The columns and content of the Notice of Claim for works claims: the division of detail between notice and formal claim report, the prescribed forms and the clause basis

The system splits claim documents into two levels: the Notice of Claim (GB/T 50500-2024 clause 8.11.3 item 1 - within the contractual period after the event, 28 days if not agreed, stating only 'the cause of the event and the intention to claim') and the claim report (items 2 and 5 - cause, contract clauses relied on, the fee or extension days claimed, with records, evidence and a calculation schedule). The fullest column list is DB37/T 5028-2022 clause 9.5.4: the notice carries time, synopsis, basis, a preliminary assessment of cost and time impact and the claim declaration; the review form carries the detailed account, grounds, clauses, amount and evidence - the line between levels is 'preliminary assessment' versus 'amount plus evidence'. Forms per GB/T 50319-2013 Tables C.0.3 (notice) and B.0.13 (cost claim review, in triplicate).

Applicable Codes

  • GB/T 50500-2024 第8.11.2、8.11.3、8.11.4、8.11.5、8.11.21条
  • GB/T 50319-2013 第6.4.3、6.4.4、6.4.5条及App. BTable B.0.13、App. CTable C.0.3
  • DB37/T 5028-2022 第9.5.4条
  • T/CAEC 006-2024 第7.3.8条
  • GB/T 50326-2017 第7.5.8条

Positioning

How to write a Notice of Claim - which columns, to what depth - separating the two levels of claim documents (notice / claim report and review form), their forms and clause basis, with the normative source of each column.

Core conclusions

1. First, the levels: there is no generic "claim notification"

Level 1 - the Notice of Claim (a rights-preservation letter). GB/T 50500-2024 clause 8.11.3 item 1: "The contractor shall, within the contractual period after the claim event (28 days if not agreed), submit a written Notice of Claim stating the cause of the event and the intention to claim. Failure to give notice in time is dealt with per the contract." At the notice stage the standard requires exactly two things: the cause and the intention to claim.

Level 2 - the claim report (the substantive demand). Item 2: "within the contractual period after the notice (28 days if not agreed), submit a written claim report detailing the cause, the contract clauses relied on, and the fee and/or extension days claimed, with the necessary records, evidence and a calculation schedule of the claim cost." Item 5 (final report): detail the whole event, clauses, and the aggregate fee and/or days. Item 3: fees and extensions "are claimed together"; item 4: continuously affected events - continuing notices at the contractual interval (28 days if not agreed) listing cumulative fees and/or days.

The general requirement (even a notice needs grounds). Clause 8.11.2: "A claiming party shall claim within the contractual period with reasonable grounds and valid basis and evidence, per the contract and the law." Claims are "economic compensation, not punishment"; either party may claim; "events already price-adjusted under the (non-claim) adjustment rules are not claimed again".

The employer's mirror duties. Clause 8.11.4 sets the same sequence for employer claims other than delay damages (28-day notice, 28-day report, continuing notices, final report within 28 days after the event ends) - fees only, no extension. Clause 8.11.21: both parties follow clauses 8.11.3~8.11.6 and countersign the adjusted duration and claim cost, as the basis of progress payments and settlement; agreed claim costs are paid currently with progress and interim settlement payments.

Forfeiture and deemed approval (three clauses, same wording): "A prejudiced party failing to claim within the agreed time is, save as otherwise agreed or provided by law, deemed to have waived the claim. Where the claiming party submits the report as agreed and the other party fails to reply within the agreed time, it is deemed to have approved the claim as made."

2. The column skeleton: the fullest normative list

Forms. GB/T 50319-2013 clause 6.4.4: "The cost-claim notice follows Table C.0.3; the cost-claim review form follows Table B.0.13." Table B.0.13 note: in triplicate (supervision, employer, contractor); the evidence includes the notice itself - the notice is a required attachment to the later review, so sending it first is both procedure and evidence.

Columns (DB37/T 5028-2022 clause 9.5.4): "The cost-claim notice includes the time of the event, a synopsis, the claim basis, a preliminary assessment of cost and time impact, and the claim declaration. The review form includes a detailed account of the event, the grounds, the contract clauses, the amount and the evidence." The chief supervising engineer may attach a review report: date of acceptance, the demand, the process, the confirmed grounds and contract basis, the approved amount and its computation.

3. Column-by-column mapping

Column Requirement and depth Source
1 Project data / receipt names, contract number, addressee, sender, date; receipt time starts the contractual response period GB/T 50319-2013 Table C.0.3; T/CAEC 006-2024 clause 7.3.8 item 4
2 Contract basis clauses relied on - listed at notice stage, detailed in the report 8.11.3 items 2/5; DB37/T 5028 clause 9.5.4
3 Event description notice: time + synopsis; report: detailed account, cause, grounds DB37/T 5028 9.5.4; 8.11.3
4 Loss (cost/time) computation notice: preliminary assessment only; report: amount, extension days and a calculation schedule DB37/T 5028 9.5.4; 8.11.3 item 2; GB/T 50326-2017 clause 7.5.8
5 Evidence list notice: "claim basis"; report: necessary records and evidence (documents, objects, audio-visual, electronic data, witness statements, expert opinions, inspection records - verified before use) 8.11.3 item 2; GB/T 50326-2017 7.5.8
6 Declaration / reservation the "claim declaration" is a listed notice column; "reservation of rights" clauses are practice additions, not standard columns - their function is served by the notice itself plus continuing notices (8.11.3 item 4) DB37/T 5028 9.5.4; 8.11.3 item 4

4. Review-side thresholds (setting the required depth)

  • Supervision procedure (GB/T 50319-2013 clause 6.4.3): accept timely notices - collect materials - accept timely review forms - review (requesting detail within the period where needed) - after tripartite agreement, issue the review within the period to the employer.
  • Approval conditions (clause 6.4.5, all three required): 1 the contractor claimed within the contract period; 2 the event is not caused by the contractor and complies with the contract; 3 it caused the contractor direct economic loss.
  • Review focus and acceptance limits (T/CAEC 006-2024 clause 7.3.8): the supervision unit replies on acceptance within the agreed period; the chief supervising engineer's review focuses on "compliance with the contract" and "the validity of the event materials"; claims filed outside the agreed period may be refused.
  • Employer time limits (8.11.5): requests for further materials within the agreed period (14 days if not agreed) after the notice; reply to the report or materials within the agreed period (28 days if not agreed) - silence "is dealt with per the contract and, absent agreement, may be deemed approval of the contractor's claim"; fees and time claimed together are approved together; agreed claim costs are paid at the contractual ratio in current progress / interim payments, the balance in the final account.
  • Three conditions of a valid claim (GB/T 50326-2017 clause 7.5.8): claimed per the contract (or the law where silent); materials collected completely; notice and report filed per the agreed or statutory procedure and periods - basis, evidence and procedure are interlinked and indispensable.

Applicable boundaries

  1. GB/T 50500-2024 is recommended: its periods and procedures yield to the contract, 28 days (and 14 for employer requests) being fallbacks only.
  2. The column list fits employer-contractor claims under BOQ pricing; the supervision forms (C.0.3 / B.0.13) fit supervised works - unsupervised projects adjust the addressee and format, but the two-level structure and depth requirements stand.
  3. A notice never replaces the report (no substantive demand); filing a report without a prior notice risks a finding of late claiming (out-of-period claims may be refused, T/CAEC 006-2024 clause 7.3.8).
  4. Events already price-adjusted under the non-claim rules are not claimed again (8.11.2).
  5. "Reservation of rights" is a practice addition, not a standard column; its effect depends on the timeliness of continuing notices and the final report.

Further reading

  • GB/T 50500-2024 clauses 8.11.2~8.11.5, 8.11.21.
  • GB/T 50319-2013 clauses 6.4.3~6.4.5; Appendix C Table C.0.3; Appendix B Table B.0.13.
  • DB37/T 5028-2022 clause 9.5.4; T/CAEC 006-2024 clause 7.3.8; GB/T 50326-2017 clause 7.5.8.