Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Definition, classification hierarchy, and bases for handling the final account for construction works (GB/T 50500-2024)

The final account is the total-price settlement handled by the employer and contractor in accordance with the contract after the works pass taking-over (completion acceptance), and is the aggregation of interim settlements by construction stage (China's 2020-introduced staged settlement system, with no exact international equivalent); it is composed level by level from unit works -> single works -> project final account. Unless otherwise agreed in the contract, the amounts in the interim settlement by construction stage shall serve as the basis for the final account; the basis for settlement comprises five categories — contract documents; as-built drawings and variation documents; technical data and material-substitution approvals; pricing documents and bills of quantities (BOQs); and mutually confirmed site instructions / variation records and claim documents.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 50326-2017 建设工程项目管理规范
  • GB/T 51095-2015 建设工程造价咨询规范

Topic Positioning

This card explains the standard definition of 'final account for construction works', its position in the settlement system, its hierarchy, and its bases for handling — to quickly define 'what the final account is' and its relation to interim settlement by construction stage (China's 2020-introduced staged settlement system, with no exact international equivalent) and final project accounts.

Core Conclusions

  • Definition (GB/T 50500-2024 term 2.0.35): the final account is the total-price settlement handled by the employer and contractor per the contract after the works pass taking-over (completion acceptance), aggregating the interim settlements by construction stage.
  • The settlement system falls into four classes: interim settlement by construction stage (monthly, quarterly, annual, by physical-progress milestone); contract-termination settlement; final account; warranty clearance settlement.
  • Hierarchy: unit-work final account -> single-work final account -> project final account, aggregated level by level.
  • Handling rule (10.3.1): compiled and checked after completion per the contract and Clause 10.2.1, based on all interim settlement by construction stage documents signed and confirmed by both parties; unless otherwise agreed, the interim settlement by construction stage amounts shall serve as the basis for the final account.
  • Five basis categories (GB/T 50326-2017 18.3.3): contract documents; as-built drawings and variation documents; technical data and material-substitution approvals; pricing documents and bills of quantities (BOQs); mutually confirmed site instructions / variation records and claim documents.
  • Easily confused: the final account is prepared by the contractor and reviewed by the employer — a price settlement between the two parties; final project accounts are prepared by the project owner to determine the project's asset value.

Applicable Boundaries

For the definition, classification, and basis for settlement of the final account; specific quantity/pricing methods and dispute-appraisal rules are expanded in related cards. Contract agreements prevail. Do not confuse with 'final project accounts' — different preparers and purposes.

Further Reading

GB/T 50500-2024 'China national pricing standard for BOQ of construction works' Clause 2.0.35 (term), Clauses 10.2.1, 10.3.1 (final account handling); GB/T 50326-2017 'Code for construction project management' Clause 18.3.3 (basis for settlement); GB/T 51095-2015 'Code for construction cost consultancy' Clause 8.1.2 (final account review adjustment items).