Time limits for giving and processing claims for extension of time and cost under GB/T 50500-2024 clause 8.11 (dual 28-day nodes applying in both directions, 14-day request for further particulars), consequences of default, the nature of claims and the evidence checklist

Claims for time or cost follow dual 28-day nodes: a written Notice of Claim must be issued within 28 days after the claim event arises, and the claim report must be submitted within 28 days after the Notice of Claim is issued; the rule applies in both directions (the contractor's claims under 8.11.3 and the employer's reverse claims under 8.11.4 share the same nodes); claims involving both time and cost must be raised together; where the employer considers further particulars necessary it must request them within 14 days of receiving the Notice of Claim and reply in writing within 28 days of receiving the claim report, failing which the claim is deemed accepted (8.11.5); the contractor, when processing the employer's claim, must likewise reply in writing within 28 days of receiving the report, failing which the claim is deemed accepted, and the amount may be deducted from progress payments, stage settlements during construction or the final account payment (8.11.6); where the injured party fails to make its claim within the time limit, it is deemed to have waived the claim (late Notices of Claim may be dealt with as agreed in the contract); a claim is economic compensation, not a penalty, and events already adjusted under the price-adjustment rules must not be claimed again (8.11.2). Five categories of evidence must be kept: contractual basis; instructions and correspondence (keep proof of receipt); site records (site instructions must be certified and signed off); the impact of the event; and financial vouchers.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11.1、8.11.2、8.11.3、8.11.4、8.11.5、8.11.6、8.11.7、8.11.21条
  • GB/T 50500-2024 第11.1.1、11.1.2、11.1.4、11.1.5、11.2.4~11.2.8、11.4.1、11.4.3、11.4.5条

Topic Positioning

This card answers the complete procedure and time-limit questions of construction claims: the submission deadlines and default consequences for the Notice of Claim, the claim report, further notices for continuing events and the final claim report (bidirectional - the contractor claiming against the employer and the employer claiming against the contractor), the reply deadlines by which each party processes the other's claim, how claim monies are paid or deducted, the legal nature of a claim, and the checklist of evidence to be kept. It applies to the general situation where the contract agrees no claim periods and the 28-day default time limits of clause 8.11 of GB/T 50500-2024 govern.

Core Conclusions

Under clause 8.11 of GB/T 50500-2024 "Pricing Standard for Bill of Quantities of Construction Works": where the contract agrees other periods, the contract prevails; absent agreement the following default day counts apply:

General provisions (8.11.2): claims shall be made within the period agreed in the contract, supported by reasonable grounds and a valid basis and proof documents, and shall comply with the contract and with laws and regulations. Under the Civil Code, a claim is an act by which the employer and the contractor, each on the basis of the contract, safeguard their own lawful interests; its nature is economic compensation, not a penalty; the contractor may claim against the employer, and the employer may likewise claim against the contractor. A construction claim covers compensation for economic loss and/or adjustment of time; where both occur they shall be raised together; where the price of an event has already been adjusted under the contract price adjustment provisions (excluding claims), no construction claim shall be calculated again.

1. Contractor claiming against the employer (8.11.3): within the contract-agreed period (28 days absent agreement) after the claim event arises, submit a written Notice of Claim stating the cause of the event and the intention to claim; within the contract-agreed period (28 days absent agreement) after the Notice of Claim is issued, submit a written claim report stating the cause, the contract clauses relied on, the cost claimed and/or the number of days of extension of time, attaching the necessary records and supporting documents and a schedule of the claim calculation; claims involving both additional cost and extension of time shall be raised together; for events with continuing effect, further Notices of Claim must be submitted at contract-agreed intervals (not exceeding 28 days absent agreement) or at reasonable intervals (describing the continuing effect, providing records, and listing the cumulative claimed cost / days of delay), and within the contract-agreed period (28 days absent agreement) after the event ends, submit the final claim report.

2. Employer claiming against the contractor (8.11.4, except delay damages): likewise follows "Notice of Claim 28 days -> claim report 28 days -> continuing effect: further notices at intervals of not more than 28 days -> final claim report within 28 days after the event ends"; the rules are symmetrical with the contractor's claims.

3. Employer processing the contractor's claim (8.11.5): where the employer considers further particulars necessary, it shall request them in writing within the contract-agreed period (14 days absent agreement) after receiving the Notice of Claim; within the contract-agreed period (28 days absent agreement) after receiving the claim report or the further particulars, it shall reply in writing with its decision; cost and time claims shall be approved together; once the claimed cost is agreed through negotiation, the employer shall pay it at the contractual payment percentage in the current progress payment or the interim settlement by construction stage, and pay the remainder in the final account payment.

4. Contractor processing the employer's claim (8.11.6): within the contract-agreed period (28 days absent agreement) after receiving the employer's claim report, the contractor shall reply in writing with its decision; failing a reply within the time limit, it may be deemed to have accepted the employer's construction claim; once the claimed cost is agreed through negotiation, the employer may deduct the determined claim amount from the current progress payment, the interim settlement by construction stage or the final account payment.

Three tiers of wording for the consequences of default: (i) late Notice of Claim - the clause reads "where the contractor fails to issue the Notice of Claim for a construction claim in time, it may be dealt with as agreed in the contract" (8.11.3 paragraph 1, 8.11.4 paragraph 1); the 2024 edition no longer states directly that the right is lost, the consequence being remitted first to the contract; (ii) where the injured party fails to make its claim within the agreed time, "except as otherwise agreed in the contract and otherwise provided by laws and regulations, it may be deemed to have waived the relevant construction claim" (default time-bar clause); (iii) where the claiming party submits its claim report as agreed and the other party fails to reply within the agreed time or makes no reply, it "may be deemed to have accepted the relevant construction claim claimed by the claiming party" - applying symmetrically to the employer (8.11.5 paragraph 2) and the contractor (8.11.6 paragraph 1).

These 28-day periods are contractual procedural time-bar periods, not the limitation period for litigation; do not delay the nodes on the ground of the three-year limitation period under the Civil Code. FIDIC Red Book 2017 clause 20.2.1 likewise uses a 28-day baseline. Evidence is filed in five categories: contractual basis (tender documents, contract and supplementary agreements, drawings, project execution plan, design briefing); instructions and correspondence (design-change instructions with dates of service, receipts for correspondence, minutes of meetings); site records (construction/supervision diaries, progress comparisons, certified and signed-off site instructions, dated photographs and video); the impact of events (dates and quantities of water and power stoppages and road openings/closures, dates of interference and restoration, weather records); financial vouchers (amounts and dates of advance and progress payments, vouchers for material procurement, transport and acceptance, price and wage indices). Based on GB/T 50319-2013 clause 6.4.1 and the 16-item list in DB37/T 5130-2018 clause 7.6.8; he who claims must prove; site instructions must be certified and signed off, and records must be dated.

Applicable Boundaries

Applies to the claim procedures between employer and contractor on domestic construction works (including the employer's reverse claims and both parties' processing roles); where the contract agrees other periods, the contract prevails - the particular conditions may agree otherwise (e.g. 14 days) and the contract governs. The 28-day nodes are a procedural time bar; they coexist with, and must not be confused with, the limitation period for litigation. Clause 8.11.4 does not apply to claims for delay damages (liquidated damages in nature), which are handled separately under the particular conditions. The "no further construction claim" rule in 8.11.2 means matters already adjusted under the other price-adjustment rules of chapter 8 (e.g. variations, changes in costs, provisional sums etc.) must not be claimed twice. The evidence checklist is general guidance, subject to the contract and the supervising engineer's requirements; local standards (e.g. the Shandong DB37 series) are for regional reference only, and international works follow the FIDIC clauses.

Further Reading

See GB/T 50500-2024 "Pricing Standard for Bill of Quantities of Construction Works" clause 8.11 construction claims: 8.11.2 nature of claims and exclusion of double recovery, 8.11.3 the contractor's claim procedure, 8.11.4 the employer's claim procedure, 8.11.5 the employer's procedure for processing claims, 8.11.6 the contractor's procedure for processing claims; GB/T 50319-2013 "Code for Construction Project Supervision of Construction Works" clause 6.4.1 (evidence checklist for cost claims); DB37/T 5130-2018 "Specification for Construction Cost Consulting Services" clause 7.6.8 (16-item verification list); DB37/T 5009-2022 "Rules for Management of Construction Supervision Documents" (he who claims must prove); FIDIC Red Book 2017 clause 20.2.1 (the 28-day notice period for international works). The contractual prerequisites of the "deemed acceptance" mechanism may be understood by reference to Article 21 of the SPC judicial interpretation Fa Shi [2020] No. 25 and GB/T 50500-2024 clause 10.3.8 (deemed acceptance where the final account is not checked within the time limit).