaries

  • GB 50500-2013 is abolished and serves only to understand the evolution of provisions and for older contracts that cite it; current contracts are governed by GB/T 50500-2024.
  • GB/T 50500-2024 is a recommendatory national standard (GB to GB/T); its claim procedure clauses are not mandatory and bind the parties only once incorporated by the contract. In practice, what truly binds the parties are the contract's general conditions (e.g., the procedure of Clause 19.1 of GF-2017-0201) and the particular conditions - how the contract is written matters more than how the standard is written.
  • 28 days is a procedural forfeiture period, not a limitation period (the Civil Code, Article 188, provides a three-year limitation period); the two mechanisms coexist, and a procedural lapse may still forfeit the right.
  • Judicial practice (not the standard's text, for reference): procedural forfeiture clauses have consistently been applied strictly; where a mere late Notice of Claim neither prejudices the other party's ability to adduce evidence nor is the substantive claim time-barred, courts are generally reluctant to dismiss the substantive right; but where the particular conditions expressly provide that an overdue claim is deemed waived, the risk is high when the other party invokes this defence.

Further Reading

  • GB/T 50500-2024, China national pricing standard for BOQ, Section 8.11 (8.11.3 contractor's construction claims, 8.11.4 employer's construction claims, 8.11.5 employer's handling of the contractor's claim), chapter on adjustment of the contract price.
  • GB 50500-2013, Code for Valuation with Bills of Quantities (BOQ) for Construction Works, Clause 9.13.2 (abolished), as the historical comparison.
  • For procedural details and judicial positions, see the cited cards: 28-day dual-node procedure and evidence checklist (card_09c641f2), the employer's 28-day reply period and 14-day supplementation period and the 'deemed approval upon lapse of the response period' judicial position (card_2ce4a194), tiered forfeiture for overdue site instructions / variation records (card_7dab16b3), and the chain of evidence review framework for claims (card_36aada75).