Preventing over-settlement and duplicate settlement of subcontracted quantities: dual-signature locking of measurement + interim settlement by construction stage merged into the final account + the list of items not measured

Preventing over-settlement/duplicate settlement relies on procedural control rather than account-checking error correction: measurement results, once signed and confirmed by both parties, are locked as the basis for settlement (GB/T 50500-2024 Clauses 7.1.7/7.1.8); signed interim settlement by construction stage documents are merged into the final account and are not re-measured or re-priced (Clause 10.2.3); after dual signing of the final account no repeated checking is allowed (Clause 10.3.12); quantities with unapproved commencement reports, failed acceptance, beyond the construction drawings, unlawful subcontracting or contract transfer (re-letting of the whole works), rework, etc. are not measured at all (TB 10402-2019 Clause 6.0.6 and others).

Applicable Codes

  • GB/T 50500-2024 第7.1.7、7.1.8、7.5.5、9.1.13、10.2.3、10.3.12条
  • TB 10402-2019 第6.0.1~6.0.8条
  • DB37/T 5028-2022 第6.2.4条
  • DBJ41/T 208-2018 第7.3.2条
  • 建设部令第124号 房屋建筑和市政基础设施工程施工分包管理办法

Topic Positioning

The governance mechanism for preventing over-settlement and duplicate settlement in the measurement and settlement of subcontracted (specialist/labour) works: four procedural gates — dual-signature locking of measurement results, interim settlement by construction stage merged into the final account, a list of items not measured, and ledger reconciliation.

Core Conclusions

  1. Dual-signature measurement system: the employer and the contractor shall sign and confirm the measurement results on which agreement is reached (GB/T 50500-2024 Clause 7.1.7); the signed and confirmed measurement results serve as the basis for adjustment of the contract price and for settlement (Clause 7.1.8) — once signed, they are locked; neither party may reopen and recalculate afterwards.
  2. Locking by interim settlement: interim settlement documents signed and confirmed by both parties shall form part of the final account documents, and the final account shall not re-measure or re-price them (Clause 10.2.3); preliminaries and the main contractor's attendance and coordination provisions are adjusted only per Clause 10.3.3; after dual signing of the final account the employer may not demand repeated checking with other cost consultants (Clause 10.3.12). This mechanically eliminates computing the same quantity twice.
  3. Items not measured (TB 10402-2019 Clause 6.0.6, DB37/T 5028-2022 Clause 6.2.4, DBJ41/T 208-2018 Clause 7.3.2): quantities with an unapproved commencement report, not accepted or failing acceptance, beyond the construction drawings or approved design changes, arising from unlawful subcontracting or contract transfer (re-letting of the whole works), with incomplete inspection documentation, inconsistent with the contract and design documents, or reworked due to the contractor's own reasons are not measured at all.
  4. Procedure and ledgers: the Engineer verifies declared quantities against the construction drawings (including approved changes) and the contract BOQ; where there is doubt, both parties re-check jointly and re-measure by sampling; if the contractor does not cooperate with the re-check, the quantities corrected by the Engineer's review are deemed the completed quantities; the Engineer shall establish monthly (quarterly) ledgers of completed quantities and payment statistics, comparing actual with planned (TB 10402-2019 Clauses 6.0.4, 6.0.5).

Applicable Boundaries

Applies to control during construction of subcontract measurement and settlement in building, municipal, railway and other works; the core is procedural constraint — with dual-signature measurement, locking by interim settlement, and enforcement of the list of items not measured in place, over-settlement and duplicate settlement cannot occur. This card does not cover specific amount calculations; for the rule that certified dayworks records not reviewed within the agreed period are deemed accepted, see GB/T 50500-2024 Clause 7.5.5.

Further Reading

GB/T 50500-2024 Clauses 7.1.7, 7.1.8, 7.5.5, 9.1.13, 10.2.3, 10.3.12; TB 10402-2019 Clauses 6.0.1~6.0.8; DB37/T 5028-2022 Clause 6.2.4; DBJ41/T 208-2018 Clause 7.3.2; for the definition of unlawful subcontracting and contract transfer (re-letting of the whole works) and subcontract contract filing, see Ministry of Construction Order No. 124, Measures for the Administration of Construction Subcontracting of Building and Municipal Infrastructure Works, Articles 5, 10 and 13.