Node division modes, payment percentage floors and post-confirmation re-review rules for interim settlement by construction stage: GB/T 50500-2024 Clauses 10.1.3/10.2.3/10.2.4/10.3.15/10.5.1, Cai Jian [2022] No. 183 and local implementation documents
Nodes, procedures and methods are governed by the contract (GB/T 50500-2024 Clause 10.1.3), and the forms may be monthly/quarterly/annual/physical-progress nodes (Clause 2.0.35); policy and local documents refine this into three modes: fixed cycle, physical-progress nodes, and sub-section/segment/specialism. The payment percentage of interim settlement shall not be lower than 80% of the total interim settlement amount for the current period (Clause 10.2.4). The payable final account amount = final account total price - retention money withheld - cumulative amounts actually paid beforehand (Clause 10.3.15); the cumulative retention money, or the bond amount where a bond substitutes for it, must not exceed 3% of the total settlement price of the works (Clause 10.5.1), so where 3% is retained a single payment reaches 97% of the settlement total price and the cumulative payment reaches 100% on expiry of the defects liability period. Interim settlement documents signed and confirmed by both parties form part of the final account documents, and the final account shall not re-measure or re-price them (Clause 10.2.3); Cai Jian [2022] No. 183 words this as 'in principle not reviewed again after completion', and the documents of Xinjiang, Zhejiang and other places read 'not reviewed again' or 'in principle not reviewed again'.
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.35条、第9.1.7条、第9.4.1条、第10.1.3条、第10.2.3条、第10.2.4条、第10.3.15条、第10.5.1条
- 财政部、住房城乡建设部《关于完善建设工程价款结算有关办法的通知》(财建〔2022〕183号)第二条,https://www.gov.cn/zhengce/zhengceku/2022-06/30/content_5698595.htm
- 新疆维吾尔自治区住房和城乡建设厅等《关于在房屋建筑和市政基础设施工程中开展施工过程结算试点工作的通知》(2022年3月24日)第四条,https://zjt.xinjiang.gov.cn/xjzjt/c113238/202205/917d2c70463647c6a159e0e4c12575a5.shtml
- 浙江省住房和城乡建设厅等《关于房屋建筑和市政基础设施建设工程中推行施工过程结算的实施意见》第六条,https://jst.zj.gov.cn/col/col1229129246/art/2020/art_e5ceb71e605d20f609ffb50549b2e3a7.html
Topic positioning
Answers three consecutive practical questions: how the nodes of interim settlement by construction stage are divided (on what documents and in which modes); what payment percentages apply to interim settlement and to the final account; and whether interim settlement documents confirmed by both parties can still be re-reviewed at the final account stage.
Core conclusions
I. Node division: contract agreement comes first, with four node forms
GB/T 50500-2024, the China national pricing standard for BOQ, Clause 10.1.3: 'Where the contract provides for interim settlement by construction stage, the employer and the contractor shall carry out the measurement and payment of the relevant interim settlements in accordance with the nodes, procedures and methods agreed in the contract.'
Clause 2.0.35 of the terms defines works settlement as 'comprising interim settlement by construction stage, settlement upon termination of the contract, the final account and the closure of accounts after the defects period', and states that 'interim settlement by construction stage, also called interim settlement, includes settlements made by month, quarter, year and physical-progress nodes'; 'the final account refers to the total-price settlement of the works made by the employer and the contractor in accordance with the contract after the works pass taking-over, and is the summary of the interim settlements by construction stage'; the final account is built up level by level from the final accounts of unit works, individual works and the construction project.
The supporting Clause 9.4.1: 'The employer and the contractor shall, at the times or physical-progress nodes of the works agreed in the contract and following the agreed procedures and methods, measure and pay for the completed works in each measurement period, and the measurement period shall coincide with the payment period. Where the progress payment measurement period is not clearly agreed in the contract, measurement and payment may be made in monthly instalments.'
The national policy position (Article 2 of the Notice on Improving the Measures for the Settlement of Construction Project Payments, Cai Jian [2022] No. 183, of the Ministry of Finance and the Ministry of Housing and Urban-Rural Development): 'Newly commenced projects started in the year that cannot be completed in the year may adopt interim settlement by construction stage. Through agreement in the contract, the employer and the contractor divide the construction process into construction cycles by time or progress nodes, and calculate, confirm and pay the price of the works completed and free of dispute within each cycle (including variations, site instruction records, claims and the like); the payment amount must not exceed the approved estimate (budget) corresponding to the completed portion. Interim settlement documents confirmed by both parties form part of the final account documents and will in principle not be reviewed again after completion.'
Three engineered division modes:
- By fixed cycle - the measurement period coincides with the payment period; where the contract is not clear, measurement and payment are made in monthly instalments (Clause 9.4.1); some provincial implementation documents add a floor on settlement frequency.
- By physical-progress nodes - Article 6 of the Implementation Opinions on Promoting Interim Settlement by Construction Stage in Building and Municipal Infrastructure Construction Projects of Zhejiang Province (issued by the Provincial Department of Housing and Urban-Rural Development, the Development and Reform Commission and the Department of Finance; issued 15 May 2020, effective 20 June 2020): 'the settlement cycle may be divided by physical progress nodes of the works, so as to link up with the progress payment nodes'; building works may be divided into piling works, basement works, superstructure works and decoration and fit-out works, and municipal works may be divided reasonably by section, by individual work or by specialism.
- By sub-section, segment or specialism - Article 4 of the Notice on Pilot Work of Interim Settlement by Construction Stage in Building and Municipal Infrastructure Projects of Xinjiang Uygur Autonomous Region (Departments of Housing and Urban-Rural Development and others, 24 March 2022): 'The interim settlement cycle may be divided by physical progress nodes of the works, so as to link up with the progress payment nodes. For building works, interim settlement nodes may be divided by time nodes or progress nodes, by sub-section, segment or specialism according to the size of the project; for municipal infrastructure works, interim settlement nodes may be reasonably divided by section, by individual work or by specialism.'
The three modes are not mutually exclusive: contracts usually agree on a combination of 'physical-progress nodes + monthly measurement'; what matters is that they link up with the progress payment nodes and that the quantities of a completed node are confirmable and free of dispute.
II. Payment percentages: 80% floor for interim settlement -> 97% at the final account -> 100% on expiry of the defects liability period
- Interim settlement (Clause 10.2.4): 'The payment percentage of interim settlement amounts shall be agreed in the contract and shall not be lower than 80% of the total interim settlement amount for the current period.' The 80% is a hard floor with no upper limit, and the base is the total interim settlement amount for the current period, not a cumulative amount.
- Progress payment (Clause 9.1.7): 'The amount payable against the value of works completed and the recovery of advance payments shall be determined as agreed in the contract. Where the contract does not agree the percentage of the works value to be paid, the payment percentage should not be lower than 80% of the cumulative value of works completed; the recovery of advance payments shall comply with Clause 9.2.6 of this standard, and the advance payment of statutory safety provisions shall comply with Clause 9.3.2 of this standard'; 'the progress payment is calculated from the cumulative works price of the current period and that of the previous period, and the advance payment of statutory safety provisions shall not be recovered from progress payments.'
- Final account (Clause 10.3.15): after the price is confirmed the contractor submits a payment application stating '1 the total final account price of the completed works; 2 the amount already actually paid; 3 the retention money to be withheld (except where another method of works quality guarantee has been provided); 4 the amount of final account payment actually payable', together with the formula: 'payable final account amount = final account total price - retention money withheld - cumulative amounts actually paid beforehand', in which 'the retention money withheld - where the works adopt another method of works quality guarantee, the retention money in the formula shall not be calculated'.
- Cap on retention (Clause 10.5.1): 'The employer shall withhold retention money by the method of quality guarantee agreed in the contract; the cumulative retention money withheld, or the bond amount where a guarantee bond replaces the retention money, must not exceed 3% of the total settlement price of the works. Where the contractor has already provided performance security, the employer shall not withhold works quality retention money before completion of the project. Where a works quality guarantee bond, works quality insurance or another guarantee method is adopted, the employer may not withhold retention money again.'
- Percentage comparison: interim settlement no less than 80% (current period) -> at the final account, where retention is withheld at the 3% cap, a single payment may reach 97% of the settlement total price (where no retention is withheld, or a bond or insurance substitutes, nothing is deducted and payment may reach 100%) -> on expiry of the defects liability period, after deducting the costs of defect rectification to be borne by the contractor, the accounts are closed with the cumulative payment reaching 100% of the settlement total price.
III. Whether confirmed settlements can be re-reviewed: locked at the national level, reinforced by local documents
- National standard position (Clause 10.2.3): 'Except as provided in Clause 10.2.7 of this standard, interim settlement documents signed and confirmed by the employer and the contractor shall form part of the final account documents of the works, and the final account shall not re-measure or re-price them. The preliminaries and the main contractor's attendance and coordination provisions specified in Clause 10.2.7 of this standard may be adjusted in accordance with Clause 10.3.3 of this standard'; the accompanying explanation points out that the preliminaries and the main contractor's attendance and coordination provisions within interim settlement amounts are provisional payments of the works price, may for convenience be calculated pro rata, and shall at the final account be re-measured accurately and determined as agreed in the contract. That is: quantities and prices in signed interim settlements are locked and not recalculated, and the only opening is the preliminaries and the main contractor's attendance and coordination provisions.
- National policy position: Article 2 of Cai Jian [2022] No. 183 - 'Interim settlement documents confirmed by both parties form part of the final account documents and will in principle not be reviewed again after completion.'
- Local documents (wording varies in strength; when preparing settlement notes quote the original text and cite the document number): Xinjiang, Notice on Pilot Work of Interim Settlement by Construction Stage in Building and Municipal Infrastructure Projects, Article 4, reads 'will not be reviewed again'; Zhejiang, Implementation Opinions on Promoting Interim Settlement by Construction Stage in Building and Municipal Infrastructure Construction Projects, Article 6, reads 'will in principle not be reviewed again'; some municipal documents are more direct and state that interim settlement is 'final at first review' (e.g. the relevant documents of Jinhua City).
- Practical meaning: 'no repeated review' targets the quantities and prices within the signed nodes; it does not give up remedies for the unsettled parts, for the re-calculation of the preliminaries and the main contractor's attendance and coordination provisions, or for errors in the signed documents themselves (calculation errors, insufficient basis); where a signed document is found to be genuinely wrong, it shall be handled through the checking/review and dispute resolution procedures agreed in the contract, not by simply re-measuring and re-pricing it in the final account.
Applicable boundaries
- The above node and procedure clauses apply only where the contract provides for interim settlement by construction stage (Clause 10.1.3); works without such provision still follow the path of interim progress payment + one-off settlement at the final account.
- The 80% is a payment floor, not the full amount payable: the preliminaries and the main contractor's attendance and coordination proportions paid within interim settlements are provisional, and at the final account they must be re-measured accurately and determined (Clauses 10.2.3, 10.2.7 and 10.3.3).
- The arithmetic premise of 'paying up to 97% of the settlement total price' is retention withheld at 3% of the settlement total price; where performance security has been provided, retention may not be withheld before completion, and where a works quality guarantee bond, works quality insurance or another substitute is adopted, no retention is withheld, in which case the final account does not deduct this amount.
- Local documents are valid only within their own administrative region and for the works within their stated scope (most are limited to state-invested or newly commenced projects), have validity periods and are amended; verify the current effective version and document number before citing them. The strength of 'no repeated review' wording differs between provinces and cities and must not be applied across regions.
- The payment percentage clauses govern the payment of the contract price and do not change the evidentiary requirements for the measurement of the works and for variation and site instruction records.
Further reading
- GB/T 50500-2024, China national pricing standard for BOQ: Chapter 2 terms 2.0.34 and 2.0.35; Chapter 9 Clauses 9.1.7, 9.2.6, 9.3.2 and 9.4.1; Chapter 10 Clauses 10.1.3, 10.2.3, 10.2.4, 10.2.7, 10.3.3, 10.3.15 and 10.5.1.
- Ministry of Finance and Ministry of Housing and Urban-Rural Development, Notice on Improving the Measures for the Settlement of Construction Project Payments (Cai Jian [2022] No. 183), Article 2; original text on the Chinese government website: https://www.gov.cn/zhengce/zhengceku/2022-06/30/content_5698595.htm
- Xinjiang Uygur Autonomous Region Departments of Housing and Urban-Rural Development and others, Notice on Pilot Work of Interim Settlement by Construction Stage in Building and Municipal Infrastructure Projects (24 March 2022), Article 4; original text on the website of the Xinjiang Housing and Urban-Rural Development Department: https://zjt.xinjiang.gov.cn/xjzjt/c113238/202205/917d2c70463647c6a159e0e4c12575a5.shtml
- Zhejiang Provincial Departments of Housing and Urban-Rural Development and others, Implementation Opinions on Promoting Interim Settlement by Construction Stage in Building and Municipal Infrastructure Construction Projects, Article 6; see the policy documents section of the Zhejiang Housing and Urban-Rural Development Department website (jst.zj.gov.cn).
- Related reading: the evolution of the 'double 80%' payment floors for progress payments and interim settlement amounts, the re-measurement of preliminaries and main contractor's attendance and coordination provisions before the final account, and the mutually exclusive boundary between retention money and performance security; see the related cards cited by this card.
Keywords
- interim settlement by construction stage
- 过程结算节点划分
- 过程结算支付比例80%
- GB/T 50500-2024 10.2.4
- 竣工结算应支付价款
- 质量保证金3%
- 过程结算不再重复审核
- 财建〔2022〕183号