Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Priority of price bases for construction payment settlement: contract agreement > price confirmed by both parties > published price information > market price enquiry (purchase contract / invoice prices require the employer's approval of material prices)

Bases for settlement by priority: ① contract-agreed price (fundamental basis); ② price confirmed by the employer and contractor (certified record of agreed material prices — report quantity and unit price to the employer for verification before purchase; deemed approval upon lapse of the response period); ③ published price information (base price for adjustment / dispute fallback); ④ market price enquiry (for provisional sums and materials without published prices). Purchase contract prices and invoice prices only prove actual cost and become a basis for settlement only after the employer's approval of material prices.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • T/ZBD 100.5-2023 建设工程结算审核作业指引
  • DB42/T 823-2021
  • DB37/T 5130-2018
  • DBJ/T 15-153-2019
  • DB11/T 382-2017

Topic Positioning

When published price information, market price enquiry prices, purchase contract prices and invoice prices conflict, which is the basis for settlement? This card sets out the ranking of the legal effect of the four price types and the key points of the "employer's approval of material prices" procedure, for use in certified records of agreed material prices, price adjustment (for fluctuation) and final account disputes.

Core Conclusions

Priority of bases for settlement: ① Contract-agreed price — the fundamental basis of construction payment settlement is the construction contract; wherever pricing rules or adjustment methods are agreed, the agreement governs (GB/T 50500-2024 Clause 10.3.1; T/ZBD 100.5-2023 Clause 1.4.2); ② Price confirmed by the employer and contractor — absent or unclear agreement, where the employer-approved purchase price is used as the basis for adjustment, the contractor shall report the quantity and unit price to the employer for verification before purchase, and failure to reply within the time limit constitutes deemed approval (GB/T 50500-2024 Appendix A, Clause A.2.5); certified records of agreed material and equipment prices are among the bases of preparation for settlement; ③ Published price information — indicative guidance prices, serving as the source of the base price for adjustment; where the dispute is significant, provisionally book at the current published price and adjust at final account per the actually confirmed price (Appendix A, Clauses A.2.1, A.2.2), with the adjustment order "contractual agreement takes precedence → published price information → market conditions"; ④ Market price enquiry — for provisional sums and materials without published prices, confirmed by both parties after multi-source comparison. Purchase contract and invoice prices prove "what was actually spent" and become the basis of "what should be paid" only after the employer's approval of material prices.

Applicable Boundaries

Applies to construction contract settlement and material price differential adjustment. Where the contract clearly agrees the adjustment method, other prices serve only as corroborating references. Published price information cannot directly replace market price enquiry as a pricing basis (some provincial standards explicitly forbid "directly selecting the published price") and serves only as fallback. Not applicable to pure market procurement without a construction contract, fixed-price contracts, or retrospective certification outside the procedure.

Further Reading

GB/T 50500-2024 Clause 10.3.1, Appendix A Clauses A.2.1/A.2.2/A.2.5; T/ZBD 100.5-2023, Guideline for Final Account Review of Construction Works, Clause 1.4.2; DB42/T 823-2021 (certified records of agreed material prices as a basis for settlement); DB37/T 5130-2018 Clause 7.5.2 (adjustment order); DBJ/T 15-153-2019 (price enquiry and verification must not directly take published prices); DB11/T 382-2017 Clause 5.3.3 (joint enquiry and comparison for provisional-sum materials).

Keywords

Cited By