Claim costs in the final account: settlement line item + 28-day procedure chain + review and determination rules
Claim costs enter the final account only where both procedural compliance and a complete chain of evidence are satisfied: (1) line item — item 11 of the final account price under GB/T 50500-2024, Clause 10.3.2 is the "engineering claim amount", a separately billed item in the final account documents; (2) procedure — absent contract agreement, the 28-day chain applies (Notice of Claim -> claim report -> continuing notices -> final report); failure to give notice in time is deemed waiver, and the other party's failure to respond in time is deemed acceptance (8.11.3/8.11.4); (3) determination — amounts are stated per the claim documents and confirmed site instructions signed by both parties, and where disputed instructions enter appraisal they are computed under the GB/T 51262-2017 5.9.1 rules.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB/T 51262-2017 建设工程造价鉴定规范
- DBJ41/T 208-2018 建设工程监理工作标准
- GB/T 50875-2013 工程造价术语标准
Topic Positioning
The route by which claim costs enter the final account: which line item they sit under, what procedure preserves the claim right, and how review and appraisal determine the amounts.
Core Conclusions
- Line item: the final account price is itemized per GB/T 50500-2024, Clause 10.3.2; item 11 is the "engineering claim amount", parallel to variation increase/decrease amounts and penalties, and is a separately billed item in the final account documents.
- Procedure (Clauses 8.11.3/8.11.4, absent agreement): submit the Notice of Claim within 28 days of the event; submit the claim report within 28 days after giving notice; for continuing effects, submit continuing notices at intervals not exceeding 28 days; submit the final claim report within 28 days after the event ends. Failure to give notice in time is deemed waiver; the other party's failure to respond in time is deemed acceptance.
- Amount determination: review rests on the claim documents and confirmed site instructions signed by both parties; appraisal follows GB/T 51262-2017, Clause 5.9.1 — where the signed instruction states labour, material and machinery quantities and prices, those are followed; where only labour quantities are given without unit prices, the corresponding labour unit rates are marked up by about 20%; where only material and machine-shift quantities are given without prices, the corresponding prices apply; where only a total amount is given, that total applies; where the instructed quantity differs from the quantity actually executed, the actual completed quantity applies.
Applicable Boundaries
Applies to the handling of claim costs at the employer-contractor final account stage; where the contract provides otherwise, the contract governs. Whether a claim stands also depends on attribution of responsibility and the chain of evidence — evidence checking is not developed in this card.
Further Reading
GB/T 50500-2024, Clauses 10.3.2, 8.11.3, 8.11.4; GB/T 51262-2017, Clause 5.9.1; DBJ41/T 208-2018, Clause 9.4.4; GB/T 50875-2013, Clause 3.4.8.
Keywords
Related Cards
- →
Bases for determining final account quantities: completed qualifying quantities + measurement certification and sign-off lock-in + measurement method by contract type
The final account quantity (in FIDIC contexts, the Final Statement plus discharge) = the qualifying quantities actually completed by the contractor in accordance with the contract and to be measured, calculated under the contract-agreed national and industry quantity take-off (measurement) standards and supplementary calculation rules; the measurement results certified and signed off by both parties (including documents for interim settlement by construction stage (China's 2020 node-based interim settlement system; no exact international equivalent)) serve as the basis for settlement (GB/T 50500-2024 Clauses 7.1.1, 7.1.8, 10.3.1). Lump-sum contracts adjust only the agreed adjustable contents; re-measurable (unit-rate) contracts measure actual completed quantities; cost-plus contracts calculate cost, fee, and taxes per the agreed method; as-built drawings, changes, site instructions/variation records, and concealed-acceptance records form the chain of evidence for 'actual completion'.
- →
Linking the five document types — contract, drawings, BOQ, site instructions / variation records, settlement — and managing the settlement chain of evidence
Using unified codes as the bond, lineage relations attached via linking fields, on-the-spot linkage in the workflow, and a basis for settlement ledger as the master index, build contract, drawings, BOQ, site instructions / variation records, and settlement into a traceable chain of evidence: every settlement amount must be able to state which contract clause it relies on, which BOQ item it corresponds to, which drawing it comes from, and which site instruction / variation record triggered it; only when the four elements are complete and certification and sign-off are complete is it included in settlement.
- →
Whether the employer's overdue non-reply to the final account documents is deemed acceptance of the submitted amount - the three-requirement test of Fa Shi [2020] No. 25, Article 21, and interface with GB/T 50500-2024
Where the contract stipulates 'overdue non-reply is deemed acceptance', under Fa Shi [2020] No. 25, Article 21, the people's court shall support the contractor's claim for settlement per the final account documents (submitted price); three requirements must be met simultaneously: an express contractual stipulation, delivery of complete settlement documents, and no reply within the agreed period. Absent such stipulation, claims based only on ministerial rules or model contract texts containing 'deemed acceptance' wording are not supported by the SPC and the overwhelming majority of courts. GB/T 50500-2024, Clause 10.3.8, points the same way but is a recommendatory national standard that becomes a contractual obligation only when incorporated by the contract; at the rule level, Article 16 of the former MOC Decree No. 107 has been carried over by Article 18 of MOHURD Decree No. 16, with 28 days as the default period absent agreement.
- →
A verification framework for judging the completeness of a construction claim evidence chain: three-factor multiplication, four fact links, four-question checks
A claim holds = the multiplicative product of basis + evidence + procedure — any factor at zero zeroes the result; the evidence chain must link by link support the four fact links "event occurred → cause attributable → consequence → loss quantified", with each document checked by four questions — timeliness, competent party, relevance, and corroboration; procedurally, absent contract terms, claims proceed on the 28-day two-node basis, and late submission is deemed waiver.
- →
Preventing over-settlement and duplicate settlement of subcontracted quantities: dual-signature locking of measurement + interim settlement by construction stage merged into the final account + the list of items not measured
Preventing over-settlement/duplicate settlement relies on procedural control rather than account-checking error correction: measurement results, once signed and confirmed by both parties, are locked as the basis for settlement (GB/T 50500-2024 Clauses 7.1.7/7.1.8); signed interim settlement by construction stage documents are merged into the final account and are not re-measured or re-priced (Clause 10.2.3); after dual signing of the final account no repeated checking is allowed (Clause 10.3.12); quantities with unapproved commencement reports, failed acceptance, beyond the construction drawings, unlawful subcontracting or contract transfer (re-letting of the whole works), rework, etc. are not measured at all (TB 10402-2019 Clause 6.0.6 and others).
- →
Work completed but not certified: three-way classification of the nature of the missing certification + staged remedial paths + chain of evidence priority
Completed work without certification does not mean working for nothing: factual increments may still be claimed on an actuals basis once supplementary evidence is assembled; stoppage/idle-time claims may be procedurally time-barred if not notified within 28 days (where the contract is silent); purely verbal instructions with no physical evidence carry the greatest risk. Remedy by stage — where the final account is not yet finalized, retrospective certification or written clarification permits adjustment on an actuals basis (GB/T 51095-2015 8.3.6); a final account not certified and signed off does not take effect, and objections with supplementary evidence remain possible (GB/T 50500-2024 10.3.11/10.3.12); once in construction cost expert assessment, compute on actually completed quantities, and defective certifications may be listed as separate opinions (GB/T 51262-2017 5.9.1/5.9.2). Chain of evidence: acceptance records > supervision measurement logs > as-built drawings + photographs > minutes and correspondence > cost vouchers.
Cited By
- ←
Distinguishing claims for extension of time from cost claims: an axis-by-axis comparison of the two independent remedies, time and money, on causation threshold (critical path), basis of calculation (delay duration / total float vs actual-cost method / total-cost method), whether profit is claimable, evidence and time limits, plus the rules of combined calculation and joint approval where both are claimed together
An EOT claim asks for time, a cost claim asks for money; both are economic compensation, not penalty (GB/T 50500-2024 clauses 2.0.31, 8.11.1, 8.11.2). The core divide: an EOT claim is hard-gated by the critical path - delay to work on the critical path is taken at the delay duration; delay to non-critical work that exceeds its total float and turns critical is taken as delay duration minus total float; if the work remains non-critical, no EOT claim arises (8.11.8). A cost claim does not require the critical path, only direct economic loss (8.11.9, 8.11.11). Both share one 28-day procedure (8.11.3); a claim involving both cost increase and extension of time must be raised together and approved jointly by the employer (8.11.3 para 3, 8.11.5 para 3); in calculation the EOT outcome is confirmed first and cost computed on it, each event assessed separately with no double counting.
- ←
Measurement of rework and the rules on rework compensation: the written rework confirmation requirement and the consequences of delay, the two measurement branches by responsible party (employer responsibility vs contractor fault), the order for setting rework rates (the three tiers of variation valuation), and the eight categories of employer-responsibility events carrying an additional profit claim
Under GB/T 50500-2024: the contractor must submit a written rework confirmation request within the time agreed in the contract; on expiry the rework is deemed not to have occurred, the rework quantities are not measured and no costs are compensated (Article 7.6.1). Where the rework arises from a variation or the employer's responsibility, the rework items, quantities and amounts of written-off or scrapped materials stated in the rework confirmation sheet form the measured quantities and are priced under Chapter 8; rework attributable to the contractor is not measured (Article 7.6.4). Rework rates follow the three tiers of variation valuation: where the price list has an applicable item, adopt its rates and prices; where none is applicable but a similar item exists, proceed by reference to the similar item; where neither exists, set new rates on a cost-plus-profit basis. Where the employer's responsibility causes rework, profit is claimable in addition to economic loss and increased costs (Article 8.11.10).
- ←
The force majeure processing chain: immediate notice -> continuing interim reports -> final report within 28 days after the end of the event -> Notice of Claim and claim report -> review and reply by the other party -> confirmation, signing and concurrent payment, plus the 84-day/140-day termination exit (GF-2017-0201 Clauses 17.2/17.4/19 and GB/T 50500-2024 Clauses 8.11.3/8.11.5/8.11.21)
After a force majeure event occurs, the party shall immediately notify the other party and the supervising engineer in writing with supporting proof; while the event continues, interim reports must be submitted, and the final report within 28 days after the event ends (GF-2017-0201 Clause 17.2); cost and time claims merge into the claims procedure: within the contractual period after the event (28 days if not agreed), a written Notice of Claim is submitted, and within the same period after its issue the claim report; for continuing effects, further notices at intervals of no more than 28 days or at reasonable intervals, and the final report within the period after the end; the employer may, within 14 days (if not agreed) after receiving the Notice of Claim, request further particulars in writing, and shall reply in writing within 28 days (if not agreed) after receiving the report, failing which the claim may be treated as approved (GB/T 50500-2024 Clauses 8.11.3 and 8.11.5; GF Clauses 19.1~19.4); the parties shall confirm and sign the adjusted duration and the claim costs as the basis for progress payments and settlement, paid concurrently (Clause 8.11.21); where force majeure prevents performance of the contract continuously for more than 84 days or cumulatively for more than 140 days, both parties are entitled to terminate (Clause 17.4).
- ←
GF-2017-0201 Model Construction Contract, General Conditions clause 19.1, the contractor claims procedure chain: Notice of Claim (short form, event grounds only) - claim report (detailed form: claim grounds + additional payment amounts and/or extension of time + supporting records) - continuing claim notice - final claim report; two separately running 28-day periods and the time-bar consequences of missing them
Under General Conditions clause 19.1 of GF-2017-0201: the Notice of Claim must be submitted to the supervising engineer within 28 days after the contractor becomes aware or deemed aware of the claim event and need only 'state the grounds on which the claim event arose'; failure to give it within those 28 days means the contractor 'loses the right to additional payment and/or extension of time'. The claim report must be formally submitted within 28 days after the Notice of Claim is given and must 'detail the claim grounds and the additional payment amounts and/or extension of time demanded, with the necessary records and supporting documents'. The two 28-day periods run independently (the former from the event, the latter from the giving of the Notice of Claim); they are not a single 56-day bundle after the event. For events with a continuing effect, the first Notice of Claim must still be given within 28 days of the event, otherwise the whole claims chain is broken.
- ←
Calculation of plant standby costs when the works stand suspended for reasons attributable to the employer: standby cost = standby rate per machine-shift x number of standby machine-shifts, the cost components of the standby machine-shift rate, whether overheads and profit are taken, and the difference in compensation scope between contractor-owned plant (priced on machine-shift rate norms) and hired plant (priced on hire charges)
Plant standby cost = sum of (standby rate per machine-shift x number of standby machine-shifts); the number of standby machine-shifts is fixed as 'idle plant units x days of suspension x machine-shift conversion factor per day (an 8h working day = 1 machine-shift per unit per day)'. Under T/YJXB 0001-2023 Clause 5.0.3: hired plant is priced on the hire charges actually incurred during the suspension, and contractor-owned plant on the machine-shift rate norms. The standby rate per machine-shift is built up from depreciation + labour cost + other charges (the Shandong and Jiangsu scope); the Hunan scope takes machine-shift depreciation only, with idle operator and banksman costs calculated separately per certified site records; repair, maintenance and power charges are excluded. The standby rate carries no uplift for overheads or profit; where the employer is liable, profit may be claimed separately under GB/T 50500-2024 Clause 8.11.10 (listed alone under the suspension-profit rule, not duplicated inside the machine-shift rate).
- ←
GB/T 50500-2024 clause set 8.8: adjustments of contract price and duration for changes in laws, regulations and policies - scope, the one-way adjustment rule during extended durations, and no adjustment of overheads and profit
GB/T 50500-2024 clause 8.8: for laws, regulations, policy provisions or government interpretations newly enacted, amended or repealed after the contract base date, price and/or duration adjust per the contract and the rules published by the authorities; policy changes during contractor-caused extension adjust downward only (8.8.2), during employer-caused extension upward only (8.8.3); where policy change causes material extension and subsequent abnormal market price moves, the price-fluctuation rules apply (8.8.1/8.8.2/8.8.3); overheads and profit inside the total and unit prices never adjust for policy changes (8.8.5).
- ←
The columns and content of the Notice of Claim for works claims: the division of detail between notice and formal claim report, the prescribed forms and the clause basis
The system splits claim documents into two levels: the Notice of Claim (GB/T 50500-2024 clause 8.11.3 item 1 - within the contractual period after the event, 28 days if not agreed, stating only 'the cause of the event and the intention to claim') and the claim report (items 2 and 5 - cause, contract clauses relied on, the fee or extension days claimed, with records, evidence and a calculation schedule). The fullest column list is DB37/T 5028-2022 clause 9.5.4: the notice carries time, synopsis, basis, a preliminary assessment of cost and time impact and the claim declaration; the review form carries the detailed account, grounds, clauses, amount and evidence - the line between levels is 'preliminary assessment' versus 'amount plus evidence'. Forms per GB/T 50319-2013 Tables C.0.3 (notice) and B.0.13 (cost claim review, in triplicate).
- ←
Time limits for giving and processing claims for extension of time and cost under GB/T 50500-2024 clause 8.11 (dual 28-day nodes applying in both directions, 14-day request for further particulars), consequences of default, the nature of claims and the evidence checklist
Claims for time or cost follow dual 28-day nodes: a written Notice of Claim must be issued within 28 days after the claim event arises, and the claim report must be submitted within 28 days after the Notice of Claim is issued; the rule applies in both directions (the contractor's claims under 8.11.3 and the employer's reverse claims under 8.11.4 share the same nodes); claims involving both time and cost must be raised together; where the employer considers further particulars necessary it must request them within 14 days of receiving the Notice of Claim and reply in writing within 28 days of receiving the claim report, failing which the claim is deemed accepted (8.11.5); the contractor, when processing the employer's claim, must likewise reply in writing within 28 days of receiving the report, failing which the claim is deemed accepted, and the amount may be deducted from progress payments, stage settlements during construction or the final account payment (8.11.6); where the injured party fails to make its claim within the time limit, it is deemed to have waived the claim (late Notices of Claim may be dealt with as agreed in the contract); a claim is economic compensation, not a penalty, and events already adjusted under the price-adjustment rules must not be claimed again (8.11.2). Five categories of evidence must be kept: contractual basis; instructions and correspondence (keep proof of receipt); site records (site instructions must be certified and signed off); the impact of the event; and financial vouchers.
- ←
Full process of construction payment: advance payment, safety-measures fee, progress payment, interim settlement by construction stage, final account, retention money and final settlement (GB/T 50500-2024 Chapters 9-10)
Payment along the timeline in six segments: advance payment (for works with contractor-procured materials, neither below 10% nor above 30% of the contract price after deducting provisional sums etc., prepaid before commencement, recovered as agreed) → statutory safety provisions (at least 50% prepaid within 28 days after commencement; not deducted from progress payments, recovered once at the final account) → progress payments (amount due = cumulative completed − cumulative paid − deductions; not less than 80% of the cumulative completed value where the contract is silent) → interim settlement by construction stage (new in 2024: signed stage settlements enter the final account without re-pricing; stage payments not below 80%) → final account (thirteen heads; failure to check or to certify in time is deemed acceptance) → retention money (3% cap) and final closure (defects liability period generally 1 year, 2 at most). The chain runs on contract-agreed time limits with a 28-day backstop; judicial enforcement of "accepted at the submitted price" requires an express contractual provision.
- ←
Re-work confirmation requirements and claim procedure deadlines for material scrap from variations/employer-risk events: notice of intent within 28 days, claim report, employer reply in 14/28 days, and deemed waiver/acceptance on default (GB/T 50500-2024, 7.6.1/8.11.3/8.11.5)
Material-scrap claims require a written re-work confirmation demand within the contractual time — failing which no scrap is deemed, re-work is unmeasured and uncompensated (7.6.1); claims require a written Notice of Claim within the contractual period (28 days if silent) after the event and a claim report (with cost computation sheets) within 28 days thereafter, continuing notices at <= 28-day intervals for continuing effects and a final report within 28 days after they end — late filing may be deemed waiver (8.11.3); the employer replies in writing within 28 days of the report, silence may be deemed acceptance; claim costs are paid proportionally in progress payments and stage settlement payments and the balance in the final account (8.11.5).
- ←
The non-equivalence of FIDIC 2017 Red Book delay machinery and the national-standard delay regime: delay fact / EOT / Delay Damages vs delay claims / extensions / delay damages / liquidated damages
Not equivalent. FIDIC never treats delay as a single term: it is a chain "delay fact -> attribution -> (EOT 8.5 or Delay Damages 8.8)", while the national standard splits the same chain into separate tools - delay claims, delay damages, liquidated damages. At the fact level (neutral time fact) the systems agree; at the time-relief level they are isomorphic (FIDIC 8.5 EOT <-> GB/T 50500-2024 delay claim/extension); at the money-penalty level they look alike but differ in core: FIDIC 8.8 makes Delay Damages the "only damages" for late completion (except fraud, gross negligence, deliberate default, reckless misconduct, and 15.2 termination), while GB 8.11.19 lets the employer "choose one or more" (extended warranty / extra cost / delay damages / liquidated damages) cumulatively. GB/T 50500-2024 term 2.0.33 renders delay damages as "delay damages" in English - masking the exclusivity difference. Both systems share the 28-day procedure (FIDIC 20.2.1 bar; GB 8.11.3/8.11.4 defaults plus deemed waiver/acceptance).
- ←
The contractual definition and form requirements of a Notice under FIDIC 2017 Red Book (1.1.56 + 1.3): formal compliance is constitutive - a non-compliant document is not a Notice
In FIDIC 2017 Red Book, Notice is a term of art: 1.1.56 defines "'Notice' means a written communication identified as a Notice and issued in accordance with Sub-Clause 1.3". Three cumulative elements: (1) in writing; (2) identified as a Notice; (3) issued per 1.3 (signed paper original or designated electronic system, copies to the other side). The logic runs "formal compliance makes it a Notice carrying contractual effect", not "effect first, certification later"; a document failing the elements is an ordinary communication and cannot trigger any mechanism conditioned on giving a Notice - claims (20.2.1: 28-day bar on additional payment) or NODs (1.1.57/3.7.5: the special Notice of Dissatisfaction within 28 days of determination, preconditioning arbitration under 21.4.4).
- ←
Supplementing omitted claims after final-account double signing: the dual bars of procedural forfeiture and finality of settlement, and the exception windows (GB/T 50500-2024 Clauses 8.11.3 and 10.3.12)
After the final-account documents are signed and sealed by both parties, claims for events that occurred before settlement but were not asserted then cannot, in principle, be supplemented: (1) procedurally, failure to serve the claim notice/report within the contractual (default 28-day) periods forfeits the claim (GB/T 50500-2024 Clause 8.11.3); (2) substantively, the double-signed account takes contractual effect and cannot be re-audited (Clause 10.3.12) - the settlement absorbs accrued but unasserted costs. Exception windows: express reservation in the settlement documents, events arising after settlement, the employer's written undertaking (independent debt), and rescission of the settlement for gross misunderstanding or obvious unfairness (Civil Code Articles 147, 151, 152).
- ←
Site instructions and certified records overview: applicable matters and prohibited items, the five-node handling procedure, graded signing authority, the 2024 standard basis and settlement application
Certification runs a five-node closed loop: assess reasonableness beforehand and survey the original conditions → at occurrence, measure on site, keep photos, have all parties sign the original vouchers → submit the certification file within the contract-agreed time → the supervising engineer reviews, the chief supervising engineer signs, the employer approves → participate in acceptance, confirm the completed content and compute the final cost. Signature authority: written documents signed by both parties' site management within their scope of duty are valid pricing vouchers (GB/T 50500-2024 cl. 12.2.1); the supervisor certifies facts strongly but prices weakly — priced certifications need the joint sign-off of employer, contractor and supervisor (T/CAEC 006-2024 cl. 7.2.9); a one-party signature binds only the signing party. With the 2024 code dropping the site-certification clause, off-contract work flows through three channels — variation, additional works and dayworks — and dayworks certification reports not verified in time are deemed accepted (cl. 7.5.5).
- ←
Design change overview: authority to propose, classification and grading, approval and implementation, three-tier pricing, settlement and disputes across six links (with variation concept cross-links and FIDIC mapping)
The design-change full chain: any of four parties may propose; only the original designer issues the document (Survey and Design Administration Regulations, art. 28); the chief supervising engineer must sign it off before construction; approve first, then construct; price on the three-tier ladder; settle on the documents. Procedural red lines: verbal instructions are no pricing voucher (unless construction per them is proven); the supervisor's emergency verbal instruction must be confirmed in writing within 24 hours (local supervision codes); emergency-rescue works proceed first with formalities completed within 10 working days. Pricing runs the ladder "identical — contract rate; analogous — converted; different — negotiated" (GB/T 50500-2024 cl. 8.9.1), with quantities beyond ±15% re-rated (down for increases, up for decreases) and the preliminaries scheme to be submitted before execution or the adjustment forfeited. Claims run the double 28-day limit, forfeited on default; the variation price takes the ninth head of the final account, disputes assessed across five tiers by instructions, drawings and confirmations.