The "double 80%" rule for progress-payment and in-process settlement payment ratios: GB/T 50500-2024 Clauses 9.1.7 and 10.2.4 vs GB 50500-2013 Clause 10.3.7 (60%-90%)
GB/T 50500-2024 raises the payment floor from 2013's 60% to 80% and remo…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第9.1.7、9.2.2、9.2.6、9.3.2、9.4.1、9.4.9、9.4.11、10.2.4条GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第10.3.7条(已被GB/T 50500-2024替代,仅作历史对照)GB/T 50319-2013 · Code for Construction Project Supervision 第5.3.1条2026-10-18 - 02
Measuring the advance-funding peak and capital occupation period of construction projects (monthly cumulative cash flow method + weighted occupation period formula + simplified estimation)
Advance-funding peak (exact method) = the absolute value of the lowest p…
GB/T 50500-2024 第9.1.7、9.2.2、10.2.4条GB/T 51095-2015 第7.2.1条DBJ/T 15-153-2019 第5.11.2条2026-09-25 - 03
GB/T 50500-2024: both progress payments and process-settlement payments floored at 80% — the wording contrast between 9.1.7 "should not be lower" and 10.2.4 "shall not be lower"
Under GB/T 50500-2024, the payment-ratio floors for progress payments an…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第9.1.7条、第10.2.4条(配套第9.2.6、9.3.2、10.1.3、10.2.3条)https://jst.zj.gov.cn/col/col1229129246/art/2023/art_8109b9598e49aa7ca1002670dc7c6011.htmlhttps://jst.zj.gov.cn/col/col1229129246/art/2020/art_e5ceb71e605d20f609ffb50549b2e3a7.html2026-09-25 - 04
Quantifying advance-funding pressure when contract payment proportions are too low, and standard floors (GB/T 50500-2024: 80% progress payments, 10%-30% advance payment)
Every 10-point drop in the payment proportion adds roughly 10% of the co…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works《保障中小企业款项支付条例》(国务院令第728号)《保障农民工工资支付条例》2026-09-25