Claim costs in the final account: settlement line item + 28-day procedure chain + review and determination rules

Claim costs enter the final account only where both procedural compliance and a complete chain of evidence are satisfied: (1) line item — item 11 of the final account price under GB/T 50500-2024, Clause 10.3.2 is the "engineering claim amount", a separately billed item in the final account documents; (2) procedure — absent contract agreement, the 28-day chain applies (Notice of Claim -> claim report -> continuing notices -> final report); failure to give notice in time is deemed waiver, and the other party's failure to respond in time is deemed acceptance (8.11.3/8.11.4); (3) determination — amounts are stated per the claim documents and confirmed site instructions signed by both parties, and where disputed instructions enter appraisal they are computed under the GB/T 51262-2017 5.9.1 rules.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 51262-2017 建设工程造价鉴定规范
  • DBJ41/T 208-2018 建设工程监理工作标准
  • GB/T 50875-2013 工程造价术语标准

Topic Positioning

The route by which claim costs enter the final account: which line item they sit under, what procedure preserves the claim right, and how review and appraisal determine the amounts.

Core Conclusions

  1. Line item: the final account price is itemized per GB/T 50500-2024, Clause 10.3.2; item 11 is the "engineering claim amount", parallel to variation increase/decrease amounts and penalties, and is a separately billed item in the final account documents.
  2. Procedure (Clauses 8.11.3/8.11.4, absent agreement): submit the Notice of Claim within 28 days of the event; submit the claim report within 28 days after giving notice; for continuing effects, submit continuing notices at intervals not exceeding 28 days; submit the final claim report within 28 days after the event ends. Failure to give notice in time is deemed waiver; the other party's failure to respond in time is deemed acceptance.
  3. Amount determination: review rests on the claim documents and confirmed site instructions signed by both parties; appraisal follows GB/T 51262-2017, Clause 5.9.1 — where the signed instruction states labour, material and machinery quantities and prices, those are followed; where only labour quantities are given without unit prices, the corresponding labour unit rates are marked up by about 20%; where only material and machine-shift quantities are given without prices, the corresponding prices apply; where only a total amount is given, that total applies; where the instructed quantity differs from the quantity actually executed, the actual completed quantity applies.

Applicable Boundaries

Applies to the handling of claim costs at the employer-contractor final account stage; where the contract provides otherwise, the contract governs. Whether a claim stands also depends on attribution of responsibility and the chain of evidence — evidence checking is not developed in this card.

Further Reading

GB/T 50500-2024, Clauses 10.3.2, 8.11.3, 8.11.4; GB/T 51262-2017, Clause 5.9.1; DBJ41/T 208-2018, Clause 9.4.4; GB/T 50875-2013, Clause 3.4.8.