Full process of construction payment: advance payment, safety-measures fee, progress payment, interim settlement by construction stage, final account, retention money and final settlement (GB/T 50500-2024 Chapters 9-10)

Payment along the timeline in six segments: advance payment (for works with contractor-procured materials, neither below 10% nor above 30% of the contract price after deducting provisional sums etc., prepaid before commencement, recovered as agreed) → statutory safety provisions (at least 50% prepaid within 28 days after commencement; not deducted from progress payments, recovered once at the final account) → progress payments (amount due = cumulative completed − cumulative paid − deductions; not less than 80% of the cumulative completed value where the contract is silent) → interim settlement by construction stage (new in 2024: signed stage settlements enter the final account without re-pricing; stage payments not below 80%) → final account (thirteen heads; failure to check or to certify in time is deemed acceptance) → retention money (3% cap) and final closure (defects liability period generally 1 year, 2 at most). The chain runs on contract-agreed time limits with a 28-day backstop; judicial enforcement of "accepted at the submitted price" requires an express contractual provision.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准(第9.1~9.4、10.1~10.3、10.5节)
  • 财建〔2004〕369号 建设工程价款结算暂行办法
  • 建质〔2017〕138号 建设工程质量保证金管理办法
  • 住建部令第16号 建筑工程施工发包与承包计价管理办法(第十八条,28日兜底)
  • 法释〔2020〕25号 最高人民法院施工合同司法解释(一)第21条
  • 《保障中小企业款项支付条例》《保障农民工工资支付条例》
  • 《招标投标法实施条例》第58条(履约保证金上限)

An entry card for the construction payment domain: it strings along the time axis every tranche the employer pays the contractor — advance payment, statutory safety provisions, progress payments, interim settlement by construction stage, the final account, retention money and final closure — over the underlying machinery of GB/T 50500-2024 chapters 9 and 10: "time limits as agreed in the contract" plus "deemed approval on silence". What readers look up most: advance-payment ratios and recovery; the 80% progress-payment floor; how stage settlement and the final account link up; the consequences of failing to check or pay in time; the 3% retention cap and the release procedure. The card gives the whole-chain rule framework and navigates the 80-plus cards of this domain.

Concept and mechanism

The chain at a glance. The employer's payments to the contractor flow in six segments: advance payment (mobilisation and materials before commencement) → statutory safety provisions prepaid (immediately after commencement) → progress payments (interim payments) → interim settlement by construction stage (locked in stage by stage) → final account (consolidated confirmation) → retention money and final closure (winding up after the defects liability period). Chapter 9 governs payment and chapter 10 settlement; procedural time limits are always as agreed in the contract, backstopped by deemed-approval rules — a structural change from the 2013 code's fixed periods (28 days and the like).

Advance payment and statutory safety provisions. The advance payment is the payment made before commencement for mobilisation and materials, ring-fenced and interest-free; for works with contractor-procured materials it should be neither below 10% nor above 30% of the contract price after deducting provisional sums, dayworks and provisional sums for nominated specialist subcontract works (multi-year major projects: prepaid annually in proportion to the annual plan), and may be covered by an equal advance-payment guarantee; it is recovered in one or several instalments as agreed (the customary set-off point estimated by T = P − M/N), and on termination the unrecovered balance is deducted in full in the termination settlement. Statutory safety provisions: at least 50% of the total is prepaid within 28 days after commencement (cl. 9.3.2); the remainder is paid alongside progress payments, not deducted from them, and recovered once at the final account; if the employer fails to pay on time, the contractor may press for payment and ultimately suspend the works, and the employer bears corresponding responsibility for accidents so caused (cl. 9.3.3).

Progress payments (interim payments). Amount due this period = cumulative value of works completed to date − cumulative payments already made − deductions due this period (cl. 9.1.6, 9.4.9). The cumulative completed total includes eleven heads: the contract BOQ amounts, BOQ error adjustments, provisional sums, provisional-price adjustments, the main contractor's attendance and coordination provisions, dayworks, changes in costs, changes in laws and policies, variations, additional works and claims. Where the contract is silent, the payment percentage should be not less than 80% of the cumulative completed value (cl. 9.1.7); the application must list the current period's construction workers' wages on a separate line. Procedure: the employer should check within a reasonable time and issue the payment certificate (cl. 9.4.11), the draft certificate going first to the contractor for confirmation and payment following by the agreed last-payment day (cl. 9.1.10, 9.1.11). Measurement is the precondition of payment — quantities fixed, then money paid; on disputed items, the certificate is issued for the undisputed part and paid first.

Interim settlement by construction stage. New in the 2024 edition (cl. 10.2): the settlement nodes (monthly / quarterly / annual / physical progress) and the procedure are as agreed in the contract; stage settlement documents signed by both parties are carried into the final account without re-measurement or re-pricing (cl. 10.2.3) — except that preliminaries and the main contractor's attendance and coordination provisions are provisional in character and recomputed at the final account. Stage payments should be not less than 80% of the current stage settlement amount (cl. 10.2.4) — with the progress-payment floor this forms the "twin 80%": the former a contractual floor that agreement cannot break through, the latter a default floor where the contract is silent.

Final account. It starts once taking-over (completion acceptance) of the whole works has passed (cl. 10.1.4) and runs submission → checking → re-checking → confirmation under seal. The settlement price is listed in thirteen heads in order: the total contract BOQ price; BOQ error adjustment; provisional sum adjustment; provisional-price adjustment; adjustment of the main contractor's attendance and coordination provisions; dayworks; changes in costs; changes in laws and policies; variations; additional works; claims; liquidated damages; and others (cl. 10.3.2). The default chain: failing to check or comment within the agreed time → the settlement documents are deemed accepted (cl. 10.3.8); failing to verify the payment application or issue the payment certificate → the application is deemed accepted and payable as submitted (cl. 10.3.16); still not paying → the contractor presses for payment and claims under cl. 8.11.9 (cl. 10.3.17). Once both parties have signed and sealed, no re-checking and no further claims over pre-settlement events (cl. 10.3.12). Where no period is agreed, the 28-day backstop applies (MOHURD Order No. 16, art. 18); judicially, enforcing "accepted at the submitted price" requires an express contractual provision (Fa Shi [2020] No. 25, art. 21).

Retention money and final closure. Retention is capped at 3% of the total settled price (a bank guarantee may substitute to the same cap; where performance security has already been provided, double withholding is in principle not allowed — performance security is capped at 10% of the awarded contract price and covers performance during construction, while retention covers repairs during the defects liability period; the two may coexist at the final account). The defects liability period is generally 1 year, 2 at most, running from passing of completion acceptance (where the employer delays acceptance, it runs automatically 90 days after submission of the completion report); within 14 days after expiry the employer verifies and returns the retention, silence being deemed acceptance of the application, and the returned retention carries no interest. After the defects liability period ends, final closure of accounts follows; failure to check in time is deemed agreement to the closure application (cl. 10.5). Chain-wide floors: where the price is disputed, the undisputed part is paid first; labour costs are never suspended amid any dispute.

Card-group navigation

Chain rules: advance payment and safety provisions

  • Agreeing and paying the advance payment (cl. 9.2): nature, ratio, guarantee and recovery (card_a3406408)
  • Advance-payment ratio, old vs new code: 2024 cls 9.2.2/9.2.3, 10%-30% (card_c5357961)
  • Recovery mechanics: two recovery methods and the set-off point formula (card_368fd38f)
  • Low contract payment ratio: quantifying the advance-financing pressure and the code floor (card_9cbd5c35)
  • Prepaying and paying statutory safety provisions (cls 9.3.2/9.3.3) (card_ebc4e22c)
  • Safety-provision prepayment, two editions: 2013 60% vs 2024 50% (card_e28fc14c)

Chain rules: progress payments

  • Computing progress payments: the cumulative-difference method and the eleven heads (card_9fd927b3)
  • Fixing the progress-payment percentage and the payment certification procedure (card_385e03c8)
  • Progress payments vs stage payments — the "twin 80%": comparing the wording strength (card_5dfdafe7)
  • The twin-80% rule: 2024 cls 9.1.7 and 10.2.4 vs 2013 60%-90% (card_7e455790)
  • Progress-payment application contents and the submission-and-issue procedure (Annex F) (card_0aaeccf6)
  • The payment application (certification) form structure and advance-payment set-off entries (card_4c081ff8)
  • The employer's review time for progress payments: the reasonable-time backstop and the payment certificate (card_70c7fccb)
  • Funding risk when review runs late: deemed approval plus pay-the-undisputed-first (card_25d4e3b6)
  • Reported output value vs actual quantities: a three-layer cross-check (card_8987bbed)
  • Measurement and payment: quantities fixed, then money paid (card_634c6823)
  • Railway measurement and valuation for payment vs building progress payments: the core differences (card_b9e707fb)

Chain rules: interim settlement by construction stage

  • The stage-settlement system (cl. 10.2): nodes, procedure and computation of the price (card_d4521708)
  • Linking stage settlement to the final account: preliminaries and attendance provisions recomputed at completion (card_8405a93e)
  • Subcontract monthly settlement and payment ledgers: two-layer architecture, monthly flow (card_834f9318)
  • Preventing over- and duplicate settlement of subcontract quantities: the dual-sign measurement lock (card_dbb315f0)

Chain rules: final account

  • The final account at a glance: trigger, thirteen heads, review and finality (card_bff5c025)
  • Final-account line items and their order (cl. 10.3.2, thirteen heads) (card_b80a4d20)
  • The final account defined: definition, tiers and basis (card_ba7d74d1)
  • Starting the final account: the trigger points and the time chain (card_e51ecdf6)
  • Compiling the final account: basis, review points and review time limits (card_50ffc543)
  • The full documentary checklist and the deliverables of a final account (card_32055d98)
  • Precedence of pricing bases at the final account: the contract prevails (card_d4631db4)
  • Quantities at the final account: completed acceptable work locked by sign-off (card_06dbf446)
  • Pricing dates at the final account: period-by-period adjustment by published prices, then aggregation (card_c7cdf5a2)
  • Deducting never-built items from the contract price: the disallowance rules (card_c73654c2)
  • Which drawings govern the final account: as-built drawings prevail (card_f06aadca)
  • As-built drawings in settlement: legal basis and quantity-checking benchmark (card_343ad45d)
  • Cross-checking design changes at the final account: a five-dimension method (card_d8968b58)
  • Final-account deliverables, archiving and the dual paper/electronic track (card_18d81f4c)
  • Works in use but not settled: quality runs under the warranty, settlement is still due (card_e66e7e23)
  • Annex D pricing statement: the four required sheets and the risk of omissions (card_bfb43f62)

Default, remedies and disputes

  • The consequence chain when the employer neither checks nor pays: deemed approval plus liability (card_feb5af9b)
  • "Fail to check in time, deemed accepted": the 28-day source and the two editions compared (card_161893ea)
  • Does silence mean acceptance? Three requirements under Fa Shi [2020] No. 25 art. 21 (card_302b266d)
  • When the employer sits on the final account: responses and the escalating remedies (card_ac7f8b5c)
  • Drafting an effective deemed-approval clause: six requirements (card_a6eced04)
  • When the employer delays payment: the contractor's four-layer remedy ladder (card_088d8cc2)
  • Interest on overdue payments: when it starts — agreement first, plus three deemed nodes
  • Challenging the final-account review: objection windows and the remedy ladder (card_631ed5aa)
  • Claiming omitted items after both parties have signed the final account: feasible or not? (card_8006c957)
  • Finality after confirmation and the boundary of reopening the price (card_82d3160e)
  • Where the price is disputed: the undisputed part is paid first (card_415eedf7)
  • Employer-side disallowances: the required basis and the burden of proof (card_757b58b1)
  • Can review or audit move the awarded all-in unit rates? (card_a589b4b5)
  • Final account review, government fiscal review and government audit: three different things (card_39267a92)
  • While the price is disputed, completed work keeps being measured and paid (card_a8dc851c)
  • The pricing administration measures through editions: Order No. 16 vs the repealed Order No. 107 (card_dd8f1895)
  • Work not in the BOQ but mandated by the code: can it be disallowed? (card_c8437496)

Retention and security

  • Withholding and returning retention money: the full process (card_ed8b875d)
  • Retention return: timing, procedure and the link to final closure (card_6734989d)
  • Performance security vs retention money: the 10%/3% caps and where they may coexist (card_63349dff)

Pricing elements entering the settlement

  • Provisional prices at the final account (card_cf1fe184)
  • Provisional sums — ownership and use, two editions compared (card_1be602eb)
  • Provisional sums at the final account: incurred work priced as executed, unused balance deducted in full (card_78a9d04c)
  • Main contractor's attendance and coordination provisions: pricing and settlement adjustment (card_a679609f)
  • Free-issue (employer-supplied) materials at the final account: the deduction basis and over-drawal liability (card_6e7488d0)
  • The full path of certified records into the final account (card_2fa30132)
  • Claim costs into the final account: line position plus the 28-day procedural chain (card_4d980139)
  • Design changes into the final account: line position and the pricing ladder (card_b5925994)
  • Can a certification stand directly as the settlement basis? (card_7d57ff00)
  • Work done but never certified: the trichotomy and the remedies (card_dfdcf754)
  • Failed acceptance: may payment still be made? (card_55753def)
  • The construction price under three measurement bases: an overview (card_7be149a6)
  • The pricing standard and the nine measurement standards: how they interlock (card_5b12d7a2)
  • Linking contract, drawings, BOQ, certifications and settlement: chain-of-evidence management (card_2a2454c5)
  • Quantities computed from design-drawn dimensions: the general rule and its exceptions (card_fb31ba87)

Funding and cash-flow links

  • Reconciling accounts receivable against settlement data: finance ledger × commercial ledger (card_2fc88418)
  • Projecting the advance-financing peak and the funds-occupancy cycle (card_2c99f9c6)
  • Compiling the construction project cash-flow forecast (funds utilization plan) (card_d444823c)
  • Late progress-payment collection: effects on the advance-financing peak and financing cost (card_a37d6d57)
  • Computing guarantee fees, security-occupation cost and financing charges (card_41e7dcc6)
  • Comparing procurement payment terms: payment present value vs cost of funds occupied (card_3907015d)
  • Four-quantity reconciliation: procurement plan — delivery — acceptance — payment (card_33a7b0ab)
  • Project procurement and supply-chain management: an overview (card_db1cadd7)

International comparison (FIDIC)

  • The FIDIC Engineer's measure-value-pay chain (12.1/12.2/12.3/14.1) (card_f0f8764a)
  • The FIDIC Performance Certificate vs the Chinese chain of completion acceptance — defects liability period — final closure (card_af602bdf)
  • The FIDIC Defects Notification Period (DNP) vs China's defects liability period: same name, different machinery (card_2bb67139)

Related term entries: interim payment; interim settlement by construction stage; final account; retention money; defects liability period; provisional sum for specified materials / nominated works; provisional sums; dayworks; deemed approval; claim (see the term-entry library).