GF-2017-0201 Model Construction Contract, General Conditions clause 19.1, the contractor claims procedure chain: Notice of Claim (short form, event grounds only) - claim report (detailed form: claim grounds + additional payment amounts and/or extension of time + supporting records) - continuing claim notice - final claim report; two separately running 28-day periods and the time-bar consequences of missing them
Under General Conditions clause 19.1 of GF-2017-0201: the Notice of Claim must be submitted to the supervising engineer within 28 days after the contractor becomes aware or deemed aware of the claim event and need only 'state the grounds on which the claim event arose'; failure to give it within those 28 days means the contractor 'loses the right to additional payment and/or extension of time'. The claim report must be formally submitted within 28 days after the Notice of Claim is given and must 'detail the claim grounds and the additional payment amounts and/or extension of time demanded, with the necessary records and supporting documents'. The two 28-day periods run independently (the former from the event, the latter from the giving of the Notice of Claim); they are not a single 56-day bundle after the event. For events with a continuing effect, the first Notice of Claim must still be given within 28 days of the event, otherwise the whole claims chain is broken.
Applicable Codes
- GF-2017-0201《建设工程施工合同(示范文本)》通用条款第19.1、19.2、19.5条
- GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第9.13节〔索赔〕、第9.14节〔现场签证〕(已被GB/T 50500-2024替代)
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11节〔工程索赔〕
- GB/T 50319-2013 · Code for Construction Project Supervision Table C.0.3、Table B.0.13
- DB37/T 5028-2022《建设工程监理工作规程》第9.5.4条
- TB 10402-2019 · Standard for Construction Quality Acceptance of Railway Water Supply and Drainage Works App. C Table C.0.2
Topic positioning
For construction contracts adopting the GF-2017-0201 Model Construction Contract, this card sets out the two core documents in the contractor claims procedure chain of General Conditions clause 19.1 - the 'Notice of Claim' and the 'claim report' - their respective required contents, the starting points and interlocking of the two 28-day periods, and the legal consequences of losing rights through lateness; and clarifies the correspondence with the claims provisions of the BOQ pricing standards (GB 50500-2013 section 9.13; GB/T 50500-2024 section 8.11).
Core conclusions
1. The procedure chain in the original text of 19.1 [Contractor's claims]
'In accordance with the contract, where the contractor considers itself entitled to additional payment and/or an extension of time, it shall make a claim to the employer through the following procedure:
(1) Within 28 days after the contractor becomes aware or deemed aware of the claim event, the contractor shall submit a Notice of Claim to the supervising engineer, stating the grounds on which the claim event arose; if the contractor fails to give the Notice of Claim within the said 28 days, it loses the right to additional payment and/or extension of time;
(2) Within 28 days after giving the Notice of Claim, the contractor shall formally submit a claim report to the supervising engineer; the claim report shall detail the claim grounds and the additional payment amounts and/or extension of time demanded, with the necessary records and supporting documents;
(3) Where the claim event has a continuing effect, the contractor shall continue to submit continuing claim notices at reasonable intervals, stating the actual situation and records of the continuing effect and listing the cumulative additional payment amounts and/or days of extension of time;
(4) Within 28 days after the effect of the claim event ends, the contractor shall submit a final claim report to the supervising engineer, stating the final additional payment amounts and/or extension of time claimed, with the necessary records and supporting documents.'
2. Division of labour between the two documents (a two-level structure deliberately designed by the standard)
- Notice of Claim = short form; the sole statutory content requirement is to state the grounds on which the claim event arose. Its function is to preserve rights within the time limit; it carries no burden of proof or quantification, so no amount or number of days need be fixed within the 28 days.
- Claim report = detailed form; three statutory content requirements: (1) detail the claim grounds; (2) the additional payment amounts and/or extension of time demanded; (3) attach the necessary records and supporting documents.
- In practice the Notice of Claim may add a reservation-of-rights declaration; the supervision system refines the forms - the cost claim Notice of Claim is filed on form C.0.3 of GB/T 50319-2013, Code for Construction Project Supervision, and the cost claim review form on form B.0.13; local supervision rules add detail: the cost claim Notice of Claim should state the time of the event, an outline of the event, the claim basis, a preliminary assessment of the cost and time effects, and the claim declaration; the cost claim review form should contain a detailed account of the event, the claim grounds, the contract clauses, the amount and the supporting documents; when the chief supervising engineer issues the review form it may attach a claim examination report (date of acceptance, claim demand, claim history, the confirmed claim grounds and contractual basis, the approved claim amount and its calculation method). Railway supervision uses form C.0.2 of appendix C to TB 10402-2019 [Notice of Claim], whose format requires the contract clause, the event that occurred and the statement that 'the occurrence of the event was not caused by us', with claim event materials attached.
3. The time-limit chain (per GF-2017-0201)
T0 (becoming aware or deemed aware of the event) -> within 28 days: submit the Notice of Claim (lateness forfeits rights) -> within 28 days from giving the Notice: submit the claim report -> for continuing effects, continuing claim notices at reasonable intervals listing the cumulative amounts / days -> within 28 days after the effect ends: the final claim report -> the supervising engineer completes its review and forwards it to the employer within 14 days of receiving the claim report (and, if it disagrees, may require submission of complete copies of the original records) -> the employer issues its claim determination signed by the employer within 28 days after the supervising engineer receives the claim report or further supporting materials; 'if the employer fails to respond in time, the contractor's claim demand is deemed approved' -> if the contractor accepts the determination, the claim sum is paid in the current progress payment; if not, clause 20 [dispute resolution] applies.
4. Final closure (19.5 [time limit for making claims])
After the contractor receives the completion payment certificate under clause 14.2 [review of the final account], it is deemed no longer entitled to raise any claim for events arising before the issue of the taking-over certificate; the final closure application submitted under clause 14.4 [final closure of accounts] may claim only events arising after the issue of the taking-over certificate, and the time limit for making claims ends on acceptance of the final closure certificate.
5. Common citation corrections
In the BOQ pricing standards, the claims provisions are not in 'section 9.14': section 9.14 of GB 50500-2013 is [site instruction records] (9.14.1 to 9.14.5, requiring the contractor to submit a site instruction record within 7 days of receiving the employer's instruction and the employer to verify and confirm it or propose modifications within 48 hours of receipt, failing which, with neither confirmation nor comment given, it is deemed approved); the claims procedure is in section 9.13 (9.13.2 Notice of Claim 28 days, claim notice 28 days, continuing notices for continuing effects, final claim notice within 28 days after the end; 9.13.3 the employer replies within 28 days, deemed approved if it fails to answer in time, and the claim sum enters the current progress payment). The two sections are parallel lines and must not be substituted for each other. GB 50500-2013 has been replaced by GB/T 50500-2024, Standard for Valuation with Bill of Quantities of Construction Works, whose counterpart is section 8.11 [construction claims], with time limits expressed as 'the period agreed in the contract (28 days if none is agreed)', the consequence of lateness changed from 'loses the right to claim' to 'may be handled as agreed in the contract', and the general provision worded as 'may be deemed to have waived the relevant claim against the works'.
Applicable boundaries
- Clauses 19.1 to 19.5 are General Conditions of the GF-2017-0201 Model Construction Contract and apply only where the contract actually adopts the model text and the particular conditions make no special provision on the claims procedure; where the particular conditions provide otherwise (e.g. shortening or lengthening the notice periods, changing the recipient), those provisions prevail.
- The recipient under the model text is the supervising engineer (for the employer's side, 'through the supervising engineer'), unlike the wording 'submit to the employer' in GB/T 50500-2024; in practice, submit per the route agreed in the contract and retain proof of receipt.
- '28 days' is the period set by the General Conditions of the model text, consistent with the 28 days of the 2013 BOQ pricing code; the 2024 standard changes this to 'the period agreed in the contract, 28 days if none is agreed'; the two apply to different subjects (one is a contract text clause, the other a recommended provision of a pricing standard) and must not be cited interchangeably.
- Forfeiture through lateness is a contractually agreed loss of rights; whether it can defeat statutory claims (e.g. compensation of substantive loss caused by the employer) still requires assessment against contract validity, breach liability clauses and limitation periods, and must not be absolutised in every situation.
- This card does not cover the calculation of claim costs or the critical path tests for delay; see the construction claims chapter of the pricing standard.
Further reading
- GF-2017-0201 Model Construction Contract, General Conditions: clause 19.1 (contractor claims procedure), clause 19.2 (handling of the contractor's claims: 14-day engineer review, 28-day employer response, deemed approval on lateness), clauses 19.3 / 19.4 (the employer's claims and their handling, mirrored procedure), clause 19.5 (time limit for making claims), and clause 14.2 [review of the final account], clause 14.4 [final closure of accounts], clause 20 [dispute resolution]; the corresponding places in Part Two, particular conditions, may set special periods.
- GB 50500-2013, Code of Valuation with Bill of Quantities of Construction Works: section 9.13 [claims] (9.13.1 to 9.13.9) and section 9.14 [site instruction records] (9.14.1 to 9.14.5).
- GB/T 50500-2024, Standard for Valuation with Bill of Quantities of Construction Works: section 8.11 [construction claims] (8.11.3 contractor claim requirements, 8.11.5 employer handling of contractor claims, 8.11.7 independent assessment of delay claims, 8.11.8 critical path and total float tests, 8.11.9 scope of claimable costs, 8.11.10 profit claimable for employer-responsibility causes).
- GB/T 50319-2013, Code for Construction Project Supervision: form C.0.3 (cost claim Notice of Claim), form B.0.13 (cost claim review form); DB37/T 5028-2022, Specification for Construction Supervision Work, clause 9.5.4; TB 10402-2019, Code for Supervision of Railway Construction Works, appendix C form C.0.2 (Notice of Claim).
Keywords
- Notice of Claim
- 索赔报告
- GF-2017-0201
- 28 days
- 监理人
- 逾期失权
- 延续索赔通知