Quantifying advance-funding pressure when contract payment proportions are too low, and standard floors (GB/T 50500-2024: 80% progress payments, 10%-30% advance payment)
Every 10-point drop in the payment proportion adds roughly 10% of the contract amount in advance funding: peak advance = (1 - payment proportion) x contract amount; average advance ~= peak/2; annual financing cost ~= average advance x annual rate. GB/T 50500-2024: progress payments should not be below 80% of cumulative completed work value (9.1.7); in-process settlement not below 80% (10.2.4); advance payment not below 10% and not above 30% of contract price (9.2.2). Advance funding stacks migrant-wage, supply-chain, and tax-prepayment chain risks; the Regulation on Payment to SMEs (30/60-day terms and overdue interest) can be invoked for relief.
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works
- 《保障中小企业款项支付条例》(国务院令第728号)
- 《保障农民工工资支付条例》
Topic Positioning
This card covers how to quantify a contractor's funding pressure when contract payment proportions are too low (e.g., 60%, 50%), the national-standard floors for progress payment proportions, and the legal instruments available. For payment-condition assessment in contract review, bid decisions, and settlement negotiations.
Core Conclusions
Standard floors (GB/T 50500-2024): absent agreement on payment proportion, progress payments should not be below 80% of cumulative completed work value (9.1.7); in-process settlement progress payments "shall not be below" 80% (10.2.4, mandatory phrasing); for labor-and-material contracts, advance payment should be no less than 10% and no more than 30% of the contract price (9.2.2). Contract terms of 60%/50% fall below the national recommended conditions and can be cited in negotiation. Advance-funding quantification (contract amount C, payment proportion p, uniform output): peak advance at completion = (1-p) x C—each 10-point drop in p adds about 10% of C in advance; average advance ~= peak/2 (linear approximation); annual financing cost ~= average advance x annual financing rate (bank working-capital loans ~5%, factoring/commercial-bill discounting ~8%). Switching monthly to quarterly payment adds roughly 2 months of output in advance; after advance-payment recovery, the peak still returns to (1-p) x C—merely shifting the pressure later. Chain risks: monthly full payment into migrant-wage special accounts is a statutory duty—owner arrears must not stop wages; supplier credit runs 2-3 months—supply cutoff erupts first; VAT obligations arise at invoicing—advancing funds also advances taxes; shortfalls inevitably transmit to subcontractors and labor crews, triggering wage suits.
Applicable Boundaries
The estimate uses a uniform-output linear approximation; with compressed schedules or front-loaded output, month-by-month discounting is more precise; financing rates per the enterprise's actual funding cost; the 80% floor is a recommended/mandatory term "when unspecified"—where the contract explicitly agrees lower, the agreement governs, but the above articles can still be cited in negotiation; Order No. 728 applies only to government agencies/public institutions/large enterprises delaying payments to SMEs.
Further Reading
See GB/T 50500-2024, Articles 9.1.7, 9.2.2, 10.2.4; Regulation on Ensuring Payment to Small and Medium Enterprises (State Council Order No. 728), Article 8 (payment within 30 days of delivery, 60 days max) and Article 15 (overdue interest at LPR or 0.05% per day); Regulation on Ensuring Wage Payment to Migrant Workers, Article 23 (no contractor advances on government-invested projects) and the monthly full-payment rule for wage accounts.
Keywords
Related Cards
- →
Four-tier progressive identification of high-risk bid-pricing clauses in tender documents (rejection clauses -> substantive requirements -> price locking -> performance funding)
Read tender documents as risk-allocation contracts: (1) rejection clauses (the seven statutory grounds of Implementation Regulations Article 51 as baseline, sector measures expand with catch-all clauses; below-cost is the hidden trap); (2) substantive requirement clauses ("must/shall/shall not" wording + deviation tables—non-response is statutory rejection); (3) price-locking clauses (GB/T 50500-2024: risk-scope clarification, three elements of price adjustment, lump-sum by total, lump-sum per item, preliminaries responsibility, unbalanced bidding); (4) performance funding clauses (Article 3.4.8 14-item checklist, performance deposit <=10%, seven quality-reserve agreements).
- →
Steel price adjustment calculation: price-information adjustment formula, per-specification per-period threshold checks with adjustment on actual basis, and tax treatment (GB/T 50500-2024 Appendix A.2)
Steel price adjustment uses the price-information adjustment method (GB/T 50500-2024 Appendix A.2): △P = Σ[(Ci − C0·(1±r)) × Q] × (1 + VAT rate), adjusting only the portion beyond the risk band on an actual basis; the agreed risk band prevails, with the beyond-5% fallback where not agreed or unclear (8.7.2). Each specification must be checked independently each period for exceeding the risk band (base prices, published price information, and increase rates differ; specifications within the risk band are not adjusted for the period); the price difference carries VAT only, no management fee or profit (3.3.5); when checking adjustment tables, first look at whether the bid price is above or below the base price (A.2.4 determines the excess-calculation base).
- →
Maximum bid price (former tender price ceiling) compilation framework and cost composition under GB/T 50500-2024
State-funded projects must set a maximum bid price (the former tender price ceiling), compiled and reviewed by the tenderer or a commissioned cost consultant, published in detail with the tender documents, and not to be raised or discounted; compilation basis: the seven items of GB/T 50500-2024, Clause 5.2.1. Cost composition: divisional and elemental work costs (pre-tax fully loaded all-in unit rate, including risk costs and auxiliary work costs) plus preliminaries (statutory safety provisions, non-competitive) plus other-item costs (provisional sums, provisional prices, dayworks, general contractor's service fee, etc.) plus taxes (VAT listed separately). Note the 2024 edition abolishes the separate line item for statutory fees, absorbing them into the all-in unit rate - different from the 2013 edition and some local documents; confirm the applicable edition before compiling.
Cited By
- ←
Statutory payment terms and late-payment liability for construction sums owed to small and medium-sized enterprises (SMEs), covering progress payments and settlement sums: 30 days, capped at 60, for government agencies and public institutions; 60 days for large enterprises; rules for when the clock starts; the overdue-interest benchmark; and the priority right to payment out of the works price (State Council Decree No. 802, Regulation on Ensuring Payment to SMEs, 2025 revision, Articles 9 to 20; Civil Code Article 807; Fa Shi [2020] No. 25, Articles 26 and 41)
Government agencies and public institutions procuring works from SMEs must pay within 30 days of delivery; a contract may provide otherwise, but the payment term must not exceed 60 days; for large enterprises the outer limit is 60 days. Where the contract adopts stage settlement, periodic settlement or the like, the payment term runs from the date both parties confirm the settled amount (State Council Decree No. 802, Article 9). Late payment carries overdue interest: any agreed rate must be no lower than the 1-year loan prime rate at the time of contract conclusion; absent agreement, interest accrues at a daily rate of 0.05% (Article 17). The contractor may further claim the priority right to payment out of the construction price under Civil Code Article 807; that right must be exercised within 18 months at most, counted from the date on which the employer became obliged to pay the construction price (Fa Shi [2020] No. 25, Article 41).
- ←
Two-stage comparison of requirement elements between interim settlement by construction stage and the final account (GB/T 50500-2024): timing, definition of completed works, payment percentage, price calculation, dispute handling and node division
Interim settlement by construction stage is the calculation, adjustment, confirmation and payment of the contract price for completed works at settlement nodes (term 2.0.34, also termed interim settlement, with nodes divided by month / quarter / year / physical progress); the final account is the consolidated settlement of the total price of the works after completion acceptance has passed and is the summary of the interim settlements by construction stage (2.0.35). Signed stage settlement documents form part of the final account documents and the final account does not re-measure or re-price them (10.2.3); only preliminaries and the main contractor's attendance and coordination provisions are interim payments that must be recalculated at final account stage (10.2.7, 10.3.3). The stage settlement payment percentage is no less than 80% of the total settlement amount for the current period (10.2.4); the final account has no percentage concept - it is closed out on the total price less retained retention money (cumulatively no more than 3% of the total settlement price of the works, 10.5.1), per formula 7 of clause 10.3.15.
- ←
Checklist of payment compliance obligations under the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Decree No. 802): 30-day and 60-day-maximum payment terms for state organs and public institutions and 60-day terms for large enterprises, and the starting points of those terms; prohibition of third-party payment conditions; delayed acceptance treated as expiry of the term; prohibition of compulsory commercial bills of exchange; no compelling use of audit conclusions as the settlement basis; security limited to four types and not restricted to cash; overdue interest at 0.05% per day; payment of undisputed portions first; and information disclosure requirements
State organs and public institutions must pay within 30 days of delivery of the goods, works or services, and where the contract provides otherwise, the term may never exceed 60 days; large enterprises must pay within 60 days and may not agree that receipt of payment from a third party is a condition of payment, nor pay SMEs in proportion to the progress of a third party's payment (Article 9). The payment term runs from the date of passing inspection or acceptance, or from the date the parties confirm the settlement amount under progress-based or periodic settlement; where a state organ, public institution or large enterprise delays inspection or acceptance, the term runs from the expiry of the agreed inspection or acceptance period (Article 10). The agreed overdue interest rate may not be lower than the 1-year LPR at the time of conclusion of the contract; failing agreement, interest accrues at 0.05% per day (Article 17). In project construction only four types of security may be collected - tender security, performance security, works quality retention money and migrant worker wage security - and they may not be restricted to cash; guarantee letters from financial institutions must be accepted (Article 13); state organs, public institutions and state-owned large enterprises must not compel the use of the audit authority's audit conclusion as the basis for settlement (Article 12).
- ←
Payment time limits under the 2025 revision of the Regulation on Ensuring Payment to Small and Medium-sized Enterprises: 30 days (60 days at most) for state organs and public institutions, 60 days for large enterprises, when the period starts (acceptance and settlement), the ban on back-to-back clauses, the four permitted securities, and interest on overdue payment (1-year LPR floor / 0.05% per day)
Under the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Decree No. 802): where state organs and public institutions procure works and the like from small and medium-sized enterprises, payment must be made within 30 days from delivery, and any contractual agreement may not extend the limit beyond 60 days; large enterprises must pay within 60 days and may agree periods reasonably per industry norms, but may not make payment conditional on receipt of third-party payment; where payment is by progress or periodic settlement, the payment period runs from the date the parties confirm the settled amount, and where acceptance is a payment condition, from the date of passing acceptance - or, where acceptance is delayed, from the expiry of the agreed acceptance period. Late payment attracts interest on overdue payment: an agreed rate may not be lower than the 1-year LPR at the time of contracting; absent agreement, 0.05% per day.
- ←
Reconciling the three output-value bases of construction output, measured output and settlement output: item-by-item basis distinction, four classes of difference attribution, the disallowance-and-resubmission tests, and the tie-out with stage settlement documents
Construction output value (physical-progress statistics basis), measured output value (contract basis of qualified quantities certified by the supervising engineer or employer) and settlement output value (contract entitlement basis) are three non-overlapping measurement boundaries; the aim of reconciliation is not to make the three figures equal, but - anchored on the measured output value - to place every difference item by item into the accounts of (1) not yet submitted, (2) measurement period not yet reached, (3) quality not yet confirmed, (4) variations not yet priced held in suspense (plus basis differences and permanent removals), until the residual is zero. Disallowance or resubmission must simultaneously pass the measurement-conditions tests (within the BOQ, an approved variation or dayworks scope; quality qualified with acceptance complete; per the contract calculation rules; within the measurement period; the variation priced or on a provisional price; the Notice of Claim issued within 28 days). Payment of interim settlement by construction stage shall be no less than 80% of the current stage settlement total (GB/T 50500-2024 clause 10.2.4), and stage settlement documents signed and confirmed merge into the final account without re-measurement or re-pricing (clause 10.2.3).
- ←
Node division modes, payment percentage floors and post-confirmation re-review rules for interim settlement by construction stage: GB/T 50500-2024 Clauses 10.1.3/10.2.3/10.2.4/10.3.15/10.5.1, Cai Jian [2022] No. 183 and local implementation documents
Nodes, procedures and methods are governed by the contract (GB/T 50500-2024 Clause 10.1.3), and the forms may be monthly/quarterly/annual/physical-progress nodes (Clause 2.0.35); policy and local documents refine this into three modes: fixed cycle, physical-progress nodes, and sub-section/segment/specialism. The payment percentage of interim settlement shall not be lower than 80% of the total interim settlement amount for the current period (Clause 10.2.4). The payable final account amount = final account total price - retention money withheld - cumulative amounts actually paid beforehand (Clause 10.3.15); the cumulative retention money, or the bond amount where a bond substitutes for it, must not exceed 3% of the total settlement price of the works (Clause 10.5.1), so where 3% is retained a single payment reaches 97% of the settlement total price and the cumulative payment reaches 100% on expiry of the defects liability period. Interim settlement documents signed and confirmed by both parties form part of the final account documents, and the final account shall not re-measure or re-price them (Clause 10.2.3); Cai Jian [2022] No. 183 words this as 'in principle not reviewed again after completion', and the documents of Xinjiang, Zhejiang and other places read 'not reviewed again' or 'in principle not reviewed again'.
- ←
Preventing over-settlement and duplicate settlement of subcontracted quantities: dual-signature locking of measurement + interim settlement by construction stage merged into the final account + the list of items not measured
Preventing over-settlement/duplicate settlement relies on procedural control rather than account-checking error correction: measurement results, once signed and confirmed by both parties, are locked as the basis for settlement (GB/T 50500-2024 Clauses 7.1.7/7.1.8); signed interim settlement by construction stage documents are merged into the final account and are not re-measured or re-priced (Clause 10.2.3); after dual signing of the final account no repeated checking is allowed (Clause 10.3.12); quantities with unapproved commencement reports, failed acceptance, beyond the construction drawings, unlawful subcontracting or contract transfer (re-letting of the whole works), rework, etc. are not measured at all (TB 10402-2019 Clause 6.0.6 and others).
- ←
Calculating and judging the project financial internal rate of return (FIRR), financial net present value (FNPV), and payback period
FIRR is the discount rate at which the cumulative present value of net cash flows over the project calculation period equals zero; FIRR ≥ the benchmark rate means the project is viable; FNPV discounts each period's net cash flow at the benchmark rate and sums them — >0 is viable and larger is better; for hand calculation of IRR use trial-and-error linear interpolation (interval preferably ≤2%); the payback period comes in static and dynamic forms — the shorter it is, the stronger the risk resistance. Measurement of the return on contractor advance financing (deferred payment) must distinguish the all-investment basis from the equity/own-funds basis.
- ←
Diagnosing "profitable but cash-strapped" construction projects: a five-step indicator system for the divergence between accrual-basis profit and cash-basis cash flow
Put accrual-basis book profit side by side with cash-basis operating net cash flow: cumulative negative operating net cash flow + cash content ratio (operating net cash flow ÷ net profit) <0 + collection rate <80% confirms "profit without cash"; a collection rate ≥90% with negative cash is mostly stage occupation by retention money and the like — not a disease. The root cause is revenue recognized by completion progress while collection lags, compounded by construction-specific cash black holes: progress payment lag, advance-funded construction, and deposit occupation.
- ←
The contractor's four-level remedy ladder when the owner delays payment (demand -> suspension and claims -> administrative complaint -> termination/priority of payment)
Four escalating levels — "gentle demand -> pressure by suspension -> administrative complaint -> legal remedies": (1) written demand (GB/T 50500-2024 §10.2.12/§10.3.17) + undisputed portion first (§9.4.11) + overdue interest (Decree No. 728, Article 15: agreed rate no less than the 1-year LPR, 0.05% per day absent agreement); (2) statutory suspension rights (prepayment §9.2.4, safety measure fees §9.3.3) + 28-day dual-node claims (§9.4.12); (3) complaint to the SME authority (Decree No. 728, Article 17, with credit blacklisting); (4) termination + priority of payment for the project price (Civil Code Articles 563/807, 18-month exclusion period).
- ←
Contractor cash-flow risk control when progress-payment review runs overdue: deemed approval of measurements, payment of undisputed portions, and four-layer defense (GB/T 50500-2024)
Review deadlines are not bottomless: absent contractual deadlines, GB/T 50500-2024 Article 7.1.5 establishes "overdue silence = measurement accepted," Article 9.4.11 "undisputed portions paid first," and Article 9.1.7 payment no less than 80% of cumulative completed work value; overdue non-payment supports claims under 9.4.12, and in extreme cases priority-of-payment under Civil Code Article 807 (exercisable within 18 months) and the Regulation on Payment to SMEs. Defense deploys across four layers: contract clauses - process management - legal remedies - self-rescue financing.
- ←
Measuring the advance-funding peak and capital occupation period of construction projects (monthly cumulative cash flow method + weighted occupation period formula + simplified estimation)
Advance-funding peak (exact method) = the absolute value of the lowest point of the cumulative monthly net cash flow, identical to the maximum funding gap in the rolling forecast; simplified estimation ≈ (1 − progress payment ratio) × contract amount − advance payment coverage — every 10-point drop in the payment ratio adds about 10% of the contract amount of advance funding; average advance funding ≈ peak/2. Weighted occupation period = Σ(month-end occupation × month ordinal)/Σ(month-end occupation), reflecting the average months each yuan is tied up; annual turnovers = annual collections/average occupation — the lower, the heavier. Check against the GB/T 50500-2024 floors (progress payments ≥80%, in-process settlement payments ≥80%, advance payment 10%–30%) to see whether the contract shifts advance funding onto the contractor.
- ←
Determining the progress-payment ratio and the payment sign-off procedure (GB/T 50500-2024 §9.1/§9.4 + GB/T 50319-2013 §5.3.1)
The ratio is set by three layers — "contract agreement first -> national-standard floor -> local mandates": absent agreement, no less than 80% of cumulative completed value (9.1.7); current payable = cumulative completed price - cumulative paid - current deductions (9.1.6, 9.4.9); the work-safety measure advance is not recovered from progress payments (9.3.2); the procedure runs contractor applies -> specialty supervision rechecks -> chief supervision engineer endorses -> employer approves -> chief supervision engineer issues the certificate (GB/T 50319-2013 §5.3.1); the retention base excludes advances and price-adjustment amounts.
- ←
Comparing procurement payment terms: when unit prices are equal, rank options by payment present value and capital occupation cost
When material unit prices are equal and only payment terms differ, discount each option's payment schedule at the enterprise's internal monthly capital occupation rate: payment present value = Σ(payment amount ÷ (1 + monthly rate)^months); for quick estimates, capital occupation cost ≈ amount × occupied days ÷ 360 × annualized capital cost rate — the lower present value/occupation cost wins: the longer the credit and the smaller the prepayment, the better; the choice must add four corrections: the capital cost rate value, current cash flow, the hidden risks of overly long credit, and the input tax deduction timing.
- ←
Full process of construction payment: advance payment, safety-measures fee, progress payment, interim settlement by construction stage, final account, retention money and final settlement (GB/T 50500-2024 Chapters 9-10)
Payment along the timeline in six segments: advance payment (for works with contractor-procured materials, neither below 10% nor above 30% of the contract price after deducting provisional sums etc., prepaid before commencement, recovered as agreed) → statutory safety provisions (at least 50% prepaid within 28 days after commencement; not deducted from progress payments, recovered once at the final account) → progress payments (amount due = cumulative completed − cumulative paid − deductions; not less than 80% of the cumulative completed value where the contract is silent) → interim settlement by construction stage (new in 2024: signed stage settlements enter the final account without re-pricing; stage payments not below 80%) → final account (thirteen heads; failure to check or to certify in time is deemed acceptance) → retention money (3% cap) and final closure (defects liability period generally 1 year, 2 at most). The chain runs on contract-agreed time limits with a 28-day backstop; judicial enforcement of "accepted at the submitted price" requires an express contractual provision.
- ←
Dual-basis attribution of project capital costs into business analysis (period expenses in financial accounting vs explicit disclosure in management analysis)
Project capital costs are handled on a dual basis: externally, the financial statements follow Article 49 of the Accounting Standards for Business Enterprises — finance costs are period expenses charged directly to current profit or loss, not into project production costs; internally, business analysis must attribute capital costs explicitly by project (one-off financing fees + capital occupation fees + deposit occupation + overdue interest received/paid), listing a separate "capital cost" line on the project income statement (after gross profit, before taxes). Attribution formula: project capital cost = Σ(month-end occupation × internal monthly occupation rate) + one-off financing fees − overdue interest recovered; month-end occupation = max(0, −cumulative net cash flow); the internal rate is set uniformly by the company's financial system; keep the three synchronizations of physical progress, output value statistics, and cost collection.
- ←
GB/T 50500-2024: both progress payments and process-settlement payments floored at 80% — the wording contrast between 9.1.7 "should not be lower" and 10.2.4 "shall not be lower"
Under GB/T 50500-2024, the payment-ratio floors for progress payments and construction-process settlement payments are both 80%, with different force: Clause 9.1.7 on progress payments — "where the contract does not state a payment ratio for the works value, the ratio should not be lower than 80% of the cumulative completed works value" — "should" is recommendatory: agreement prevails, the 80% floor applies only absent agreement; Clause 10.2.4 on process-settlement payments — "the payment ratio shall be agreed in the contract and shall not be lower than 80% of the current process-settlement total" — "shall not" is a prohibitive hard floor: even an agreed ratio below 80% fails the standard. The bases differ: progress payments on "cumulative completed works value", process-settlement payments on "current process-settlement total".
- ←
The employer's time requirement for reviewing progress payments (GB/T 50500-2024 §9.1/§9.4): the reasonable-time fallback, the certificate-confirmation procedure, and common deadline conventions
GB/T 50500-2024 sets no fixed review days: Clause 9.4.11 requires the employer to check within a "reasonable time" after receiving the progress-payment application and issue the payment certificate, with disputed items paid first on undisputed parts; Clauses 9.1.10/9.1.11 form the procedural chain "draft certificate first to the contractor for confirmation + contract-agreed latest payment date". Specific deadlines rest on the contract — the model text GF-2017-0201 general-conditions convention: supervision 7 days + employer 7 days (late deemed acceptance); government and public-institution employers are further bound by the "Regulations on Payment to Small and Medium Enterprises" (State Council Order No. 802) 30/60-day payment limits.
- ←
Calculation of progress payments (GB/T 50500-2024 §9.1/§9.4): the cumulative-difference method, the 11-item composition of cumulative completed value, and payment/deduction rules
Current payable progress payment = cumulative completed value to date − cumulative paid price − current deductions (GB/T 50500-2024 Clauses 9.1.6, 9.4.9); absent an agreed ratio, payment should be no less than 80% of cumulative completed value (9.1.7); the cumulative value comprises 11 items — contract BOQ price, BOQ errors/omissions adjustments, provisional sums, adjustments of provisional prices after procurement, main contractor's attendance and coordination provisions, dayworks, changes in costs, regulation/policy changes, variations, additional works, claims; the statutory safety provisions advance may not be recovered from progress payments (9.1.7, 9.3.2), advances recovered per the agreement (9.2.6); disputed items certified and paid first on undisputed parts (9.4.11); payment applications must list construction workers' wages separately (9.4.9).
- ←
Full workflow of agreeing and paying construction advance payments (GB/T 50500-2024 Section 9.2): nature, proportion, procedure, guarantee, and recovery
The construction advance payment (materials advance) is paid by the Employer before commencement for the Contractor's materials preparation - earmarked and interest-free. For labour-and-material contracts, the payment proportion should not be less than 10% of the signed contract price (net of provisional sums, dayworks and provisional sums for nominated specialist subcontract works) and should not exceed 30% of the signed contract price (for major multi-year projects, prepaid annually at the same proportion in accordance with the annual plan). The Contractor applies -> the Employer reviews and pays (an equal-value guarantee may be agreed); recovery is made as agreed in the contract, or, if not agreed, in one or more instalments; on termination of the contract, any unrecovered portion is recovered in full.
- ←
Measuring the impact of progress payment collection delays on the advance-funding peak and financing costs (three-tier interest rate bases + claim grounds)
Each month of collection delay adds roughly one month of net cash outflow to the advance-funding peak (example ≈7.5% of the contract amount per month), and financing costs rise roughly linearly; at an 8% annualized basis, extending the lag from 1 to 3 months adds ≈1.4% of the contract amount in cumulative cost. Overdue interest has three rate bases: the 1-year LPR (≈3%) / the enterprise's actual financing (≈8%) / 0.05‰ per day under the Regulation on Ensuring Payment to SMEs (18.25% annualized, ≈6× LPR) — both a ceiling for rights enforcement and a negotiation lever, supported by claims under GB/T 50500-2024 Clause 9.4.12 and the work suspension cost standards.
- ←
Core differences between railway work-acceptance valuation and building progress payments: positioning, pricing basis, procedure, non-valuable list, and payment rules
Railway work-acceptance valuation is an investment-control tool (approved-estimate cap + supervisor review sign-off + investment completion reported level by level + five-item negative list of non-acceptable items + deduction of employer-supplied materials); building progress payment is a contract-price payment tool (the contract BOQ is the sole pricing basis; absent agreement, payment should not be below 80% of the cumulative completed value; undisputed portions paid first). Similar in function but entirely different in institutional foundation.
- ←
Old-vs-new rules on the advance payment ratio: GB/T 50500-2024 Clauses 9.2.2/9.2.3 vs GB 50500-2013 Clause 10.1.2 — the 10%–30% band and changed deduction bases
The 10%–30% payment band is retained in GB/T 50500-2024 but the deduction bases changed: the lower-bound base now deducts the provisional sum for nominated specialist subcontract works in addition to provisional sums; the upper-bound base is now 30% of the signed contract price with no deductions; the basis for computing the advance expressly deducts three items (provisional sums, dayworks amounts and the provisional sum for nominated specialist subcontract works); the lower-bound wording softens from "shall not be below" to "should preferably not be below" (the standard as a whole becoming a recommended national standard). Advances for major multi-year works are paid annually against the annual programme, with each year preferably not below 10% and not above 30% of that year's planned contract price for completion (excluding provisional sums and the provisional sum for nominated specialist subcontract works) (9.2.3).
- ←
Preparing the construction project cash flow forecast (funds utilization plan): dual bases of contract × project execution plan, dual revenue/expenditure lines, dual-basis closure
Preparing the cash flow forecast = translating the contract payment terms and the project execution plan's resource inputs into a monthly receipts-and-payments schedule: the revenue line (advance payment and its recovery, progress payments, final account payments, retention money recovery) and the expenditure line (labor/materials/machinery, subcontracting, site management fees, statutory levies and fees, taxes and duties, deposits and guarantees) are netted month by month; the lowest cumulative point is the maximum funding gap. The basis of preparation must match the construction contract, the approved project execution plan, and the planned schedule; the totals decomposed by cost item and by contract must close; the monthly rolling replaces forecasts with actuals.