The "double 80%" rule for progress-payment and in-process settlement payment ratios: GB/T 50500-2024 Clauses 9.1.7 and 10.2.4 vs GB 50500-2013 Clause 10.3.7 (60%-90%)

GB/T 50500-2024 raises the payment floor from 2013's 60% to 80% and removes the 90% cap, forming "double 80%": progress payments (9.1.7) - where the contract is silent, preferably not below 80% of the cumulative completed work value; in-process settlement payments (10.2.4, new in 2024) - not below 80% of the current in-process settlement amount. The two 80s differ in force: the progress-payment one is a fallback when the contract is silent ("preferably not below"); the in-process one is a floor that contractual agreement cannot breach ("shall not be below").

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第9.1.7、9.2.2、9.2.6、9.3.2、9.4.1、9.4.9、9.4.11、10.2.4条
  • GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第10.3.7条(已被GB/T 50500-2024替代,仅作历史对照)
  • GB/T 50319-2013 · Code for Construction Project Supervision 第5.3.1条
  • 最高人民法院〔2008〕民一他字第4号《关于人民法院在审理建设工程施工合同纠纷案件中如何认定财政评审中心出具的审核结论问题的答复》
  • 《保障中小企业款项支付条例》(国务院令第728号)第十一条
  • https://www.gov.cn/
  • https://www.mohurd.gov.cn/

Topic Positioning

GB/T 50500-2024's adjustments to progress-payment and in-process settlement payment ratios: the "double 80%" rule, contrasted with the repealed GB 50500-2013 (not below 60%, not above 90%), why in-process settlement has its own ratio, and the differing force of the two 80s.

Core Conclusions

I. Progress-payment ratio, two editions:

  • GB 50500-2013 (repealed) 10.3.7: not below 60% and not above 90% of the interim settlement total - a banded rule.
  • GB/T 50500-2024 (current) 9.1.7: where the contract does not set a ratio, preferably not below 80% of the cumulative completed work value, with no cap. Original: "Payment of completed work value and recovery of advance payments shall follow the contract. Where the contract is silent on the ratio, it should preferably not be below 80% of the cumulative completed work value; advance recovery per 9.2.6; safety-measures advance per 9.3.2. Progress payments are computed from cumulative amounts of the current and previous periods; the safety-measures advance shall not be recovered from progress payments."

II. In-process settlement payments (new institution in 2024):

  • 10.2.4 original: "The payment ratio of in-process settlement shall be agreed in the contract and shall not be below 80% of the current in-process settlement total." 2013 had no in-process settlement - this is a new requirement with the same 80% floor as progress payments.

III. Differing force:

  • Progress 80% (9.1.7) uses "preferably not below" - a fallback when the contract is silent; agreed ratios govern.
  • In-process 80% (10.2.4) uses "shall not be below" - a floor contractual agreement cannot breach; once in-process settlement is adopted, even an agreed ratio cannot fall below 80% - stronger.

IV. Other points:

  • Base change: 2013 used the "interim settlement total"; 2024 uses "cumulative completed work value" (per 9.1.6, covering contract list amounts, defect adjustments, provisional sums, prime-sum adjustments, main-contract service fees, dayworks, price changes, legal changes, variations, new works, claims, etc.).
  • Legislative intent: floor 60% -> 80%, cap removed - squeezing the room for advance financing and arrears; both 80s are floors, and higher agreed ratios are fully compliant.
  • Force note: 2024 is a recommended GB/T, weaker than the 2013 mandatory GB; practically it binds through contractual incorporation.

Applicable Boundaries

  • Field: BOQ pricing within GB/T 50500-2024's scope; highways, railways, etc. have their own standards with possibly different ratios.
  • The progress 80% is a fallback: only when the contract is silent; agreed ratios govern otherwise.
  • The in-process 80% is a floor: applies only to works adopting in-process settlement; once adopted, agreed ratios cannot go below 80% of the current settlement total.
  • 2024 is recommended (GB/T); 2013 was mandatory but is repealed; binding force depends on contractual incorporation.

Further Reading

  • 9.1.7 (original above); base composition in 9.1.6; advance recovery in 9.2.6; safety-measures advance in 9.3.2; application and issuance procedure in Section 9.4.
  • In-process settlement: 10.2.4; merging into final accounts without re-measurement in 10.2.3; final-account verification in Section 10.3.
  • Old comparison: GB 50500-2013 10.3.7 (repealed).
  • Extensions: cumulative-difference progress calculation, the three-tier ratio rule (contract -> national fallback -> local mandate), advances and recovery, financing-pressure estimation - see related cards.