Priority of price bases for construction payment settlement: contract agreement > price confirmed by both parties > published price information > market price enquiry (purchase contract / invoice prices require the employer's approval of material prices)
Bases for settlement by priority: ① contract-agreed price (fundamental basis); ② price confirmed by the employer and contractor (certified record of agreed material prices — report quantity and unit price to the employer for verification before purchase; deemed approval upon lapse of the response period); ③ published price information (base price for adjustment / dispute fallback); ④ market price enquiry (for provisional sums and materials without published prices). Purchase contract prices and invoice prices only prove actual cost and become a basis for settlement only after the employer's approval of material prices.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- T/ZBD 100.5-2023 建设工程结算审核作业指引
- DB42/T 823-2021
- DB37/T 5130-2018
- DBJ/T 15-153-2019
- DB11/T 382-2017
Topic Positioning
When published price information, market price enquiry prices, purchase contract prices and invoice prices conflict, which is the basis for settlement? This card sets out the ranking of the legal effect of the four price types and the key points of the "employer's approval of material prices" procedure, for use in certified records of agreed material prices, price adjustment (for fluctuation) and final account disputes.
Core Conclusions
Priority of bases for settlement: ① Contract-agreed price — the fundamental basis of construction payment settlement is the construction contract; wherever pricing rules or adjustment methods are agreed, the agreement governs (GB/T 50500-2024 Clause 10.3.1; T/ZBD 100.5-2023 Clause 1.4.2); ② Price confirmed by the employer and contractor — absent or unclear agreement, where the employer-approved purchase price is used as the basis for adjustment, the contractor shall report the quantity and unit price to the employer for verification before purchase, and failure to reply within the time limit constitutes deemed approval (GB/T 50500-2024 Appendix A, Clause A.2.5); certified records of agreed material and equipment prices are among the bases of preparation for settlement; ③ Published price information — indicative guidance prices, serving as the source of the base price for adjustment; where the dispute is significant, provisionally book at the current published price and adjust at final account per the actually confirmed price (Appendix A, Clauses A.2.1, A.2.2), with the adjustment order "contractual agreement takes precedence → published price information → market conditions"; ④ Market price enquiry — for provisional sums and materials without published prices, confirmed by both parties after multi-source comparison. Purchase contract and invoice prices prove "what was actually spent" and become the basis of "what should be paid" only after the employer's approval of material prices.
Applicable Boundaries
Applies to construction contract settlement and material price differential adjustment. Where the contract clearly agrees the adjustment method, other prices serve only as corroborating references. Published price information cannot directly replace market price enquiry as a pricing basis (some provincial standards explicitly forbid "directly selecting the published price") and serves only as fallback. Not applicable to pure market procurement without a construction contract, fixed-price contracts, or retrospective certification outside the procedure.
Further Reading
GB/T 50500-2024 Clause 10.3.1, Appendix A Clauses A.2.1/A.2.2/A.2.5; T/ZBD 100.5-2023, Guideline for Final Account Review of Construction Works, Clause 1.4.2; DB42/T 823-2021 (certified records of agreed material prices as a basis for settlement); DB37/T 5130-2018 Clause 7.5.2 (adjustment order); DBJ/T 15-153-2019 (price enquiry and verification must not directly take published prices); DB11/T 382-2017 Clause 5.3.3 (joint enquiry and comparison for provisional-sum materials).
Keywords
Related Cards
- →
Contractor's objection period and tiered remedies against final account review results (GB/T 50500-2024)
After receiving the settlement verification/review result, the contractor must raise itemized written objections within the agreed objection period (28 days absent agreement), failing which the result is deemed accepted (GB/T 50500-2024 Clauses 10.3.8, 10.3.10); if dissatisfied, escalate through the ladder: recheck → incomplete settlement first for undisputed parts → negotiation/professional conferencing → dispute review/mediation → administrative mediation (within one month) → arbitration/litigation, while continuing performance during the dispute.
- →
Market-inquiry pricing when no applicable quota exists: the two-step method (multi-source inquiry → labor/material/machinery pricing) and traceability/audit requirements
A missing quota does not mean missing pricing rules: the all-in unit rate structure (labor/materials/machinery + management fee + profit + statutory fees + taxes) stays unchanged, with labor/material/machinery prices obtained instead from multi-channel market inquiries (online platforms / telephone / site visits / similar-project benchmarks), and consumption referenced from similar quotas with correction, manufacturer technical parameters, or field measurement. Inquiries must be multi-source and benchmarked, consistent with design parameters, and must not directly pick published prices; records are countersigned and a ledger kept; fees still accrue per the fee standards. The priority of price bases is contract agreement > price confirmed by both parties > published price > market inquiry — inquiry-based pricing is the last resort and requires employer / auditor acceptance with traceability (inquiry-verification report, preparation notes, all-in unit rate analysis sheets).
- →
Guidance price vs market price: definition sources, essential difference and role positioning (official term definitions + three-channel classification rule)
The guidance price (construction cost information) is the labor/material/plant-shift price information plus cost indices and indicators periodically published by cost management agencies — a reference, guidance price (GB/T 50875-2013 clause 2.1.16); the market price is the actually transacted price, acquired mainly through transactions. The two differ essentially; per T/ZBD 100.1-2022 clause 7.2.3 they must be developed as data under the three channels market/guidance/vendor-quotation prices, strictly never mixed. Guidance prices serve maximum bid prices, adjustment base prices and dispute fallbacks; market prices serve actual procurement cost verification, filling gaps of materials without guidance prices, and — after joint confirmation — as settlement bases.
- →
Published price information vs actual procurement price: issuing body, basis and timeliness, settlement effect (practice comparison)
The published price information is a regional statistical composite price periodically issued by cost management agencies (monthly/quarterly issues, lagging, excluding brand, batch, haul distance and payment terms); the actual procurement price is the enterprise's real current transaction price (including brand/model, batch, haul distance and freight, payment terms, VAT rate, bargaining power and other specifics) — either can be higher or lower: batch purchase plus cash payment is often below the published price information, while small-batch urgent purchase or long-distance haul is often above. The published price information is used for tender price ceilings, contract-agreed adjustment base prices and dispute fallback references; the procurement contract price and the invoice price only prove actual cost and must first be confirmed by the employer as an agreed material price (certified record of agreed material prices) before being upgraded to a basis for settlement.
Cited By
- ←
The price-taking order for deducting employer-supplied materials where the contract is silent: fix the 2013 / 2024 pricing basis first, then descend supply-contract unit price -> the signed Schedule of Employer-Supplied Materials -> the parties' pre-purchase confirmed price -> the Civil Code statutory fallback, with the price and quantity rules of cost expert assessment
Silence never means a blanket published price or market price. Under GB/T 50500-2024 (free-issue prices never enter the all-in rate, clause 3.6.1) the deduction price takes first the unit price of the corresponding supply contract (clause 3.6.3), deducting only the contractor-fault over-draw; under GB 50500-2013 (free-issue prices already in the rate, clause 3.2.1) recovery runs in full at the unit price of the signed Schedule of Employer-Supplied Materials and Equipment x quantity (clause 10.3.5). Next the parties' pre-purchase confirmed price (2024 Appendix A clause A.2.5, silence in time deeming approval; GB/T 51262-2017 clause 5.6.4(1)); unreported purchases take the contractual price (item 2 of the same clause); only a wholly missing evidence chain falls to Civil Code Article 510 (supplementary agreement, related terms or trade usage) and Article 511(2) - 'the market price at the place of performance when the contract was concluded', with the assessment fallback per T/ZBD 100.4-2023 clause 3.1.6's three routes. Quantity runs its own basis: actual consumption = issues - stock (T/ZBD 100.4-2023 clause 4.5.7); the 2013 basis takes the consumption of like items in the pricing quotas (2013 clause 3.2.4).
- ←
Splitting the remedy paths and procedural requisites when material prices rise: whether to go first for contract price adjustment (price adjustment for cost fluctuation) or for a works claim; the time limits, written requisites and negotiation sequence of each path; and the consequences of a missed or wrong procedure (GB/T 50500-2024 cl. 8.7, cl. 8.11 and Annex A; Civil Code art. 533; Fa Shi [2026] No. 12 art. 9)
The first path for a material price rise is contract price adjustment, not a claim: GB/T 50500-2024 cl. 8.11.2 states that where an event has already had its price adjustment calculated under the contract price adjustment provisions (excluding claims), no further works claim shall be calculated - duplicate claims will be disallowed. The adjustment path runs: report quantities and unit prices before procurement -> employer checks and confirms (no reply within the agreed period is deemed approval; GF-2017-0201 general conditions 11.1 gives 5 days) -> adjust under cl. 8.7.2 (fluctuation beyond 5% where the contract sets no band) per Annex A -> submit the price adjustment report, employer verifies and confirms (cl. 8.1.3) -> confirm, sign and pay together with the progress payments / interim settlement by construction stage payments (cl. 8.1.6). Only where the contract provides no adjustable price, for abnormal fluctuation of non-adjustable materials (cl. 8.7.3), or where the rise intertwines with delay losses does the claim path open: Notice of Claim (within the contract-agreed period after the event, 28 days where unspecified) -> claim report (28 days after the notice) -> employer 14 days to request further particulars, 28 days to reply -> confirm, sign and pay; a late notice 'may be treated as waived', and the other party's late reply 'may be deemed accepted'. For fixed-price settlement, requests to adjust solely for major changes in labour cost or key material prices within the construction period are not supported by the courts (Fa Shi [2026] No. 12 art. 9), unless otherwise agreed or qualifying as change of circumstances under Civil Code art. 533.
- ←
Hierarchy of effect and order of interpretation when tender documents, bid documents and the awarded contract conflict over material price adjustment (adjustment of the works price): substantive content follows the tendering and bidding documents; conflicts that are not substantive follow the priority order of contract documents (particular conditions first; later signing of the same class first) and the limits of those rules
A price-adjustment clause is part of the pricing and adjustment method of the 'works price' and so falls within the reach of substantive content: where the awarded contract differs from the tender documents, bid documents or letter of acceptance, those documents govern settlement of the works price (Bidding Law Art. 46; Implementation Regulations Art. 57; Fa Shi [2020] No. 25 Arts. 2 and 22). Internal conflicts not amounting to substantive departure are construed by the priority order of contract documents (GF-2017-0201 Clause 1.5: contract agreement > letter of acceptance > letter of tender with appendices > particular conditions > general conditions > technical standards > drawings > priced BOQ > other documents; for documents of the same class the latest signing prevails), that is 'particular over general, later over earlier within the same class'; but 'later over earlier' is a rule of interpretation, not a power of variation, and cannot give variation effect to a later agreement that departs from substantive content (Civil Code Art. 544: a variation whose content is unclear is deemed not varied). Where the position still cannot be fixed, construe comprehensively under Civil Code Arts. 142 and 466 and Fa Shi [2023] No. 13 Art. 1.
- ←
Determining the settlement quantity where the quantity in a materials procurement contract differs from the delivery note: contractual measurement terms prevail; signing raises only a presumption of quantity and apparent conformity (rebuttable); written quantity objection within the inspection period and the chain of proof
Neither the 'contract quantity' nor the 'delivery-note quantity' can be used directly as the settlement basis; the settlement quantity is the quantity actually delivered and confirmed by the buyer's inspection (acceptance / re-weighing) under the measurement and settlement standards agreed in the contract. The contract fixes only the 'due quantity' and the pricing basis; the quantity actually performed is fixed at the delivery and inspection stage. Where no inspection period is agreed, a signed delivery note merely 'presumes' under Article 623 of the Civil Code that the buyer has inspected the quantity and apparent defects, unless contrary evidence suffices to rebut it. The buyer must object to the quantity in writing within the agreed inspection period (or, absent agreement, within a reasonable period from discovery or when it should have discovered, at most two years from receipt); failure to notify deems the quantity conforming (Article 621).
- ←
Construction contract void but works passed acceptance - the rule of discounted compensation by reference to the contractual agreement
Civil Code, Article 793(1): where the contract is void but the works passed acceptance, the contractor may be compensated at a discount by reference to the contract's agreement on the price of the works; where several void contracts exist for the same works, reference is made to the contract actually performed, or, if that cannot be determined, to the last contract signed (Fa Shi [2020] No. 25, Article 24). 'Reference' does not mean repricing under government quota norms; passing acceptance is a precondition for the claim.
- ←
Choosing among the three bases of material price adjustment (bid price / base-period published information / jointly confirmed price): statutory sources, defaults, difference-rate versus risk-band linkage and item-by-item locking (GB/T 50500-2024 term 2.0.21, Appendix A.2, G.2.1)
Per GB/T 50500-2024 Appendix A.2.1, the base price C0 is 'the market price level at the base date (28 days before the tender deadline; non-tendered, 28 days before contract signature)' with only three statutory sources: the market prices used for the tender price ceiling, the cost authority's current-quarter (month) published information, and award prices of like works from the trading centre of the same period and conditions - the tenderer must state the source, publisher and specific quarter (month). The bid price is thus not a statutory C0 source (Table G.2.1-1: base price and risk band by the tenderer, bid price by the bidder), and the confirmed price corresponds in A.2.1 to a source of the current period price Ci - both rise to C0 only by express contract. Difference rate = (Ci - C0) / C0 x 100%; against the risk band r only the excess adjusts: rising, unit difference = Ci - C0 x (1 + r); falling, = C0 x (1 - r) - Ci; the amount x Q carries VAT only, never overheads or profit (3.3.5); absent an agreed band, swings beyond 5% adjust (8.7.2).
- ←
The step chain of adjusting on published price information: fix the adjustable list -> lock base price C0 -> take period prices Ci -> difference x adjustable quantity Q -> adjust the excess over the risk band -> book into progress and settlement, with fallbacks for missing periods and items and the Q test (GB/T 50500-2024 Appendix A.2; against superseded GB 50500-2013 Appendix A.2)
Six steps: (1) fix the adjustable material / labour list (2024: 3.3.5 item 2 + Appendix G Tables G.2.1-1/-2; 2013: 9.8.2 agreed scope, else over 5% adjusts the excess) -> (2) lock C0 = the market price 28 days before the tender deadline (non-tendered: signature), source, publisher and quarter (month) stated (A.2.1; 2013 A.2.3) -> (3) take Ci per measurement period; several prices within a period take the arithmetic mean, the quantity-weighted mean or the main-consumption-period price (A.2.1, A.2.3) -> (4) difference x Q (2024 A.2.1 formula; 2013 has only the 'excess on actuals' principle, no explicit formula) -> (5) adjust only beyond the agreed band r (rising Ci - C0(1+r), falling C0(1-r) - Ci; absent a band, over 5% - 8.7.2 / 2013 9.8.2) -> (6) book into cumulative progress and pay with progress and interim settlements (9.4.6, 8.1.6). Missing periods fall back in order: contract rule -> same-period alternative source -> in-period averaging -> provisional posting on current information with later truing (A.2.2) -> employer-recognised purchase price (A.2.5; 2013 A.2.3 item 4: 3 working days' silence deems approval; unreported self-purchase refused by the employer never adjusts) -> market enquiry by three parties; 'carry the last period forward' has no national-text basis outside the index method (2013 A.1.2). Q follows the contractual quantity rule; the default is the consumption of measured completed work - never signed list quantities or purchase / invoice totals; differences carry VAT only (3.3.5 item 4).
- ←
Defining the scope of adjustable (price-adjustable) materials: locked by contract annex tables, not share thresholds; auxiliary and low-value materials outside adjustment (neither coefficient-merged nor overheads-lumped); the negotiation channel for unlisted materials' abnormal swings (GB/T 50500-2024 clauses 3.3.1, 3.3.5, 8.7.3, 8.7.5, 8.7.6; Appendix G.2, A.2.1)
GB/T 50500-2024 sets no material-cost share threshold: the adjustable scope locks item by item in annex Tables G.2.1-1 / G.2.1-2 (Appendix G.2) - tenderer filling name, specification, unit, base price and risk band, bidder the price, quantities per the contractual rule (3.3.5, G.2.1). Auxiliary and low-value materials (consumables, small tools, preliminaries, non-agreed materials) plus overheads and profit never adjust for price moves (8.7.6) - there is no national channel 'merging auxiliaries by coefficient', nor are they an overheads lump: their price risk sits inside the material cost of the all-in rate. Unlisted materials adjust in principle never; only on abnormal, unforeseeable-at-contracting moves making performance plainly inequitable may the parties negotiate band or sharing per equitable allocation (8.7.3). Free-issue and provisionally priced items sit outside 8.7.2~8.7.4 (8.7.5). Local share-threshold practices are local documents - verify current numbers.
- ←
Tender BOQ versus priced BOQ - relationship and effect compared: preparing and pricing parties, document status, content differences, accuracy responsibility (2013 edition clause 4.1.2 versus 2024 edition clause 3.1.8 split by unit-rate and lump-sum contracts), benchmark role in settlement (quantity variance under 9.6.2, variation valuation under 9.3.1), effect of unilateral amendment, and the order of precedence of contract documents
The two bills are not two documents but two stages of one bill: the tender BOQ is prepared by the tendering employer stating 'quantities and item descriptions' and issued with the tender documents as the common basis of tender pricing (GB 50500-2013 clauses 2.0.2, 4.1.2 (mandatory provision) and 4.1.3); the priced BOQ is the priced version in which the bidder enters all-in unit rates and lump sums and which becomes part of the contract documents after award (2013 edition clause 2.0.3; the 2024 edition calls it the 'contract bill of quantities', clauses 2.0.18 and 3.4.5), its all-in unit rates being the contract unit rates used for settlement and contract price adjustment. Responsibility follows the basic split 'quantities by the tendering employer (employer), prices by the bidder': clause 4.1.2 of the 2013 edition puts it on the tendering employer in all cases; GB/T 50500-2024 clause 3.1.8 changes course - under unit-rate contracts the employer answers for the measured-works bill (bidders may not alter it; defects are repriced under section 8.2), under lump-sum contracts the contractor answers, and preliminaries are always the contractor's. In settlement, quantity variance follows clause 9.6.2 of the 2013 edition (deviation beyond 15%: the all-in unit rate is lowered for the portion of quantity increase above 15%, and raised for the remaining portion after a decrease beyond 15%), and variation valuation follows the three-tier cascade of clause 9.3.1 (applicable -> analogous by reference -> a rate proposed by the contractor from the pricing methods and published price information combined with the tender price fluctuation rate, submitted to the employer for confirmation).
- ←
Treatment of the four items of the bill of provisional sums and other charges under GB/T 50500-2024 in performance and at the final account: unused provisional sums revert to the employer, provisional prices replaced and adjusted, dayworks measured as incurred, main contractor's attendance and coordination provisions lump-sum or re-rated, plus the final account item sequence (sections 8.3-8.6, clauses 10.3.2 / 10.3.3)
Under GB/T 50500-2024: provisional sums (8.3.1, 8.3.5) are controlled by the employer and used per instruction; they accrue to the contractor only when actually incurred, and where no adjustment event occurs the whole amount is deducted at the final account with the balance reverting to the employer. Provisional prices (8.4) are replaced by the tender winning price or a price confirmed by the employer; for materials only the pre-tax material provisional price inside the all-in unit rate is adjusted and other costs stand, while nominated specialist works are replaced wholesale at tax-inclusive prices. Dayworks (8.6) are measured as incurred under section 7.5 and priced at the contract dayworks rates; the final account includes the amounts actually incurred and deducts the dayworks amounts of the original BOQ, with no separate preliminaries. Main contractor's attendance and coordination provisions (8.5): when priced per item they are at lump-sum risk and not adjusted at the final account; when priced by percentage rate they may adjust under clauses 8.5.1-8.5.5 for changes in the scope of materials or subcontract works, variations, or employer-caused time changes; contractor-caused delay is not adjusted and attracts delay damages. The final account lists items in the 13-item sequence of clause 10.3.2, and attendance provisions and preliminaries must be re-calculated per clause 10.3.3.
- ←
Labour cost pricing basis within the all-in unit rate: norm-based labour cost (base-period workday rate) versus current-period published labour price information and labour market prices, the applicable rules at the tender price ceiling and tender stages, and the test that the labour cost differential and the labour cost inside the all-in unit rate are not adjusted twice
Labour cost in the all-in unit rate = norm (budget) labour consumption x the current-period labour rate (published price information or a market price confirmed by the parties): consumption is locked to the quota manual while the rate is opened to the current-period market (GB/T 51095-2015, clause 5.3.9). The base-period workday rate published with the quota manuals is not itself the pricing input for BOQ rate build-up; it is a component of norm-based labour cost and the comparison base of the labour cost differential. At the tender price ceiling stage the published labour rates / published price information take precedence (GB/T 50500-2024, clauses 5.2.1 and 5.2.8); the tender is priced freely by the tenderer on its in-house norms and the market, but not below cost and not above the tender price ceiling (clauses 6.1.1, 6.1.3, 6.2.1). Differentials caused by changes in costs carry VAT only, not overheads or profit (clause 3.3.5); the same labour differential may be taken once only, in either the current-period-price pricing system or the base-period-price-plus-differential system, and must not be stacked on the labour cost already inside the all-in unit rate.
- ←
Choosing the format of the all-in unit rate analysis sheet, its mandatory preparation requirements, and its roles across tendering, settlement and audit (GB/T 50500-2024 Appendix E, tables E.2.2-1 and E.2.2-2)
GB/T 50500-2024 Appendix E provides that detailed all-in unit rate analysis shall follow table E.2.2-1 and simplified analysis table E.2.2-2, the choice being fixed by the tender requirements and the contract; the rates in the analysis sheet and the prices of lump-priced items must be 'completely consistent' with the corresponding figures in the BOQ (clause 3.1.7); at tender the sheet, together with tables E.3.2, E.3.3 (which must list initial set-up, mid-term operation and final dismantling costs) and E.3.4, must be submitted in full, consistent with the priced BOQ (clauses 6.2.12 and 6.2.13). The all-in unit rate carries risk costs within the agreed scope and bands and excludes VAT (clauses 2.0.9 and 3.2.2), so the risk allowance sits inside the rate build-up rather than as a stand-alone charge. At settlement, clause 3.1.6 requires item-by-item checking that rates match the priced BOQ in the contract, with no adjustment except for variations and agreed matters; dayworks and additional works may draw on 'the detailed price make-up in the all-in unit rate analysis sheet of similar BOQ items' (clause 8.6.3; cost expert assessment guideline clause 4.8.4); audit examines whether new rate build-ups follow the quota pricing rules agreed in the contract, whether every line-item price is fixed, and whether common material prices are reasonable.
- ←
Deduction of employer-supplied (free-issue) materials from payments and allocation of costs: deduction mechanism, procurement/custody fee and wastage responsibility (GB/T 50500-2024, T/ZBD 100.4-2023)
Where employer-supplied (free-issue) material prices are not included in the all-in unit rate (stripped pricing), settlement naturally requires no deduction; where the contract stipulates prior inclusion, deduct from the settlement amount at actual consumption (issued quantity − stock) × the supply contract unit price. Procurement and custody costs follow the material and belong to the procuring party (the employer); the cost of the contractor's custody and assistance services is borne by the employer and charged under the main contractor's attendance and coordination provisions; wastage within the valid wastage rate is borne by the employer, over-drawing attributable to the contractor is borne by the contractor, and employer-caused causes (non-conforming specifications, untimely supply) are borne by the employer.
- ←
Provisional prices (materials / specialist works): the settlement adjustment procedure of replacing the provisional price with the actual confirmed price - legal position, the submission-checking-review-re-examination-confirmation chain and deemed approval on expiry, the two confirmation routes (compulsory tendering and otherwise), adjusting only the pre-tax material price, the deduction direction when the confirmed price is lower, the boundary against material price adjustment, and the clause mapping of GB/T 50500-2024 against GB 50500-2013
The final account replaces the provisional price with the 'confirmed price' (the tender-winning pre-tax price, or the tax-inclusive tender-winning specialist subcontract price, for items that must be tendered by law; or the pre-tax price from market enquiry or the contractor's own quotation confirmed by the employer for items outside compulsory tendering); published price information is not a basis for settlement adjustment (it only guides the provisional unit rate when compiling the tender price ceiling, or serves as the adjustment baseline where the contract makes that material price-adjustable); the procedure runs under GB/T 50500-2024 clauses 8.1.2 to 8.1.6 - submission, checking, review, re-examination and confirmation - and failure to confirm or comment within the time limit is deemed approval; the adjustment replaces only the material provisional price inside the all-in unit rate (pre-tax); labour, plant, overheads and profit do not move (clause 8.4.6), VAT being charged on the difference; where the confirmed price is below the provisional price the adjustment runs the same way down, deducted from the current progress payment or interim settlement by construction stage, and the final account lists 'provisional price adjustment amounts' separately; BOQ items carrying material provisional prices are outside the material cost adjustment of clauses 8.7.2 to 8.7.4 (clause 8.7.5). The 2013 counterparts are clauses 9.9.1 to 9.9.4.
- ←
Selecting between the two methods of contract price adjustment for changes in costs: comparison of applicable conditions, clause-by-clause contrast and same-contract mixing boundaries of the Appendix A.1 index-based adjustment and the Appendix A.2 adjustment based on published price information under GB/T 50500-2024
The two methods share an identical adjustable scope, base time point and trigger threshold (only labour cost, key material cost and the fuel and power cost of construction plant are adjustable; the base time point is 28 days before the tender deadline; where the contract sets no band or sets it unclearly, fluctuations beyond 5% are adjustable; the differential carries VAT only, never overheads or profit). The difference lies only in the price variable. A.1, index-based (formula) adjustment, takes the VAT-exclusive contract price P0 as the base and weights the fixed weight A and the variable weights B1...Bn of each adjustable factor by the ratio 'current index / base index' - the index source is agreed in the contract, the agreed fluctuation band is folded into the base price index, and where an index is missing the previous measurement period's index may be used provisionally. A.2, adjustment based on published price information, takes the adjustable factor quantity Q as the base and computes the money price differential between the base price C0 and the measurement-period market price Ci less the risk band coefficient r; the base price and the market price are each chosen from three sources (market price used in setting the tender price ceiling / published price information of the cost management agency / tender-winning prices published by the trading centre), whether the band is exceeded is determined by scenarios of the tender price against the base price, and under the purchase-price route the contractor must submit quantity and unit price to the employer for checking before purchase (no reply in time is deemed approval). The standard itself has no dedicated 'applicable conditions' clause, only 'one of the methods of Appendix A'; the choice is first a matter for the contract; where one contract assigns different methods to different adjustable factors, they must be entered separately in Table G.2.1-1 (published price information method) / Table G.2.1-2 (index method), without double counting the same differential.
- ←
Boundary distinctions among omitted BOQ items (BOQ errors), provisional prices, provisional sums, dayworks and site instruction records in contract price adjustment: required but not listed vs listed but unpriced vs confirmation evidence for unforeseen matters
Under GB/T 50500-2024: omission falls under 'BOQ errors' (clause 2.0.27, differences between the BOQ and the contract drawings in items, item descriptions and quantities), handled by re-determining the all-in unit rate under sections 8.2 and 8.9; a provisional price is an item already listed but with the price provisional - once the price is fixed only the price element is replaced: for items subject to mandatory tendering by law, the pre-tax tendered material price or the VAT-inclusive tendered specialist subcontract price replaces it (8.4.1); for items not subject to mandatory tendering, the pre-tax price confirmed by the employer from enquiry or the contractor's own quote replaces it, with the VAT change computed (8.4.5, 8.4.7); a material provisional price adjusts only the pre-tax material price within the all-in unit rate, leaving all other cost elements untouched. Provisional sums are controlled by the employer and used on instruction (8.3.1); when used for works not fully foreseen or specified, the price is adjusted as contract unit rates x quantities from the confirmed drawings (8.3.2); where no adjustment event has occurred, the whole amount is deducted at final account (8.3.5). Dayworks are a pricing method for work not suitably priced under the contract and the pricing standards (8.6.1); at settlement they are counted as actually incurred, but the daywork items already included in the contract price are deducted (8.6.5). Site instruction records are certification of process facts (GB/T 50875-2013 clause 3.4.8, GB/T 50500-2024 clause 12.2.1) and are not an independent price adjustment matter in themselves. The same matter must not be priced twice - once as a new BOQ item for omission and again under dayworks or provisional sums.
- ←
Rate build-up basis and confirmation procedure when a BOQ omission or new item has neither an applicable nor an analogous rate: GB 50500-2013 Section 9.5 (citing the four tiers of cl. 9.3.1) mapped against GB/T 50500-2024 Sections 8.2/8.9/8.10, plus the time limits for adjustment reports
GB 50500-2013 cl. 9.5.1 provides that 'where, during performance, new divisional and sub-divisional works BOQ items arise because of omissions in the tender BOQ, the unit rates shall be determined per cl. 9.3.1 of this code and the contract price adjusted'. Tier 3 of cl. 9.3.1 reads 'where the priced BOQ contains neither an applicable nor an analogous item for the varied work, the contractor shall propose a unit rate for the varied work based on the variation documents, the measurement rules and pricing methods, the published price information issued by the government construction cost administration and the contractor's price fluctuation rate, and adjustment follows employer confirmation'; tier 4 switches, where the published price information lists no price, to a rate based on 'market prices with a lawful basis obtained through market enquiry and other means', again subject to employer confirmation -- so published price information comes first and a lawful market price only fills gaps, and tier 3 must carry the contractor's price fluctuation rate. GB/T 50500-2024 no longer has a stand-alone 'omission' section: erroneous and omitted items are folded into 'errors and omissions in the BOQ' (cl. 8.2.1 -> cl. 8.9.1/8.9.2), additional works outside the contract scope follow Section 8.10 (cl. 8.10.2 requires the contractor to submit the project execution plan or execution scheme, the programme and the priced offer to the employer for review and approval before executing the additional works), the adjustment procedure is unified as 'submission, checking, re-checking, review and confirmation' (cl. 8.1.2 to 8.1.4), and employer silence past the time limit counts as deemed approval of the contractor's report.
- ←
The index-based adjustment method (GB/T 50500-2024 Appendix A.1): the adjustment formula, fixing the fixed weight A and variable weights Bi, and the sources and timing of price indices (factors)
The index method computes dP = P0 x [A + sum Bi x (Fti/F0i) - 1]: P0 the net-of-VAT contract price of the measurement period; A the fixed weight and Bi the weights of adjustable factors on the net-of-VAT contract price, with A + sum Bi = 1; weights and base indices are ranged by the employer and fixed in the tenderer's price-index and weight schedule of the tender-letter appendix, absent which the tender price ceiling's weights may be used (A.1.4); base indices at the contract base date (28 days before the tender deadline for tendered works), current indices per period, the previous period's usable provisionally (A.1.2/A.1.5/A.1.6); the index source is contractual (2024 no longer mandates authority indices first); adjustments carry VAT only, never overheads or profit.
- ←
Pricing and clawback of over- and under-supply of employer-provided (free-issue) materials: at the supply-contract price, not published price information or market price (GB/T 50500-2024 clause set 3.6)
Contractor-caused over-drawing of free-issue materials is charged at the corresponding supply contract's unit price on the over-drawn quantity and deducted from interim or final payments - neither at published price information nor market price; over-quantity = drawn quantity - drawing-derived quantity x (1 + effective wastage), the derivation being actual quantities from the construction drawings for unit-rate contracts and reasonable quantities from the contract drawings for lump-sum, variations excluded. Employer-caused short supply, non-conforming delivery or delay falls on the employer - extension per chapter 8 plus losses including profit; on a switch to contractor purchase, prices come from joint tendering or market enquiry, published price information serving only provisionally where no period market price exists or the dispute is large.
- ←
Settlement pricing when the confirmed price of a provisionally priced material differs from published price information: the procedurally formed confirmed price (net award price, or employer-confirmed enquiry price) replaces the provisional sum, published prices serving only as the contractually agreed base or a provisional fallback in disputes
Settlement follows the confirmed price formed under the contractual procedure - for mandatory-tender items, the net-of-VAT material award price replaces the provisional price; otherwise the employer-confirmed (or jointly enquired) net price does (GB/T 50500-2024 clauses 8.4.1, 8.4.5); published price information neither replaces the confirmed price nor caps or floors it - it applies only where the contract makes it the base, or where a period market price is missing or the dispute is large, provisionally, 'to be trued up in later payments against actual market prices' (Appendix A clause A.2.2). The difference adjusts only the material provisional price (net) within the all-in unit rate, other cost heads unchanged, carrying VAT but never overheads or profit (clauses 8.4.6, 3.3.5 item 4).
- ←
Three-step test for the unit price basis of cofferdam and island-building clay (borrowed fill): no extra charge where the quota already includes borrowing; priced per quota consumption where clay is listed as a material and adjusted as executed; purchased fill follows the fill material cost / norm-based material price basis
Cofferdam clay unit prices follow a three-step test (a decision order, not three alternatives): (1) where the quota item's work content already includes borrowing, no clay material cost is charged - the railway TB/T 10823-2024 Volume 2 plastic woven sack cofferdam work content includes excavation, manual bagging and haulage within 20 m, and its consumption table lists no soil material; (2) where the quota lists clay in the material consumption, price by the quota consumption and adjust at settlement per the actual borrowing (SJG 181.2-2024 Article 8.1.7 paragraph 2); (3) where purchase is genuinely required, the railway uses the fill material cost basis - fill material cost = sum of fill consumption x fill price (TB 10801-2024 Article 3.5.2), the fill price excluding deductible input VAT and being determined by the design institute through investigation and analysis (TB 10811-2024 Article 2.5.1); highways take purchased materials by reference to published prices combined with surveyed market prices, and self-quarried clay at the quota winning price plus auxiliary production on-costs and mineral resources tax.
- ←
Definition and nature of published price information (government guidance prices): reference price information published by cost management agencies (GB/T 50875-2013 clause 2.1.16)
The published price information (government guidance prices) is the 'published construction cost information' defined in clause 2.1.16 of GB/T 50875-2013 "Standard for construction cost terminology": price information for labour, materials, permanent equipment and construction plant machine-shifts, together with cost indices and indicators for various works, published by cost management agencies — reference and indicative prices, not mandatory transaction prices. They must be developed as data under the three channels of market price / published price information / vendor quotation, strictly separated (T/ZBD 100.1-2022 clause 7.2.3), and serve as the base price and dispute fallback in settlement price adjustment.
- ←
Reviewing the final account of lump-sum contracts: adjust only the agreed-adjustable content on the contract total, plus the universal checkpoints, plus the compiling method by contract type
Lump-sum review adjusts, on the contract total, only the content agreed adjustable and the risk factors beyond the agreed scope (T/ZBD 100.5-2023 clause 3.1.5): judge the non-adjustable part from the measurement, pricing and risk-scope clauses and review adjustments only within the adjustable range; against the non-adjustable part, check the settlement drawings, scope and acceptance reports against the contract-price content - unexecuted or inconsistent parts are generally written down; BOQ gaps and quantity issues in a lump-sum contract are deemed fully verified by the contractor and generally attract no further adjustment (unless the employer issued the BOQ and the contract says adjustable); materials above contract brand or quality without employer request add nothing, below contract re-price down; statutory HSE and similar adjust per policy with the contract - agreed non-adjustable preliminaries stay; overlapping interfaces between specialist packages and the main contractor are written down; provisional materials adjust per the approved-price slips (usually materials and tax only); employer-supplied materials and metered water and electricity deduct against contract quantities, over-drawals without back-orders not counted. Clause 3.1.4 lists the universal checkpoints whatever the form: scope changes, work interfaces, whether quantities need re-determination, gaps, provisional specialist works, provisional material and plant prices, employer-supplied materials. DB37/T 5130-2018 clause 8.2.5 sets the compiling method by type: lump-sum adjusts the adjustable on the total; unit-rate holds all-in rates fixed within the risk band and measures as executed; cost-plus computes cost, fee and taxes per the agreed method.
- ←
Pricing channels for works outside the contract scope and unforeseen works: recognising and pricing additional works, when dayworks apply, and the rules for using provisional sums
Where the contractor, at the employer's request, completes additional works outside the agreed scope, the price may be computed per the item-setting requirements, measurement rules, contract rates and tendered rate levels of the national and sector quantity take-off standards, or the measurement and pricing rules may be renegotiated and an additional-works contract or supplementary agreement signed (GB/T 50500-2024 clause 8.10.1). In settlement review, where the parties have not jointly recognised additional works, then absent contract agreement otherwise, any of "contract scope = whole project / single work -> a single work added", "single work -> ancillary or independently tenderable specialist works outside the scope added", "specialist subcontract -> other specialist works outside the scope added" recognises the addition; without a supplementary agreement and without clear pricing principles and methods, the original contract's principles do not necessarily apply (T/ZBD 100.5-2023 clause 3.1.10). Ten classes of matters - added or substituted works not measurable from drawings / variations / contract rules etc. - may be measured and priced as dayworks (clause 7.5.2); provisional sums serve insufficiently foreseeable or detailed works, measured and priced under the variation rules, the contract price adjusting for the difference from the provisional sum including VAT (clause 8.3.2).
- ←
Deciding the pricing type of a contract silent on its price form (colloquially the "fully open contract") and the corresponding scope of quantity and price review
"Fully open contract" is not a legal concept; at normative level only fixed price / adjustable price / cost-plus-fee (Order No. 107 of the Ministry of Construction, Article 12) or unit-rate contract / lump-sum contract / cost-plus-fee contract (GB/T 50500-2024 clauses 2.0.6 to 2.0.8) exist. Where the contract is silent on its price form, classify by pricing mechanism (the basis on which the contract price forms, who answers for quantities, whether drawings or the BOQ prevail in conflict) - never by the contract's name alone. Classified as a re-measurable (unit-rate) contract, quantities are re-verified as executed and all-in unit rates stay fixed within the agreed risk band; classified as a lump-sum contract, only adjustable content and out-of-band risk factors adjust on top of the lump sum and, absent special agreement, re-measurement is inappropriate.
- ←
Deciding how the pumping charge for ready-mixed concrete is applied: reading whether the published price information includes pumping, and the three mutually exclusive quota paths (a separate pumping item / convert materials by delivery method and apply the conveying item / included in the item, not charged again)
There is no national unified rule for pumping charges; two lines decide. (1) The publication notes of the current published price information - where issued as "ready-mixed concrete (pump type)" or marked as including pumping, it is included and never charged again; where issued by strength grade with a remark "pumping charge: truck pump +X, trailer (boom) pump +X yuan per m3", it is excluded and must be added. (2) The compilation basis of the quota item applied - "a separate concrete pumping item" (e.g. TB/T 10831-2024 Volume 10, FY-531 pump wagon 79.57 yuan per 10 m3, FY-532 stationary pump 107.25 yuan per 10 m3); "items exclude conveying - convert materials by delivery method and apply the conveying items of the chapter" (SJG 181.2-2024 Volume 2, clause 2.1.4); "items already include conveying, no further computation" (SJG 181.3-2024, SJG 181.4-2024 general rules). The three are mutually exclusive - one only; double charging is a high-frequency audit disallowance. Where no pumping item exists, charge by pumping plant machine-shifts (JTG/T 3833-2018 pump wagon 1781.5-2194.98 yuan per machine-shift, conveying pump 257.77-1241.61 yuan per machine-shift).
- ←
Organizing the certification of material quality and price for installation materials and equipment: four applicable situations, a six-step implementation process, situation-based rules for employer approval of material prices, and dispute fallbacks
Certification of material quality and price is organized as 'lock quality first, then lock price, then lock evidence': the employer ultimately confirms the price; the contractor submits for approval before procurement; the supervisor reviews quotations, undertakes witnessed sampling and testing, and joins market price enquiries; the project-management body prepares the market price enquiry and pricing implementation plan; contractually adjustable materials must be jointly subject to market price enquiry and the price agreed by the employer, contractor and supervisor before procurement; follow the six steps 'prepare plan -> enquire and compare -> confirm price -> seal samples -> entry inspection -> settlement adjustment'; retroactively supplemented certifications of material quality and price carry weak weight in construction cost expert assessment (judicial appraisal).
- ←
Rules for determining the material adjustment base price (C0): base date, one-of-three sources and the adjustment computation base (GB/T 50500-2024)
The base price C0 = the market price level 28 days before the bid closing date (for non-tendered works, 28 days before contract signing); that instant is the contract base date (term 2.0.21). The source is one of: (1) the market price used in the maximum bid price; (2) the current quarter's (month's) guidance price of the cost management agency; (3) the winning-bid price of analogous works under the same conditions published by the local trading center — all must represent the base-date price level, and the tender documents must state the source, publishing agency and specific quarter (month). Where the guidance price is the base, whether the bid is below/above/equal to the base decides the computation base of the excess portion (appendix A.2.4, preventing high/low-bid arbitrage); the price-index method corresponds to the basic price index F0.
- ←
Can published price information directly serve as the basis for material price adjustment: legality + three preconditions (listing / beyond band / tax) (GB/T 50500-2024)
Published price information (government guidance prices) is a price source expressly recognized for price adjustment (for fluctuation) (Appendix A.2.1: both the base price C0 and the measurement-period price Ci may adopt the current published price information issued by the cost management agency; A.2.4: where published price information serves as both base price and current price, adjust within the agreed risk band), but adjustment is not unconditional and full-scope: (1) the material must be listed in the contract annex "schedule of price-adjustable key materials" (Table G.2.1-1; not listed, not adjusted); (2) only the portion beyond the contract-agreed risk band is adjusted to actual, the band being contractor-borne; (3) where the contract sets no band, fluctuation beyond 5% is the fallback trigger (8.7.2). The price difference carries value added tax (VAT) only, not management fee or profit (3.3.5).
- ←
A determination framework for whether curtain-wall design-development (detail design) costs are included in the contract price: the watershed is to whom the development obligation belongs
Whether curtain-wall design-development costs are included in the contract price depends on "whose contractual obligation the development is": development necessary for the contractor's construction (fabrication drawings, subdivision layout, embedded part positioning, edge detailing, etc.) is the contractor's obligation, its cost already amortized into all-in unit rates/measure costs, not charged again; special designs, curtain-wall consultants, and BIM consulting separately commissioned by the employer are design services commissioned by the employer, outside the construction contract price, contracted and charged separately. Judge by the contract agreement, whether the development changes the design intent, whether the tender BOQ lists it separately, and the positioning in industry specifications; the tender documents and special contract conditions prevail.
- ←
Commercial briefing during contract performance: timing, content checklist, form requirements, and dynamic supplementary briefing
The commercial briefing is the core of contract briefing: give one full briefing after contract signing and before implementation, and supplement it as events occur (variations / site instructions and variation records / claims / price adjustments) during performance; the organizing departments and the contract negotiators brief the project management organization (document interpretation + handover of management responsibilities); content covers the composition and order of interpretation of the contract documents, the contract price at signing, the pricing form, payment terms, variation and claim procedures and time limits, both parties' rights and duties, and risk and liability allocation, with dispute-prone clauses explained thoroughly; written / electronic / audio-visual / oral forms are all acceptable — a written briefing requires a signed acknowledgment, and key links, management systems, work flows, and the relevant authorities shall be fixed in writing.
- ←
Published price information vs actual procurement price: issuing body, basis and timeliness, settlement effect (practice comparison)
The published price information is a regional statistical composite price periodically issued by cost management agencies (monthly/quarterly issues, lagging, excluding brand, batch, haul distance and payment terms); the actual procurement price is the enterprise's real current transaction price (including brand/model, batch, haul distance and freight, payment terms, VAT rate, bargaining power and other specifics) — either can be higher or lower: batch purchase plus cash payment is often below the published price information, while small-batch urgent purchase or long-distance haul is often above. The published price information is used for tender price ceilings, contract-agreed adjustment base prices and dispute fallback references; the procurement contract price and the invoice price only prove actual cost and must first be confirmed by the employer as an agreed material price (certified record of agreed material prices) before being upgraded to a basis for settlement.
- ←
Bases for determining final account quantities: completed qualifying quantities + measurement certification and sign-off lock-in + measurement method by contract type
The final account quantity (in FIDIC contexts, the Final Statement plus discharge) = the qualifying quantities actually completed by the contractor in accordance with the contract and to be measured, calculated under the contract-agreed national and industry quantity take-off (measurement) standards and supplementary calculation rules; the measurement results certified and signed off by both parties (including documents for interim settlement by construction stage (China's 2020 node-based interim settlement system; no exact international equivalent)) serve as the basis for settlement (GB/T 50500-2024 Clauses 7.1.1, 7.1.8, 10.3.1). Lump-sum contracts adjust only the agreed adjustable contents; re-measurable (unit-rate) contracts measure actual completed quantities; cost-plus contracts calculate cost, fee, and taxes per the agreed method; as-built drawings, changes, site instructions/variation records, and concealed-acceptance records form the chain of evidence for 'actual completion'.
- ←
Deduction rules when subcontractors use the main contractor's machinery, materials, and temporary works and site establishment costs: characterization, pricing, and settlement points (GB/T 50500-2024)
The main contractor providing machinery/materials/temporary works and site establishment costs to its own subcontractors is a compensated transfer/lease/service, does not attract the main contractor's attendance and coordination provisions, and must be deducted under separate headings agreed in the subcontract. Materials are recovered by the strip-off method or 'actual consumption (requisition − return − stock) x supply contract unit price'; the portion exceeding the valid wastage rate is borne by the subcontractor and deducted directly from the settlement price; machinery is deducted per agreed machine-shift/monthly rent, and temporary works and site establishment costs per measurement or apportionment, with care against double charging against the subcontract quotation.
- ←
Price adjustment (for fluctuation) calculation for ready-mixed (commercial) concrete: whole-factor adjustment per m³, adjustment to actual beyond the risk band, and tax treatment (GB/T 50500-2024 Appendix A.2 adjustment based on published price information)
Ready-mixed concrete is adjusted as one whole adjustable factor per m³ (the published price information (government guidance prices) already includes raw-material cost; cement, sand/gravel, and admixtures must not be adjusted separately again, to avoid double counting), using the GB/T 50500-2024 Appendix A.2 adjustment based on published price information: beyond-band unit price difference = Ci - C0×(1+r) on a rise, or C0×(1-r) - Ci on a fall; adjustment amount = unit price difference × Q; the agreed risk band (no-adjustment tolerance, e.g. ±5%) prevails; where not agreed or unclear, fluctuation beyond 5% is the fallback trigger (8.7.2); the price differential attracts value added tax (VAT) only, not management fee or profit (3.3.5); where the tender price differs from the base price (reference price for adjustment), apply the A.2.4 cross-base rule against arbitrage. Worked example: C0=480 CNY/m³, Ci=530 CNY/m³, r=5%, Q=1000 m³; fluctuation 10.4% triggers; beyond-band unit difference 26 CNY/m³; adjustment 26,000 CNY; including 9% VAT the tax-inclusive amount is 28,340 CNY.
- ←
Matching material specifications in price information with actual materials: four-element matching, grade/unit conversion, and adjustment-specification locking
Price-taking from price information matches precisely by the four elements name + specification + model + unit (the GB/T 50500-2024 Appendix G adjustment table is listed accordingly); with no same specification, convert by the adjacent grade or grade price difference with records (marked "converted"); inconsistent measurement units are converted first (e.g., rebar in t vs kg/m using theoretical weight); missing items are filled by market inquiry (>=3 suppliers); when adjusting per price information, lock the specification caliber at contract signing via the adjustable main materials table (Appendix G.2.1) and match one-to-one at settlement; where the current issue lacks the corresponding specification, provisionally compute per the current price information and adjust later per actuals (Appendix A.2.2).
- ←
Appendix G main materials (adjustment) list of GB/T 50500-2024: locking stage and adjustment-quantity caliber (contract annex / completed quantities per measurement cycle)
Tables G.2.1-1/2 are filled during tendering and locked as a whole as a contract annex at signing: the tenderer fills scope/base price (market price level 28 days before the bid deadline)/risk band; bidders fill tender prices and agree price data in the tender-letter appendix (3.3.5 item 2, A.2.1). Adjustment quantities are neither tender quantities nor actual purchase quantities but follow "the quantity calculation method the parties specify in the contract" (table note 2, A.2.1); the default framework is quantities corresponding to completed qualifying work in the measurement cycle, measured in segments per adjustment cycle and accumulated (7.1.3).
- ←
Adjustment of the contract price (GB/T 50500-2024 Chapter 8): eleven triggering events, mechanism by section, and FIDIC mapping
Adjustment of the contract price is the mechanism for changing the contract price during performance. GB/T 50500-2024 Cl. 8.1.1 lists eleven triggering events: BOQ errors, provisional sums, PC sums (provisional estimates), contractor's services, dayworks, changes in costs, changes in laws and policies, variations, additional works, claims, and other events agreed by the parties; the procedure runs submit, check, re-check, review and confirm (8.1.2). Key mechanics: BOQ errors and variations share one re-rating ladder (identical items at contract rates; analogous items converted; different items negotiated), with a 15% quantity boundary for re-rating (8.2/8.9); provisional sums are controlled by the employer and any unused balance reverts at final account (8.3); PC-sum items are replaced by tender prices — materials pre-VAT, specialist works VAT-inclusive (8.4); dayworks are measured under 7.5 (certified dayworks records) and priced at the BOQ daywork rates (8.6, with deemed approval if verification is overdue, 7.5.5); changes in costs are adjusted beyond the agreed band — 5% by default — by index-based (formula) adjustment or adjustment based on published price information (8.7 + Annex A), the differential carrying VAT only; changes in laws pivot on the base date, adjusting price and/or time for enactments, amendments, repeals or new interpretations after it, with no upward adjustment during contractor-caused delay (8.8); additional works may follow contract rates or freshly negotiated rules under a supplementary agreement (8.10); claims cover events outside 8.2-8.10 — compensatory, not punitive, and mutual, with profit added for eight categories of employer-risk events (8.11). FIDIC counterparts sit scattered across Clause 13 (variation valuation 13.3, provisional sums 13.4, changes in laws 13.6, changes in cost 13.7 — 2017 numbering) and Clause 20 claims (28-day hard time bar): adjacent institutions, not chapter-for-chapter equivalents.
- ←
Determining labour cost in the all-in unit rate: the two-step "norm resource consumption × labour unit price" method and its standard basis
Labour cost in the all-in unit rate is determined in two steps as "norm labour consumption × labour unit price": consumption is taken from the budget quota line item (GB/T 51095-2015 Clause 5.3.9); the unit rate follows the priority "contract agreement -> published price information (government guidance prices) from the cost administration agency -> market price", taking prices of the report compilation period (Clause 7.4.2). Where dayworks has no applicable unit rate, determine it per GB/T 50500-2024 Clause 8.6.3 using tax-exclusive published price information (government guidance prices) or purchase unit prices confirmed by both parties; the railway industry, per TB 10801-2024 Section 3.1, lists labour cost by comprehensive labour unit rate and carries the compilation-period-to-base-period difference as a labour cost differential. The all-in unit rate excludes VAT.
- ←
Determining settlement quantities when drawings disagree with actual site dimensions: characterize first (variation / unauthorized work / measure-as-executed), then quantify
Where drawings and site dimensions disagree, one must not uniformly settle "per drawings" or "per actuals" — characterize first: employer changes baselines/levels/positions/dimensions -> variation, measured per the revised drawings (lump-sum contracts measure only the confirmed variation portion; unit-rate contracts re-measure per the final construction drawings); contractor builds not per drawings without authorization -> quantities beyond the drawings are not measured and no site instruction or variation record may be issued for them; design explicitly requires site verification -> a site instruction / variation record confirms per actuals. In disputes referred for construction cost expert assessment, determination follows the five-tier progression: valid confirmation signed by both parties -> one-party confirmation (no rebuttal) -> re-check or site inspection -> inspection measurement -> if still undeterminable, no measurement with explanation.
- ←
Linking the five document types — contract, drawings, BOQ, site instructions / variation records, settlement — and managing the settlement chain of evidence
Using unified codes as the bond, lineage relations attached via linking fields, on-the-spot linkage in the workflow, and a basis for settlement ledger as the master index, build contract, drawings, BOQ, site instructions / variation records, and settlement into a traceable chain of evidence: every settlement amount must be able to state which contract clause it relies on, which BOQ item it corresponds to, which drawing it comes from, and which site instruction / variation record triggered it; only when the four elements are complete and certification and sign-off are complete is it included in settlement.
- ←
Overview of material price adjustment in construction works: applicable conditions, base price (reference price for adjustment), risk band, and calculation methods (GB/T 50500-2024 Sections 3.3/8.7 and Appendices A, G)
Four indispensable elements of material price adjustment: ① adjustable scope (only labour cost, principal material cost, and construction machinery fuel and power cost, listed per Appendix G.2 Tables G.2.1-1/2 as a contract annex); ② base price (reference price for adjustment) C₀ (the market price level 28 days before the tender deadline (= FIDIC Base Date), or for non-tendered works 28 days before contract signing); ③ risk band r (contractual agreement takes precedence, in practice 3%–5%; where absent or unclear, a cost fluctuation beyond 5% triggers); ④ quantities subject to price adjustment Q (per the contract's agreed rules). Trigger |Ci−C₀|/C₀>r; upward unit price for the excess beyond the band = Ci−C₀(1+r), downward = C₀(1−r)−Ci; price difference = Σ unit price for the excess beyond the band × Q, carrying value added tax (VAT) only, with no management fee or profit.
- ←
Settlement review vs fiscal appraisal vs audit: subject, nature, object, and effect
The final account is a civil-contract act of employer and contractor (checking and confirming the final account documents); fiscal appraisal is the finance department's administrative supervision of fiscally invested funds; audit is the audit institution's statutory audit supervision of government-invested projects under the Audit Law. Fiscal appraisal and audit conclusions in principle do not affect the validity of the employer-contractor contract, unless the contract expressly makes them the settlement basis.
- ←
Pricing rules for cross-region material procurement: purchase-origin price + freight compose the delivered price; adjustment per contract and the price-confirmation procedure
Budget compilation does not force a binary "project location vs purchase location": material budget price = (material original price + freight within price) x (1 + procurement-and-keeping rate), the purchase-origin price serving as the original price and freight reflecting the inter-region difference; multi-source procurement is weighted by supply share. Settlement adjustment follows the contract first; absent agreement, the base price is the published price information (government guidance prices) for the project location or the mutually confirmed price 28 days before the bid deadline, the benefit of regional price differences accrues to the contractor, and prices must be submitted to the employer for confirmation before purchase — silence is deemed acceptance.
- ←
Six-step cleaning of historical cost data and three cost-forecasting paths (price-source classification / four-dimension tagging / index adjustment)
Historical cost data cannot be used directly for forecasting: first apply six-step cleaning (source classification, completeness and deduplication, outlier handling, caliber normalization, four-dimension tagging, average-level adjustment), then choose a forecasting path — the consumption-indicator + current-price method is the most stable; the index-adjustment method uses base date 2017-01-01 with index 1000; use the analogy method when samples are insufficient; mixing market prices/published prices/vendor quotations, different cost types, or different regions is strictly forbidden.
- ←
Price adjustment for wires and cables: itemized by full specification, copper-linkage agreements, and handling missing published price information (government guidance prices) (GB/T 50500-2024 Appendix A.2)
Cable price adjustment shares the same mechanism as steel (GB/T 50500-2024 Appendix A.2 adjustment based on published price information (government guidance prices)): difference = SUM[(Ci - C0 x (1 +/- r)) x Q], only the portion exceeding the risk band is adjusted on an actual basis; r as agreed takes precedence, and if not agreed, fluctuation beyond 5% is adjustable (8.7.2); C0 = market price 28 days before the tender deadline (= FIDIC Base Date) (for non-tendered projects: 28 days before contract signing); the difference carries value added tax (VAT) only, no management fee or profit. Cables must be listed item by item in Table G.2.1-1 by full specification (voltage class x cores x cross-section x armor x flame-retardance) and adjusted separately — merging and averaging is strictly prohibited; the copper-linkage method must fix in the contract the copper content/conversion coefficient and the copper-price source; for missing published price information, the paths are employer's approval of material prices / market price enquiry, with symmetric unit bases.
- ←
Handling rules when the price-information issue and the construction month are misaligned (GB/T 50500-2024 Appendix A adjustment)
Price-information adjustment takes the issue corresponding to the measurement period (the month of completion), not the publication time; where the current issue is unpublished, provisionally use the nearest published issue and refund or supplement the difference later per actual prices (A.2.2); a measurement period spanning multiple issues uses the arithmetic mean / weighted mean / price of the main-consumption period (A.2.3); the base price C0 is locked 28 days before the bid submission deadline and does not drift with construction (A.2.1, A.2.4).
- ←
Building a material published-price-information vs actual purchase-price comparison table: four-segment table structure, deviation analysis, and the four-party certification and sign-off process
The comparison table = base segment (name/specification precise to the grade, unit, work location and period) + price segment (published price information stating the issuing agency, period, and tax-inclusive/delivered basis; purchase price on the same basis, side by side) + analysis segment (deviation rate = (purchase price − published price information)/published price information × 100%, each deviation explained and checked against the contract risk band) + signature segment (applicant/supervision/employer signatures and seals). Based on the GB/T 51095-2015 Appendix E.0.4 enquiry (price verification) form, extended with "published price information (agency + period)" and "deviation rate" columns; process: ≥ 3 enquiries → comparison → supervision price verification → employer confirmation before purchase (failure to reply within the time limit deemed acceptance) → contract at the approved price → archive into the price library. The signed and sealed comparison table is the certified record of agreed material prices — a basis for preparing the settlement.
- ←
Establishing material sample-sealing and quality-and-price confirmation ledgers in decoration projects: samples govern quality, confirmed prices govern price, ledgers keep traceability
Sample-sealing governs quality, price confirmation governs price, ledgers keep traceability — a trinity: the sample-sealing ledger scopes per GB 50210-2018 Clause 3.3.8 + GB/T 50500-2024 Clause 3.7.2, with four-party confirmation, three-party sealing, and entry-comparison traceability; the price-confirmation ledger completes signing per the DB37/T 5096-2017 inquiry-pricing procedure before procurement — after-the-fact supplementary signing carries weak evidentiary weight in construction cost expert assessment (judicial appraisal) (GB/T 51262-2017 Clause 5.6.4); the two ledgers merge into one material control master ledger; provisional-sum material replacement adjusts the material cost only, with VAT counted separately (GB/T 50500-2024 Clauses 8.4.5/8.4.6).
- ←
Steel price adjustment calculation: price-information adjustment formula, per-specification per-period threshold checks with adjustment on actual basis, and tax treatment (GB/T 50500-2024 Appendix A.2)
Steel price adjustment uses the price-information adjustment method (GB/T 50500-2024 Appendix A.2): △P = Σ[(Ci − C0·(1±r)) × Q] × (1 + VAT rate), adjusting only the portion beyond the risk band on an actual basis; the agreed risk band prevails, with the beyond-5% fallback where not agreed or unclear (8.7.2). Each specification must be checked independently each period for exceeding the risk band (base prices, published price information, and increase rates differ; specifications within the risk band are not adjusted for the period); the price difference carries VAT only, no management fee or profit (3.3.5); when checking adjustment tables, first look at whether the bid price is above or below the base price (A.2.4 determines the excess-calculation base).
- ←
Tender pricing strategy: market price enquiry as the primary basis with published price information as auxiliary cross-validation — bidders price independently and are not compelled to use published price information
Tender pricing takes market price enquiry as primary and published price information as auxiliary cross-validation: GB/T 50500-2024 Clauses 6.1.1/6.2.1 require bidders to price independently per their own conditions; published price information (a reference price) has no mandatory binding force at the tendering stage; the cost floor and competitiveness can only be measured by actual enquiries — published price information is used to check abnormal enquiry results, supplement references for rare materials, and support explanations when comparing with the tender price ceiling; provisional sums and employer-supplied/specified brands follow the tender documents; enquiries must unify the basis of pricing and keep records.
- ←
Which period's published price applies to settlement material prices: the two-date system — base price locked at the contract base date (28 days before bid closing) plus period-by-period pricing per measurement cycle (GB/T 50500-2024 Annex A.2 price-information method)
Settlement material prices are not taken from a single period (completion date or submission date) but from the "base price locked at the contract base date + current prices per measurement cycle" two-date system: base C0 at 28 days before bid closing (non-tendered: 28 days before contract signing); current Ci per measurement cycle from the cost authority's published price information (or jointly confirmed market prices, or same-period trading-center award prices); differences beyond the contractual risk band are computed per cycle and totalled into the final account; with no band agreed, a 5% fluctuation triggers adjustment; express contracts govern.
- ←
Alternative adjustment paths when price information lacks the specification: mutually confirmed price / purchase price / awarded-bid price fallbacks + the same-caliber red line for C0 and Ci (GB/T 50500-2024 Appendix A.2)
Price information is only one of the Ci sources listed in A.2.1; lacking the specification does not mean adjustment is impossible: determine Ci per (1) contract agreement, (2) the market price of the measurement period confirmed by both parties, (3) the purchase price determined by the employer (submitted before purchase; deemed accepted upon overdue silence), (4) the awarded bid price of the trading center for similar works under similar conditions in the same period; C0 takes prices by the same rules; where information is temporarily missing, provisionally account per the published price and settle later. Red lines: C0 and Ci must be of the same caliber; the alternative price must represent the market price level of the measurement period; keep a full trail of certified records of agreed material prices.
- ←
Market-inquiry pricing when no applicable quota exists: the two-step method (multi-source inquiry → labor/material/machinery pricing) and traceability/audit requirements
A missing quota does not mean missing pricing rules: the all-in unit rate structure (labor/materials/machinery + management fee + profit + statutory fees + taxes) stays unchanged, with labor/material/machinery prices obtained instead from multi-channel market inquiries (online platforms / telephone / site visits / similar-project benchmarks), and consumption referenced from similar quotas with correction, manufacturer technical parameters, or field measurement. Inquiries must be multi-source and benchmarked, consistent with design parameters, and must not directly pick published prices; records are countersigned and a ledger kept; fees still accrue per the fee standards. The priority of price bases is contract agreement > price confirmed by both parties > published price > market inquiry — inquiry-based pricing is the last resort and requires employer / auditor acceptance with traceability (inquiry-verification report, preparation notes, all-in unit rate analysis sheets).
- ←
Guidance price vs market price: definition sources, essential difference and role positioning (official term definitions + three-channel classification rule)
The guidance price (construction cost information) is the labor/material/plant-shift price information plus cost indices and indicators periodically published by cost management agencies — a reference, guidance price (GB/T 50875-2013 clause 2.1.16); the market price is the actually transacted price, acquired mainly through transactions. The two differ essentially; per T/ZBD 100.1-2022 clause 7.2.3 they must be developed as data under the three channels market/guidance/vendor-quotation prices, strictly never mixed. Guidance prices serve maximum bid prices, adjustment base prices and dispute fallbacks; market prices serve actual procurement cost verification, filling gaps of materials without guidance prices, and — after joint confirmation — as settlement bases.
- ←
Avoiding mispricing when material names are similar but specifications differ: three lines of specification-checking defense across preparation, pricing, and audit
The three forms of mispricing (specifications missing from item characteristics, near-name mismatches, missing specification/unit dimensions) can be intercepted by three lines of defense: at preparation, write full specifications and models into the item characteristics (GB/T 50500-2024 Clause 4.2.2); at pricing, check the quota item's bracketed specification against the drawings + match material price on three fields simultaneously — name/specification/unit (do not pick the published price directly; mark conversions with "换"); at audit, use same-name specification gradients (C30>C25, DN32>DN25) to back-detect mismatches.
- ←
Recording quantities for site instructions and certified records: a three-stage closed-loop procedure, recording elements, and daywork daily reporting requirements
Quantity recording for site instructions and certified records follows the three-stage closed loop of "pre-work survey -> in-process measurement -> post-completion acceptance": before implementation, survey and record original conditions as the increment baseline; when occurring, measure and record promptly and preserve imagery; after completion, accept and confirm actual quantities. Each certified record must contain position, dimensions, quantity, materials, and a logically clear calculation formula; dayworks report daily details of personnel/materials/machinery and submit a daily summary after continuing work ends; certified records are archived one-to-one with original records, imagery, and acceptance proof.
- ←
Price-taking time point for the tender price ceiling: the latest issue of price information published as at the date of completion of preparation; "28 days before the tender deadline" is the adjustment base price time point, not the price-taking time point
The tender price ceiling (employer's maximum acceptable price) takes prices at the price level of the preparation period: use the latest issue (month/quarter) of construction cost price information published as at the date of completion of preparation, noting the issue in the deliverable; where a difference from actual construction-period conditions exists, adjust reasonably (GB/T 50500-2024 Clause 5.2.9). "28 days before the tender deadline" (for works not subject to tendering, 28 days before the date of contract signing) is the lock-in time point for the contractual adjustment base price C₀ in Appendix A.2.1, used for adjustment for cost fluctuation after award, and is unrelated to price-taking for the tender price ceiling.
- ←
Selecting the contract pricing form when material prices fluctuate sharply: the hybrid mode of fixed unit rate + price adjustment clauses
With sharp fluctuations, neither a pure fixed price (quotes carry risk premiums, disputes brew) nor cost-plus (cost out of control) fits; choose "fixed unit rate + adjustable-price clauses": base price (28 days before the tender deadline, i.e. the FIDIC Base Date) + risk band (no-adjustment tolerance; beyond 5% triggers adjustment absent agreement) + adjustment method (index-based formula adjustment / adjustment based on published price information) written into the contract; price differences carry value added tax (VAT) only, no management fee or profit. Contract prices have only three statutory forms: fixed, adjustable, and cost-plus (Construction Ministry Order No. 107, Article 12).
- ←
Basic content elements of site instruction / variation record documents: main-text checklist, attachment requirements, and sign-off formalities
Grasp the content of a site instruction / variation record along three dimensions: "main-text elements + supporting attachments + sign-off formalities". DB37/T 5028-2022 Clause 6.3.3 gives the most complete nine-item checklist (cause of the instruction; date of occurrence/completion; submission date; location, dimensions, quantity, and materials, with a logically clear calculation formula; execution basis; brief description of the fact and completion status; explanatory drawings and photos; review opinions of the supervision agency and the construction employer; signatures and seals of the contractor's handling person and project manager). T/CAEC 006-2024 distinguishes the content and attachments of quantity instructions from those of price instructions; a price instruction is valid only after joint sign-off (countersignature) by the construction employer, contractor, and supervision unit. Quantity calculation formulas, correspondence with original vouchers, a complete signature chain, and all three dates present are the gaps most easily attacked in final account review.
- ←
Pricing rules for materials without published price information: market price enquiry + pre-purchase price approval + order of determination in dispute appraisal
Materials without published price information are priced by market price enquiry: enquire with no fewer than 3 suppliers, compare, and take a representative price; submit to the employer for approval of the material price before purchase (silence within the agreed period constitutes deemed acceptance) and keep a ledger for the record; awarded contract prices for similar works in the same period, market prices adopted in the tender price ceiling, and industry price information may serve for cross-validation; in dispute appraisal, prices are determined in the order approved-and-signed price > contractually agreed price > mutually agreed price. Market prices, published price information, and manufacturer quotations must be used by classification and strictly never mixed.
- ←
Document verification in subcontract final account disputes: a five-tier order of evidentiary weight (contract sets the tone → certification and sign-off lock quantities → drawings verify quantities → price evidence verifies prices → supporting evidence validates)
Documents in subcontract final account disputes are checked in tiers of evidentiary weight: (1) contract-type documents set the tone (subcontract and supplementary agreements, tender documents, pricing bases — establish the pricing benchmark first); (2) mutually certified and signed documents lock quantities (certified measurement of the works results, interim settlement by construction stage documents, interim payment certificates, site instructions / variation records, dayworks confirmations, free-issue materials requisition/return records — certification and sign-off locks); (3) drawing/technical documents verify quantities (construction drawings, approved variation drawings — works beyond them are not measured); (4) price evidence verifies prices (material price approval records, purchase contracts and invoices, published price information (government guidance prices)); (5) supporting/procedural evidence validates (meeting minutes, photographs, acceptance records, supervisor logs). Order of weight: contract agreement > mutual certification and sign-off > unilateral declaration.
- ←
Order of applicable bases for material price adjustment: contract agreement prevails, pricing standard as fallback (GB/T 50500-2024 "agreement governs" and the 5% band rule)
Material price adjustment follows the contract agreement first (agreement governs, clause 1.0.3): adjustable material scope, base price, risk band, quantity calculation, price-information source and adjustment period all follow the contract, completing appendix G table G.2.1 as a contract annex; where the contract fixes no band or unclearly, fluctuation beyond 5% may be adjusted per appendix A (clause 8.7.2 fallback); the contract may neither violate mandatory laws and regulations nor depart from the substantive content of the tender documents (law prevails; clause 3.4.4); the price difference carries VAT only, no management fee or profit.
- ←
Site instructions and certified records overview: applicable matters and prohibited items, the five-node handling procedure, graded signing authority, the 2024 standard basis and settlement application
Certification runs a five-node closed loop: assess reasonableness beforehand and survey the original conditions → at occurrence, measure on site, keep photos, have all parties sign the original vouchers → submit the certification file within the contract-agreed time → the supervising engineer reviews, the chief supervising engineer signs, the employer approves → participate in acceptance, confirm the completed content and compute the final cost. Signature authority: written documents signed by both parties' site management within their scope of duty are valid pricing vouchers (GB/T 50500-2024 cl. 12.2.1); the supervisor certifies facts strongly but prices weakly — priced certifications need the joint sign-off of employer, contractor and supervisor (T/CAEC 006-2024 cl. 7.2.9); a one-party signature binds only the signing party. With the 2024 code dropping the site-certification clause, off-contract work flows through three channels — variation, additional works and dayworks — and dayworks certification reports not verified in time are deemed accepted (cl. 7.5.5).
- ←
Price fallback paths when the project location lacks published price information for a material: contractual agreement → alternative channels → market price enquiry → employer's approval of material prices → expert assessment backstop
Missing published price information is backfilled in steps: ① contractual agreement takes precedence; ② alternative channels (price information issued by cost-administration departments or industry bodies, and the detailed price composition of analogous billed (BOQ) items; railway compilation-period prices are determined by the design unit through investigation and analysis); ③ market price enquiry (three classified channels — market price / published price information / vendor quotations — dominated by real transaction prices, strictly not mixed, with a documented audit trail); ④ report to the employer for approval of material prices before procurement; failure to reply within the time limit is deemed approval (GB/T 50500-2024, Appendix A.2.5); for materials covered by a provisional sum, once confirmed by the employer the pre-tax price is substituted (8.4.5); ⑤ in dispute, construction cost expert assessment (judicial appraisal) follows signed-and-approved price > contract-agreed price > mutually agreed price (GB/T 51262-2017, Clause 5.6.4). Completing the price approval procedure before procurement is the key to success at settlement.
- ←
Whether actual purchase quantities can directly serve as the material adjustment quantity: triple filtering of contract agreement + employer confirmation + not exceeding rational consumption (GB/T 50500-2024)
The purchase quantity cannot directly serve as the adjustment quantity Q; it must pass triple filtering: (1) the contract/special clauses expressly agree the purchase-quantity caliber (A.2.1, Note 2 of Table G.2.1-1); (2) submission to the employer for verification and confirmation before purchase, deemed accepted upon overdue silence, batch purchases averaged by weight (A.2.5); (3) capped by the rational consumption of works completed in the period — the excess is borne by the contractor per 3.6.3, and the appraisal caliber is "actual consumption = requisition quantity − inventory" (T/ZBD 100.4-2023 Clause 4.5.7). Safest: currently measured quantities × quota consumption (including loss).
- ←
Price-taking rules when one material has multiple published prices / original prices: weighted average by supply quantity at compilation, three agreed methods at adjustment, unified caliber
When one material has multiple prices, take prices by scenario: at compilation, original prices from multiple origins/supply channels are determined by weighted average per supply proportions (TB 10811-2024 Clause 2.2.1 — neither the high nor the low); at adjustment, multiple market prices within the same measurement period use one of the three contractually agreed methods and its priority — arithmetic mean, weighted mean with completed quantities, or the price of the main-consumption construction period (GB/T 50500-2024 Appendix A.2.3); for multi-agency publications with no agreement, follow the caliber of the agency at the project location; before taking prices, unify the tax-inclusive/exclusive, delivered/ex-factory, and specification-grade calibers; market prices, published prices, and manufacturer quotations are used by classified channels and strictly never mixed.
- ←
Validity of "settlement per government audit results" clauses in government-invested projects, and drafting guardrails (deadlines / pricing basis / re-review / payment segregation)
The audit clause itself is valid: government fiscal review of project cost does not affect contract validity (SPC [2008] Min-Yi-Ta-Zi No. 4), and Regulation on Payment to SMEs Article 11's "unless otherwise agreed by contract" endorses voluntarily included audit clauses. But a "bare clause" (just "per audit") is risky for the contractor; a sound clause needs four guardrails: (1) a fixed audit deadline, overdue = acceptance of the submitted settlement; (2) locked pricing basis—audit must not alter the contract's pricing method or all-in unit rates; (3) objection to reductions reviewable by a third party; (4) audit binds only the final account balance, not progress payments.
- ←
Definition, classification hierarchy, and bases for handling the final account for construction works (GB/T 50500-2024)
The final account is the total-price settlement handled by the employer and contractor in accordance with the contract after the works pass taking-over (completion acceptance), and is the aggregation of interim settlements by construction stage (China's 2020-introduced staged settlement system, with no exact international equivalent); it is composed level by level from unit works -> single works -> project final account. Unless otherwise agreed in the contract, the amounts in the interim settlement by construction stage shall serve as the basis for the final account; the basis for settlement comprises five categories — contract documents; as-built drawings and variation documents; technical data and material-substitution approvals; pricing documents and bills of quantities (BOQs); and mutually confirmed site instructions / variation records and claim documents.
- ←
Rules for determining the quantity (Q) of materials subject to price adjustment: contractual agreement takes precedence, and key points on matching the quantity basis and the period (GB/T 50500-2024)
There is no unified statutory formula for the adjustable-factor quantity Q; it is determined by the calculation method agreed by the employer and contractor in the contract (Appendix A.2.1 + Note 2 of Table G.2.1-1), and must be detailed and clarified in the tender documents / contract special clauses. In practice, the most common basis is "quantities measured for the current period x material consumption under quota norms (prescribed resource consumption standards)/mix ratio (including wastage)", or the purchase quantities confirmed by the employer (A.2.5). Q must correspond to the basis of the price adjustment period and to the price Ci for the measurement period; where the contract is silent, the standard provides no fallback determination and disputes easily arise.
- ←
Framework of causes for the gap between quota norms and actual market construction costs: social-average vs contractor-specific levels, base-period vs market prices, six source dimensions, and practical responses
Quota norms are a pricing benchmark compiled under normal construction conditions, social-average consumption levels, and base-period prices — not a mirror of a contractor's actual cost. The gap is normal, not anomalous, and arises from six dimensions: social-average vs contractor-specific levels; base-period price vs market price (bridged by adjustment for price differentials); normal conditions vs actual working conditions; generous vs actual measured quantities (wastage-rate/margin differences); mechanisation and organisation level; and market competition and supply-demand. Profit margin = quota norm price − contractor's actual cost; settlement allows no reimbursement at actuals — follow the contract's clauses on price differentials / published price information (government guidance prices).
- ←
Price reference time point for final account: adjust period by period per each measurement period's published price information (government guidance prices) during construction and aggregate; interim settlements by construction stage (China's 2020 milestone-based interim settlement system; no exact international equivalent) are incorporated without recomputation (not a single issue at the month of completion)
A final account has no 'single settlement-period price information': contractual agreement takes precedence; where adjustment is agreed, base price C0 locks the price for the period 28 days before the tender deadline (= FIDIC Base Date) (for non-tendered works, 28 days before contract signing), while measurement-period price Ci is taken period by period using the published price information (government guidance prices) issued for the corresponding construction completion period (month/quarter), adjusted and accumulated period by period; confirmed interim settlements by construction stage are incorporated directly into the final account without re-measurement or re-pricing; where the published price information for a given period has not been issued, that period's published prices may be used provisionally, with subsequent payments adjusted on an actual basis.
- ←
Rules for determining the construction-period price (measurement-period market price Ci) in material adjustment (GB/T 50500-2024 appendix A.2)
The construction-period price is the measurement-period market price Ci in the adjustment formula — the same three source options as the base price C0 (market price confirmed by both parties / the cost agency's current guidance price / same-period analogous winning-bid prices at the trading center) and must represent the current price level of the measurement period; multiple prices within a period take the arithmetic mean, the quantity-weighted average against completed quantities, or the price for the main-usage period, the order agreed by the parties; absent price information, adjust provisionally by the guidance price and true up later; the procurement-price method requires reporting to the employer for confirmation before purchase, non-response within the agreed time deemed acceptance; on schedule delay, take the higher of the planned and actual progress-date prices where the employer is at fault, the lower where the contractor is.
- ←
Provisional sums at final account: settlement line item, replacement paths, VAT basis and review essentials (GB/T 50500-2024)
At final account, provisional sums are dealt with as "the actually determined price replaces the provisional price, with the contract price adjusted by the difference": PC sums for materials (pre-tax) are replaced by the pre-tax winning bid price or by the pre-tax price from an inquiry/self-quotation confirmed by the employer, adjusting only the PC sum item for materials within the all-in unit rate, with all other cost elements unchanged; provisional sums for nominated specialist subcontract works (tax-inclusive) are replaced in their entirety by the winning tax-inclusive subcontract price. These enter settlement line item 4, "adjustment of provisional prices after procurement"; provisional sums for nominated specialist subcontract works do not enter the VAT calculation base; the core vouchers are the price-confirmation sheet (employer's approval of material prices) / letter of acceptance confirmed by both parties.
- ←
Order of application of pricing bases for the final account: contract agreement first (agreed terms prevail); quota norms and construction cost management agency's pricing bases as fallback
Final account prices take the contract as the fundamental basis: pricing activities follow "statutory priority, agreed terms prevail" (GB/T 50500-2024 Clause 1.0.3) — where the contract provides for price determination, adjustment methods, and quantity calculation rules, the agreed terms prevail; only absent or unclear agreement are national, industry, and local pricing bases (including quota norms) referenced (T/ZBD 100.5-2023 Clause 1.4.2). In construction cost expert assessment (judicial appraisal) of price disputes, the fallback order is fair market price → pricing quota norms → cost data + on-cost level (T/ZBD 100.4-2023 Clause 3.1.6).
- ←
Handling paths when published price information clearly deviates from actual market prices: unify the bases of comparison first to exclude illusions, then correct by scenario (temporary adjustment with later true-up / price certification / expert assessment as fallback)
Published price information is only a reference guide price issued by the cost management agency (GB/T 50875-2013 Clause 2.1.16), not a mandatory price. On deviation, first unify the bases of comparison — VAT-inclusive/exclusive, delivered/ex-works, specification and unit — to exclude illusions; where an adjustment dispute is significant, temporarily use the current published price information and true up later against actual market prices, refunding the excess or paying the shortfall (GB/T 50500-2024 Appendix A.2.2); absent agreement or where the agreement is unclear, substitute the price confirmed by mutual market price enquiry and certify the price before purchase (deemed approval upon lapse of the response period, A.2.5); construction cost expert assessment ranks the certified-and-approved price > contract-agreed price > mutually agreed price (GB/T 51262-2017 Clause 5.6.4). Enquiries from >= 3 suppliers with records in a register; adjust only beyond the agreed risk band (5% if not agreed).
- ←
Price adjustment rules for brand changes of decoration materials: three situations, adjusting the material cost only, and the certification of material quality and price procedure
Brand-change price adjustment = replace the original price with the confirmed pre-tax price → adjust the material cost only (other costs unchanged) → VAT counted separately. Provisional-sum materials are replaced by tender/market price enquiry prices; non-provisional-sum (contract-agreed brand) materials must undergo the employer's certification of material quality and price before procurement — unconfirmed prices are not adjusted; under the railway system the price differential is computed as norm resource consumption x the difference between preparation-period and base-period prices.
- ←
Identifying fabricated and duplicate labour attendance records: a four-layer method — field checks → cross-verification → duplicate screening → statistical screening
Core principle: "a single record is untrustworthy; only cross-verification is valid": first run field-level checks to scan fake records, then cross-verify along four lines — quantities, construction/supervision logs, real-name attendance and payroll, and safety-education/briefing signature sheets; use a person × date pivot to find duplicates across crews/periods/dayworks/contracts on the same day; finally use statistical indicators to circumscribe anomalies. Certified dayworks records count only actual work content, excluding the contractor's on-site management personnel and machinery already on site.
- ←
Overview of the full-chain use rules for construction cost published price information: nature, price calibers, stage-by-stage pricing, and frequent misconceptions
Published price information means reference guide prices issued by cost management agencies, running through the whole chain "price-limit compilation - bid verification - adjustment base - settlement fallback". Five iron rules: contract agreement first; caliber unification (tax-inclusive/exclusive, delivered/ex-factory, procurement-keeping fee); period alignment (base price locked 28 days before the bid deadline, measurement price matched to the measurement period); adjust only beyond band (±5% if not agreed); confirmation with records (submit to the employer before purchase, silence deemed acceptance).